IDOT contract 66N23 bid tabulation

Section (112)CR-2548. Let by Illinois DOT on July 31, 2026, Livingston, District 03. 3 bids received; low bid $615,314 by Riber Construction, Inc..

Owner
Illinois DOT
Letting
31 JUL 2026
Pay items
79
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Riber Construction, Inc.$615,314Low
2Tobey's Construction & Cartage, Inc.$643,347+5.0%
3Phoenix Corporation of the Quad Cities$745,216+21%
IDOT contract 66N23: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Riber Construction, Inc.2. Tobey's Construction & Cartage, Inc.3. Phoenix Corporation of the Quad Cities
1Explor trench SPL (X2130010)LF200$0.01$22.00$20.00
2Temp access- FLD ent (X4024000)EACH1$0.01$2,125.00$1,500.00
3HMA stab 6IN at SPBGR (X4062952)SY192$98.00$105.00$60.00
4Memb WTRPRF sys B STR (X5810103)SY65$50.00$46.50$90.00
5Linear delin panels 4 (X6350204)EACH4$55.00$152.20$150.00
6Temp info signing (X7200061)SF42$30.00$38.00$34.00
7Construction layout (Z0013798)LS1$10,000$5,000.00$10,000
8Rock fill (Z0054400)CY23$175.00$200.00$75.00
9Temp pavement (Z0062456)SY229$109.00$137.00$100.00
10Earth excavation (20200100)CY193$53.00$52.00$75.00
11Furnished excavation (20400800)CY125$0.01$55.00$50.00
12Porous gran embank (20700220)CY13$250.00$157.00$120.00
13Seeding CL 2A (25000210)ACRE0.50$4,000.00$5,425.00$12,000
14Nitrogen fert nutr (25000400)LB33$10.00$1.00$5.00
15Phosphorus fert nutr (25000500)LB33$10.00$1.00$5.00
16Potassium fert nutr (25000600)LB33$10.00$1.00$5.00
17Erosion contr blanket (25100630)SY1,740$1.50$2.50$1.60
18Temp eros contr seed (28000250)LB108$7.50$1.00$7.00
19Temp ditch checks (28000305)LF72$14.00$10.00$22.00
20Perimeter eros bar (28000400)LF728$2.20$2.75$10.00
21Inlet & pipe protect (28000500)EACH2$140.00$100.00$300.00
22Stone riprap CL A4 (28100107)SY26$120.00$175.00$125.00
23Filter fabric (28200200)SY26$4.00$1.50$15.00
24Sub gran mat B 4 (31101200)SY329$6.40$22.25$42.00
25HMA base cse 5 3/4 (35501307)SY96$74.00$67.00$155.00
26Agg surf cse B (40200900)CY42$88.00$70.00$125.00
27Bit matls tack CT (40600290)LB838$0.01$0.01$1.00
28Long joint sealant (40600370)LF370$2.20$2.20$25.00
29HMA surf rem butt JT (40600982)SY214$23.00$20.00$15.00
30Temporary ramp (40600990)SY54$0.01$0.01$15.00
31HMA BC IL-19.0 N50 (40603080)TON125$242.00$218.00$225.00
32HMA SC IL-9.5 C N50 (40604050)TON101$282.00$254.00$270.00
33Pavement rem (44000100)SY326$35.00$30.00$40.00
34HMA surf rem 2 3/4 (44000160)SY909$23.00$20.00$11.00
35Paved SHLD removal (44004250)SY305$52.00$30.00$25.00
36Aggregate SHLDS B 6 (48101500)SY70$37.00$30.00$80.00
37HMA shoulders 8 (48203029)SY575$121.00$115.00$98.00
38Rem exist struct (50100100)EACH1$35,250$36,000$40,000
39Reinforcement bars (50800105)LB7,030$3.00$2.95$7.00
40Bar splicers (50800515)EACH44$46.00$59.50$150.00
41Name plates (51500100)EACH1$920.00$900.00$2,000.00
42Temp soil reten systm (52200020)SF59$447.00$315.00$500.00
43Conc box cul (54003000)CY38.70$2,000.00$2,350.00$2,400.00
44Geocomposite wall DR (59100100)SY65$25.00$39.00$45.00
45Inlets adjust (60260100)EACH2$0.01$400.00$1,500.00
46Misc concrete (61100605)CY10$0.01$700.00$1,600.00
47Storm sew prot A 12 (61101013)LF50$0.01$72.00$100.00
48Storm sew prot A 15 (61101017)LF50$0.01$78.00$118.00
49FLD tile jun vault 2D (61133100)EACH2$0.01$1,380.00$2,500.00
50Storm sewer spec 12 (61140200)LF50$0.01$60.00$80.00
51Storm sewer spec 15 (61140400)LF50$0.01$66.00$90.00
52SPBGR TY A 6FT posts (63000001)LF187.50$50.40$50.40$50.40
53LSG OV cul 12'6" span (63000350)LF100$64.40$64.40$64.40
54TR bar TRM T1 SPL tan (63100167)EACH4$4,705.00$4,705.00$4,705.00
55Guardrail remov (63200310)LF334$6.00$7.00$10.00
56Engr field office A (67000400)CAL MO4$3,000.00$3,000.00$2,800.00
57Mobilization (67100100)LS1$32,300$37,750$38,000
58Traf cont-prot 701321 (70100405)EACH1$16,345$7,850.00$22,650
59Traf cont-prot 701201 (70100450)LS1$100.00$100.00$1.00
60Traf cont-prot 701326 (70100500)LS1$100.00$100.00$1.00
61Temp BR traf signals (70106500)EACH1$10,505$12,250$11,000
62Temp rumble strips (70106700)EACH12$1,200.00$880.00$500.00
63Short term pavt mking (70300100)LF189$0.01$2.00$1.00
64SHRT TRM pavt MK rem (70300150)SF63$0.01$8.00$1.00
65Temp conc barrier (70400100)LF250$37.00$44.00$40.00
66Pin temp conc barrier (70400125)EACH216$0.01$23.00$55.00
67Rel temp conc barrier (70400200)LF250$25.00$12.50$15.00
68Imp attn temp NRD TL3 (70600250)EACH2$4,000.00$3,500.00$3,500.00
69Imp attn rel NRD TL3 (70600350)EACH2$3,000.00$800.00$700.00
70Rem & rel sign panel T1 (72400735)SF9$55.00$38.00$60.00
71Terminal marker - DA (72501000)EACH4$50.00$50.00$50.00
72Wood sin support (73000100)LF17$25.00$25.00$45.00
73Paint PVT MK line 4 (78001110)LF2,504$1.36$1.36$2.80
74Paint PVT MK line 6 (78001130)LF313$2.05$2.05$5.00
75Raised refl pavt MKR (78100100)EACH8$477.00$477.00$610.00
76Grdrail ref type A (78200005)EACH8$10.00$10.00$10.00
77Barr wall ref type C (78200011)EACH8$15.00$12.84$10.00
78Raised ref PVT MK rem (78300200)EACH8$10.00$8.01$75.00
79PVT MKG rem grinding (78300201)SF392$8.00$12.00$2.00
IDOT contract 66N23: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of July 31, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way