Riber Construction, Inc.: IDOT bid record

Riber Construction, Inc. submitted 37 bids on Illinois DOT contracts in the data, from 15 JAN 2021 to 31 JUL 2026, and was the low bidder on 18 of them (49%). When it was not low, its total sat a median +9.0% above the low bid.

Owner
Illinois DOT
Low bid volume
$14,096,667
Latest bid
31 JUL 2026
Data through
18 SEP 2026
37Bids
18Low bids
49Win rate, percent
+9.0%Median gap to the low bid when not low, 19 bids

By year

YearBidsLow bidsWin rate
202111655%
20224375%
20235240%
20246350%
20254125%
20267343%
Riber Construction, Inc., IDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
District 03341853%
District 04200%
District 01100%
Riber Construction, Inc., IDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Bit matls tack CT40600290LB2423 (96%)$0.01$0.01
Terminal marker - DA72501000EACH2619 (73%)$42.50$47.85
Driving piles51202305LF2018 (90%)$0.01$0.10
Bit matls PR CT40600275LB1917 (89%)$0.01$0.01
TR bar TRM T1 SPL tan63100167EACH2016 (80%)$3,657.50$3,800.00
Reinf bars, epoxy CTD50800205LB3015 (50%)$2.05$2.50
Name plates51500100EACH2813 (46%)$500.00$773.24
Conc struct50300225CY2413 (54%)$1,112.50$1,260.00
Guardrail remov63200310LF1512 (80%)$6.00$8.00
Seeding CL 2 SPLX2501000ACRE1512 (80%)$10,000$9,000.00
Stone riprap CL A428100107SY2010 (50%)$73.50$95.00
Perimeter eros bar28000400LF1410 (71%)$2.48$3.50
Riber Construction, Inc., IDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

Riber Construction, Inc., IDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
31 JUL 202666N23District 03Section (112)CR-25481 of 3$615,314Low, 5.0% under the second
12 JUN 202666M92District 03Section ((125)CR-2588,CR-2589)2 of 5$793,348+12%
12 JUN 202666T10District 03Section (1B-1)BRR1 of 2$236,720Low, 5.0% under the second
12 JUN 202687851District 03Project Number: 7M6S-350 / /, section 23-00306-00-BR1 of 3$1,225,921Low, 11% under the second
24 APR 202687909District 03Marseiles, section 24-00057-00-SW2 of 6$283,093+3.0%
27 FEB 202668E33District 04Section (3-B)BR2 of 4$1,741,586+2.0%
27 FEB 202668K57District 04Section (124BR)SCR2 of 6$24,360+11%
07 NOV 202587891District 03Project Number: 0Fcr-005 / /, section 22-00146-00-BR2 of 2$802,684+26%
19 SEP 202566R59District 03Section (6)SCR4 of 6$46,495+68%
13 JUN 202566B58District 03Section (106BR-2)BR1 of 2$1,643,145Low, 7.0% under the second
13 JUN 202587882District 03Seneca, section 21-00020-00-BR3 of 4$651,667+22%
08 NOV 202466L79District 03Section (112BR)BR1 of 2$1,865,719Low, 30% under the second
14 JUN 202487823District 03Project Number: Du05-738 / /, section 17-15128-00-BR2 of 2$461,445+7.0%
26 APR 202487792District 03Project Number: Zh0P-871 / /, section 19-00174-00-BR1 of 2$1,942,958Low, 0.0% under the second
26 APR 202487820District 03Project Number: Yv6Z-643 / /, section 20-00199-04-BR2 of 2$754,724+2.0%
08 MAR 202487821District 03Project Number: 2T7S-848 / /, section 21-00210-01-BR2 of 2$535,933+5.0%
19 JAN 202487822District 03Project Number: 0Wkf-381 / /, section 11-14106-03-BR1 of 3$494,605Low, 8.0% under the second
04 AUG 202366N37District 03Section (111)CLV-21 of 3$495,072Low, 1.0% under the second
10 MAR 202387795District 03Project Number: 19N1-078 / /, section 21-07127-00-BR1 of 6$1,047,965Low, 0.0% under the second
10 MAR 202387796District 03Project Number: Pkxu-134 / /, section 19-04115-00-BR2 of 3$343,077+2.0%
10 MAR 202387808District 03Project Number: 8Yb8-638 / /, section 19-25110-03-BR2 of 3$513,363+9.0%
20 JAN 202366824District 03Section (116)CR-53093 of 4$586,597+36%
18 NOV 202266M51District 03Section (3BB)CLV1 of 5$337,464Low, 8.0% under the second
23 SEP 202266F92District 03Section (108BR-4)BR1 of 3$1,025,425Low, 1.0% under the second
11 MAR 202287773District 03Project Number: Nqqe-685 / /, section 18-17119-02-BR3 of 3$447,484+10%
Riber Construction, Inc.: latest IDOT bids in the data

How this record was read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy