IDOT contract 87909 bid tabulation
Marseiles, section 24-00057-00-SW. Let by Illinois DOT on April 24, 2026, Lasalle, District 03. 6 bids received; low bid $274,017 by Davis Concrete Construction Co..
- Owner
- Illinois DOT
- Letting
- 24 APR 2026
- Pay items
- 27
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Davis Concrete Construction Co. | $274,017 | Low |
| 2 | Riber Construction, Inc. | $283,093 | +3.0% |
| 3 | D. Construction, Inc. | $289,704 | +6.0% |
| 4 | Gensini Excavating, Inc. | $309,012 | +13% |
| 5 | Gillan Construction LLC | $322,004 | +18% |
| 6 | Universal Asphalt & Excavating, Inc. | $326,890 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Davis Concrete Construction Co. | 2. Riber Construction, Inc. | 3. D. Construction, Inc. | 4. Gensini Excavating, Inc. | 5. Gillan Construction LLC | 6. Universal Asphalt & Excavating, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Street sign complete (XX009225) | EACH | 1 | $250.00 | $300.00 | $1,100.00 | $1,608.70 | $1,000.00 | $3,000.00 |
| 2 | FL beacon P MTD SP in (X0325714) | EACH | 2 | $4,000.00 | $1,000.00 | $1,210.00 | $5,827.56 | $5,000.00 | $4,000.00 |
| 3 | Pavt replace special (X4420207) | SY | 22 | $50.00 | $285.00 | $200.00 | $274.23 | $265.00 | $600.00 |
| 4 | Rem EX sign panel (X7240195) | EACH | 1 | $25.00 | $100.00 | $302.50 | $105.39 | $250.00 | $3,000.00 |
| 5 | Rem EX sign compl (X7240207) | EACH | 3 | $25.00 | $100.00 | $110.00 | $105.38 | $250.00 | $500.00 |
| 6 | Topsoil F & P 4 (21101615) | SY | 782 | $2.00 | $7.00 | $19.80 | $20.30 | $11.50 | $12.00 |
| 7 | Seeding CL 1 (25000100) | ACRE | 0.25 | $1,500.00 | $18,000 | $30,800 | $29,359 | $20,000 | $10,000 |
| 8 | Nitrogen fert nutr (25000400) | LB | 18 | $1.00 | $5.00 | $16.50 | $2.22 | $5.00 | $100.00 |
| 9 | Phosphorus fert nutr (25000500) | LB | 18 | $1.00 | $5.00 | $16.50 | $2.22 | $5.00 | $100.00 |
| 10 | Potassium fert nutr (25000600) | LB | 18 | $1.00 | $5.00 | $16.50 | $2.22 | $5.00 | $100.00 |
| 11 | Erosion contr blanket (25100630) | SY | 782 | $2.00 | $2.00 | $5.50 | $4.91 | $4.00 | $3.00 |
| 12 | Agg base cse B 2 (35101582) | SY | 1,835 | $0.10 | $3.00 | $6.50 | $15.33 | $8.50 | $5.00 |
| 13 | PCC driveway pavt 7 (42300300) | SY | 141 | $94.00 | $112.00 | $98.00 | $108.79 | $90.00 | $80.00 |
| 14 | PC conc sidewalk 4 (42400100) | SF | 14,011 | $11.75 | $9.50 | $10.00 | $8.92 | $10.50 | $12.00 |
| 15 | Detectable warnings (42400800) | SF | 200 | $25.00 | $28.00 | $40.00 | $33.29 | $31.00 | $30.00 |
| 16 | Drive pavement rem (44000200) | SY | 141 | $15.00 | $16.50 | $15.00 | $9.24 | $28.00 | $20.00 |
| 17 | Comb curb gutter rem (44000500) | LF | 180 | $13.00 | $12.50 | $11.20 | $14.48 | $17.50 | $10.00 |
| 18 | Sidewalk rem (44000600) | SF | 14,011 | $3.00 | $3.00 | $2.50 | $2.23 | $3.00 | $3.00 |
| 19 | Comb CC&G TB6.12 (60603800) | LF | 180 | $49.00 | $75.00 | $42.00 | $59.83 | $70.00 | $42.00 |
| 20 | Mobilization (67100100) | LS | 1 | $8,000.00 | $17,000 | $16,450 | $14,021 | $20,000 | $8,000.00 |
| 21 | TR cont & prot 701501 (70102620) | LS | 1 | $5,000.00 | $16,000 | $7,500.00 | $10,543 | $10,000 | $10,000 |
| 22 | Sign panel T1 (72000100) | SF | 71 | $15.00 | $35.00 | $33.00 | $42.67 | $50.00 | $20.00 |
| 23 | Teles STL sin support (72800100) | LF | 39 | $10.00 | $35.00 | $16.50 | $35.90 | $15.00 | $10.00 |
| 24 | Metal post TY A (72900100) | LF | 81 | $10.00 | $20.00 | $14.30 | $49.20 | $15.00 | $20.00 |
| 25 | Paint PVT MK line 6 (78001130) | LF | 788 | $3.20 | $1.30 | $1.43 | $2.83 | $3.50 | $3.00 |
| 26 | Paint PVT MK line 12 (78001150) | LF | 756 | $4.90 | $2.60 | $2.86 | $5.68 | $5.40 | $6.00 |
| 27 | Paint PVT MK line 24 (78001180) | LF | 143 | $8.00 | $5.20 | $5.72 | $11.10 | $8.80 | $10.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.