G. M. Sipes Construction, Inc.: IDOT bid record

G. M. Sipes Construction, Inc. submitted 214 bids on Illinois DOT contracts in the data, from 15 JAN 2021 to 31 JUL 2026, and was the low bidder on 84 of them (39%). When it was not low, its total sat a median +12% above the low bid.

Owner
Illinois DOT
Low bid volume
$53,169,646
Latest bid
31 JUL 2026
Data through
18 SEP 2026
214Bids
84Low bids
39Win rate, percent
+12%Median gap to the low bid when not low, 130 bids

By year

YearBidsLow bidsWin rate
2021432047%
2022461533%
2023241146%
2024401435%
2025341338%
2026271141%
G. M. Sipes Construction, Inc., IDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
District 03402768%
District 06321031%
District 0731619%
District 02281864%
District 0528725%
District 092827%
District 0816638%
District 0411873%
G. M. Sipes Construction, Inc., IDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Tie bars 3/444213204EACH12775 (59%)$10.00$17.00
Changeable message SN70107025CAL DAY8965 (73%)$25.00$55.00
Dowel bars 1 1/244201299EACH10262 (61%)$20.00$25.00
Welded wire reinf44200050SY8955 (62%)$10.00$16.00
Saw cuts44213200LF6922 (32%)$5.95$5.00
Patch reinforcement44213000SY8419 (23%)$75.00$70.00
Traf cont-prot 70141170100420EACH3015 (50%)$1,500.00$750.00
Mod ureth PM line 478009004LF1815 (83%)$3.33$1.69
Raised refl pavt MKR78100100EACH2414 (58%)$171.00$48.00
Paint PVT MK line 478001110LF2313 (57%)$3.55$1.00
Det loop T188600100LF1212 (100%)$29.57$26.17
Trainees TPGZ0076604HR1111 (100%)$15.00$15.00
G. M. Sipes Construction, Inc., IDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

G. M. Sipes Construction, Inc., IDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
31 JUL 202666T21District 03Section (128)PP1 of 2$690,200Low, 2.0% under the second
31 JUL 202666T22District 03Section (19)1 of 2$610,480Low, 12% under the second
31 JUL 202676V11District 08Section DIST3 of 3$1,011,532+6.0%
12 JUN 202664U86District 02Section D23 of 4$775,817+7.0%
12 JUN 202666T09District 03Section (WS)PP-22 of 4$438,215+13%
12 JUN 202666T29District 03Section (115,116)1 of 3$372,960Low, 26% under the second
12 JUN 202666T39District 03Section (50-3,4,5,8)PP-21 of 2$2,815,825Low, 41% under the second
12 JUN 202666T45District 03Section (50-6)PP-11 of 3$639,792Low, 1.0% under the second
12 JUN 202672E73District 06Section (112B-1)BRR,I2 of 4$78,850+41%
24 APR 202664U85District 02Section (8R)PP2 of 4$566,2400.0%
24 APR 202668K89District 04Section (21,20)PP1 of 1$883,425Low
24 APR 202670H82District 05Section CM4 of 4$616,539+29%
24 APR 202670H85District 05Section (57-6,7,20)PP2 of 2$1,402,544+14%
24 APR 202674E19District 07Section D73 of 3$1,180,413+23%
24 APR 202674E20District 07Section D72 of 4$424,845+4.0%
24 APR 202676U70District 08Section (48,49,50,51-1,52-1,53,54,55,62)PP-12 of 3$1,294,2230.0%
24 APR 202676V05District 08Section DIST1 of 3$1,969,789Low, 13% under the second
24 APR 202676V10District 08Section 61-(1-1,1-2,2,3,3-1,4,5,5-1,6)PP-11 of 5$1,565,730Low, 8.0% under the second
27 FEB 202664T23District 02Section (141-1)PP2 of 5$144,389+4.0%
27 FEB 202676U78District 08Section (X-3)PP1 of 4$898,651Low, 20% under the second
16 JAN 202664U81District 02Section (2-1A)PP1 of 3$779,622Low, 12% under the second
16 JAN 202664U83District 02Section (112Y-1)PP&SR1 of 3$685,514Low, 41% under the second
16 JAN 202666R85District 03Section (50-6)T2 of 4$351,694+5.0%
16 JAN 202672G53District 06Section D62 of 2$1,940,727+8.0%
16 JAN 202672H11District 06Section D62 of 2$380,529+12%
G. M. Sipes Construction, Inc.: latest IDOT bids in the data

How this record was read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way