IDOT contract 66T45 bid tabulation
Section (50-6)PP-1. Let by Illinois DOT on June 12, 2026, Lasalle, District 03. 3 bids received; low bid $639,792 by G. M. Sipes Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 12 JUN 2026
- Pay items
- 17
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | G. M. Sipes Construction, Inc. | $639,792 | Low |
| 2 | D. Construction, Inc. | $648,919 | +1.0% |
| 3 | Plote Construction, Inc. | $777,492 | +22% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. G. M. Sipes Construction, Inc. | 2. D. Construction, Inc. | 3. Plote Construction, Inc. |
|---|---|---|---|---|---|---|
| 1 | TC-prot 701201 SPL (X7010520) | LS | 1 | $500.00 | $20,000 | $35,000 |
| 2 | Temp info signing (X7200061) | SF | 42 | $0.01 | $40.00 | $20.00 |
| 3 | Dowel bar assembly (Z0017099) | EACH | 93 | $50.00 | $300.00 | $250.00 |
| 4 | Welded wire reinf (44200050) | SY | 1,781 | $25.00 | $20.00 | $18.50 |
| 5 | CL B patch T2 8 (44200934) | SY | 468 | $225.00 | $145.00 | $160.00 |
| 6 | CL B patch T3 8 (44200942) | SY | 248 | $225.00 | $145.00 | $170.00 |
| 7 | CL B patch T4 8 (44200944) | SY | 1,981 | $175.00 | $145.00 | $180.00 |
| 8 | Dowel bars 1 1/2 (44201299) | EACH | 1,856 | $10.00 | $20.00 | $47.00 |
| 9 | Saw cuts (44213200) | LF | 7,122 | $0.01 | $6.00 | $1.75 |
| 10 | Tie bars 3/4 (44213204) | EACH | 618 | $5.00 | $15.00 | $28.00 |
| 11 | Mobilization (67100100) | LS | 1 | $25,000 | $38,900 | $45,000 |
| 12 | Traf cont-prot 701456 (70100825) | LS | 1 | $500.00 | $0.01 | $1.00 |
| 13 | Changeable message SN (70107025) | CAL DAY | 60 | $0.01 | $100.00 | $60.00 |
| 14 | Mod ureth PM line 4 (78009004) | LF | 31,396 | $0.70 | $0.77 | $1.00 |
| 15 | Mod ureth PM line 6 (78009006) | LF | 600 | $0.80 | $0.88 | $1.50 |
| 16 | Mod ureth PM line 8 (78009008) | LF | 1,572 | $2.20 | $2.42 | $2.25 |
| 17 | Raised refl pavt MKR (78100100) | EACH | 52 | $177.00 | $194.70 | $200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.