Keeley & Sons, Inc.: IDOT bid record
Keeley & Sons, Inc. submitted 115 bids on Illinois DOT contracts in the data, from 23 APR 2021 to 18 SEP 2026, and was the low bidder on 50 of them (43%). When it was not low, its total sat a median +18% above the low bid.
- Owner
- Illinois DOT
- Low bid volume
- $126,026,761
- Latest bid
- 18 SEP 2026
- Data through
- 18 SEP 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2021 | 13 | 5 | 38% |
| 2022 | 17 | 6 | 35% |
| 2023 | 25 | 11 | 44% |
| 2024 | 20 | 6 | 30% |
| 2025 | 17 | 13 | 76% |
| 2026 | 23 | 9 | 39% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 08 | 102 | 47 | 46% |
| District 07 | 8 | 2 | 25% |
| District 06 | 4 | 1 | 25% |
| District 09 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Trainees TPG | Z0076604 | HR | 50 | 50 (100%) | $15.00 | $15.00 |
| Changeable message SN | 70107025 | CAL DAY | 61 | 40 (66%) | $55.59 | $55.00 |
| Trainees | Z0076600 | HR | 31 | 31 (100%) | $0.80 | $0.80 |
| Raised refl pavt MKR | 78100100 | EACH | 42 | 24 (57%) | $113.73 | $48.00 |
| SHRT TRM pavt MK rem | 70300150 | SF | 30 | 22 (73%) | $1.77 | $1.20 |
| TR bar TRM T1 SPL tan | 63100167 | EACH | 24 | 19 (79%) | $3,340.50 | $3,800.00 |
| Conc rem | 50102400 | CY | 33 | 17 (52%) | $2,390.40 | $2,400.00 |
| Conc sup-STR | 50300255 | CY | 40 | 16 (40%) | $2,960.00 | $2,100.00 |
| Earth excavation | 20200100 | CY | 33 | 16 (48%) | $29.85 | $48.00 |
| Driving piles | 51202305 | LF | 16 | 16 (100%) | $0.01 | $0.10 |
| Tie bars 3/4 | 44213204 | EACH | 36 | 15 (42%) | $19.80 | $17.00 |
| Terminal marker - DA | 72501000 | EACH | 23 | 15 (65%) | $42.84 | $47.85 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Kinney Contractors, Inc. | 40 | 20 of 40 |
| The Kilian Corporation | 21 | 9 of 21 |
| G. M. Sipes Construction, Inc. | 15 | 10 of 15 |
| Samron Midwest Contracting, Inc. | 11 | 5 of 11 |
| Keller Construction, Inc. | 10 | 6 of 10 |
| Stutz Excavating, Inc. | 10 | 8 of 10 |
| DMS Contracting, Inc. | 8 | 5 of 8 |
| Sangamo Construction Company | 8 | 4 of 8 |
| Plocher Construction Company, Inc. | 8 | 4 of 8 |
| Hank's Excavating & Landscaping, Inc. | 7 | 4 of 7 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 18 SEP 2026 | 76V40 | District 08 | Section DIST | 1 of 2 | $2,792,065 | Low, 9.0% under the second |
| 18 SEP 2026 | 76V43 | District 08 | Section DIST | 2 of 4 | $2,638,025 | +21% |
| 18 SEP 2026 | 97892 | District 08 | Shiloh, section 22-00022-00-PW | 2 of 3 | $7,879,932 | +3.0% |
| 31 JUL 2026 | 76V11 | District 08 | Section DIST | 2 of 3 | $999,552 | +5.0% |
| 12 JUN 2026 | 76R32 | District 08 | Section 1-BR-1 | 2 of 2 | $6,337,170 | +37% |
| 12 JUN 2026 | 76R36 | District 08 | Section 82-8-BJR-BDR-BP-1 | 2 of 2 | $5,153,969 | +5.0% |
| 12 JUN 2026 | 76U76 | District 08 | Section 82-3HVB-2BDR | 1 of 2 | $1,093,567 | Low, 25% under the second |
| 12 JUN 2026 | 76U77 | District 08 | Section 29-2(BDR,BRR,BJR) | 2 of 2 | $1,371,616 | +22% |
| 12 JUN 2026 | 76U82 | District 08 | Section 82-3HVB-BDR-1 | 1 of 1 | $2,195,979 | Low |
| 12 JUN 2026 | 76V08 | District 08 | Section DIST | 1 of 1 | $2,580,521 | Low |
| 12 JUN 2026 | 76V09 | District 08 | Section DIST | 1 of 1 | $3,642,071 | Low |
| 24 APR 2026 | 76U70 | District 08 | Section (48,49,50,51-1,52-1,53,54,55,62)PP-1 | 1 of 3 | $1,293,514 | Low, 0.0% under the second |
| 24 APR 2026 | 76V07 | District 08 | Section DIST | 2 of 2 | $1,511,805 | +8.0% |
| 24 APR 2026 | 76V10 | District 08 | Section 61-(1-1,1-2,2,3,3-1,4,5,5-1,6)PP-1 | 5 of 5 | $2,434,328 | +55% |
| 24 APR 2026 | 76V14 | District 08 | Section DIST | 1 of 2 | $2,792,065 | Low, 5.0% under the second |
| 27 FEB 2026 | 76A37 | District 08 | Section 29-2BR | 2 of 2 | $4,823,383 | +11% |
| 27 FEB 2026 | 76B42 | District 08 | Section 26BR,11BR-1 | 3 of 3 | $4,699,926 | +31% |
| 27 FEB 2026 | 76U52 | District 08 | Section DIST | 2 of 2 | $2,011,267 | +1.0% |
| 27 FEB 2026 | 76U73 | District 08 | Section 82-1RS-2, | 1 of 1 | $1,649,119 | Low |
| 27 FEB 2026 | 76U78 | District 08 | Section (X-3)PP | 2 of 4 | $1,081,453 | +20% |
| 27 FEB 2026 | 97886 | District 08 | Fairview Heights, section 24-00035-01-RS | 1 of 2 | $1,199,255 | Low, 6.0% under the second |
| 27 FEB 2026 | 97889 | District 08 | Valmeyer, section 22-00011-00-RS | 2 of 2 | $897,245 | +25% |
| 16 JAN 2026 | 76N65 | District 08 | Section (103,104)BR-1 | 3 of 3 | $20,720,600 | +18% |
| 19 SEP 2025 | 76T17 | District 08 | Section 580-BR-1 | 1 of 2 | $13,758,278 | Low, 17% under the second |
| 19 SEP 2025 | 76U51 | District 08 | Section DIST | 1 of 2 | $1,280,653 | Low, 56% under the second |
How this record was read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.