The Kilian Corporation: IDOT bid record
The Kilian Corporation submitted 127 bids on Illinois DOT contracts in the data, from 15 JAN 2021 to 18 SEP 2026, and was the low bidder on 69 of them (54%). When it was not low, its total sat a median +6.0% above the low bid.
- Owner
- Illinois DOT
- Low bid volume
- $141,085,913
- Latest bid
- 18 SEP 2026
- Data through
- 18 SEP 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2021 | 24 | 11 | 46% |
| 2022 | 24 | 14 | 58% |
| 2023 | 26 | 14 | 54% |
| 2024 | 29 | 16 | 55% |
| 2025 | 12 | 5 | 42% |
| 2026 | 12 | 9 | 75% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 08 | 122 | 67 | 55% |
| District 06 | 3 | 1 | 33% |
| District 07 | 1 | 1 | 100% |
| District 09 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Trainees TPG | Z0076604 | HR | 79 | 79 (100%) | $15.00 | $15.00 |
| Bit matls tack CT | 40600290 | LB | 87 | 71 (82%) | $1.35 | $0.01 |
| Trainees | Z0076600 | HR | 66 | 66 (100%) | $0.80 | $0.80 |
| Agg wedge SHLD type B | 48102100 | TON | 45 | 34 (76%) | $45.00 | $50.00 |
| Raised refl pavt MKR | 78100100 | EACH | 82 | 33 (40%) | $44.50 | $48.00 |
| Changeable message SN | 70107025 | CAL DAY | 69 | 31 (45%) | $65.00 | $55.00 |
| Short term pavt mking | 70300100 | LF | 74 | 30 (41%) | $3.00 | $1.01 |
| Long joint sealant | 40600370 | LF | 54 | 27 (50%) | $3.20 | $3.30 |
| HMA shoulders | 48203100 | TON | 47 | 26 (55%) | $133.00 | $135.79 |
| THPL PVT MK line 4 | 78000200 | LF | 48 | 24 (50%) | $0.91 | $0.88 |
| Engr field office A | 67000400 | CAL MO | 48 | 24 (50%) | $2,450.00 | $2,550.00 |
| THPL PVT MK line 12 | 78000600 | LF | 42 | 21 (50%) | $8.85 | $3.10 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Christ Bros. Asphalt, Inc. | 80 | 31 of 80 |
| Keeley & Sons, Inc. | 21 | 12 of 21 |
| E. T. Simonds Construction Company | 10 | 4 of 10 |
| Stutz Excavating, Inc. | 10 | 5 of 10 |
| Keller Construction, Inc. | 7 | 5 of 7 |
| Samron Midwest Contracting, Inc. | 7 | 5 of 7 |
| DMS Contracting, Inc. | 6 | 2 of 6 |
| Howell Paving, Inc. | 4 | 1 of 4 |
| Hank's Excavating & Landscaping, Inc. | 3 | 1 of 3 |
| Kinney Contractors, Inc. | 3 | 1 of 3 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 18 SEP 2026 | 76W01 | District 08 | Section 95-(5,6)PP-1 | 1 of 2 | $1,302,632 | Low, 0.0% under the second |
| 12 JUN 2026 | 76R36 | District 08 | Section 82-8-BJR-BDR-BP-1 | 1 of 2 | $4,888,194 | Low, 5.0% under the second |
| 12 JUN 2026 | 76U76 | District 08 | Section 82-3HVB-2BDR | 2 of 2 | $1,371,476 | +25% |
| 12 JUN 2026 | 76V18 | District 08 | Section 82-(8,9,10)I-2 | 1 of 2 | $3,286,837 | Low, 3.0% under the second |
| 24 APR 2026 | 76N37 | District 08 | Section (4,5)RS-3 | 1 of 2 | $3,340,535 | Low, 14% under the second |
| 24 APR 2026 | 76U75 | District 08 | Section 76I | 2 of 3 | $104,803 | +9.0% |
| 24 APR 2026 | 97808 | District 08 | Fairview Heights, section 20-00044-00-RS | 1 of 2 | $1,289,612 | Low, 18% under the second |
| 24 APR 2026 | 97840 | District 08 | Wood River, section 17-00048-00-RS | 2 of 2 | $1,795,748 | +13% |
| 27 FEB 2026 | 76V02 | District 08 | Section 1Z, | 1 of 2 | $835,131 | Low, 6.0% under the second |
| 16 JAN 2026 | 76U95 | District 08 | Section (130-1,130-2)RS-4 | 1 of 2 | $3,475,296 | Low, 6.0% under the second |
| 16 JAN 2026 | 97851 | District 08 | Siu-E, section 23-00007-01-RS | 1 of 2 | $982,094 | Low, 21% under the second |
| 16 JAN 2026 | 97871 | District 08 | O'Fallon, section 24-00054-02-PV | 1 of 2 | $1,369,759 | Low, 10% under the second |
| 01 AUG 2025 | 76M52 | District 08 | Section 26,45RS-3 | 1 of 2 | $2,621,744 | Low, 8.0% under the second |
| 25 APR 2025 | 76J62 | District 08 | Section (31,410,410-1)RS-4,(82-7K)RS-1 | 2 of 2 | $14,380,024 | +2.0% |
| 25 APR 2025 | 76N05 | District 08 | Section (47,113)RS-4 | 2 of 2 | $8,240,607 | +5.0% |
| 25 APR 2025 | 76U18 | District 08 | Section (82-11HB)BJR,BDR | 1 of 1 | $1,173,906 | Low |
| 25 APR 2025 | 76U30 | District 08 | Section 82-1-B-1BJR-2 | 2 of 2 | $3,841,935 | +2.0% |
| 25 APR 2025 | 76U31 | District 08 | Section 52RS-3 | 1 of 2 | $9,334,223 | Low, 1.0% under the second |
| 25 APR 2025 | 97857 | District 08 | Project Number: Hll1-832 / /, section 20-00097-00-RS | 3 of 3 | $936,454 | +21% |
| 25 APR 2025 | 97861 | District 08 | Project Number: E0I9-669 / /, section 21-00109-00-RS | 2 of 2 | $2,280,069 | +6.0% |
| 07 MAR 2025 | 76T85 | District 08 | Section 82-(1,2,3,4)I-2 | 2 of 2 | $4,020,593 | +3.0% |
| 07 MAR 2025 | 76U15 | District 08 | Section 51 | 1 of 2 | $564,097 | Low, 4.0% under the second |
| 07 MAR 2025 | 76U28 | District 08 | Section 169RS-2 | 2 of 2 | $2,061,230 | +4.0% |
| 07 MAR 2025 | 97842 | District 08 | Project Number: Byir-383 / /, section 22-00268-07-RS | 1 of 2 | $1,155,943 | Low, 5.0% under the second |
| 13 DEC 2024 | 76U07 | District 08 | Section 60-7BJR-BDR | 2 of 2 | $2,903,310 | +2.0% |
How this record was read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.