IDOT contract 97871 bid tabulation
O'Fallon, section 24-00054-02-PV. Let by Illinois DOT on January 16, 2026, St. Clair, District 08. 2 bids received; low bid $1,369,759 by The Kilian Corporation.
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 51
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | The Kilian Corporation | $1,369,759 | Low |
| 2 | Christ Bros. Asphalt, Inc. | $1,501,273 | +10% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. The Kilian Corporation | 2. Christ Bros. Asphalt, Inc. |
|---|---|---|---|---|---|
| 1 | Traf cont & prot SPL (X7010216) | LS | 1 | $11,725 | $35,425 |
| 2 | TC-prot 701501 SPL (X7010226) | LS | 1 | $1,200.00 | $77,800 |
| 3 | Rem & rein sign panel (X7200075) | SF | 14 | $52.00 | $50.00 |
| 4 | Sign panel T1 SPL (X7200105) | SF | 73.30 | $46.25 | $45.00 |
| 5 | Rem RE-erect EX sign (X7240600) | EACH | 2 | $415.00 | $400.00 |
| 6 | Sign support SPL (X7330064) | EACH | 2 | $415.00 | $400.00 |
| 7 | Construction layout (Z0013798) | LS | 1 | $7,500.00 | $16,000 |
| 8 | Paint curb (Z0036200) | LF | 49 | $10.65 | $10.67 |
| 9 | RR prot liability ins (Z0048665) | LS | 1 | $5,100.00 | $26,500 |
| 10 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 |
| 11 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 |
| 12 | Rem & disp uns matl (20201200) | CY | 70 | $75.00 | $30.00 |
| 13 | Agg base cse B 12 (35102400) | SY | 200 | $50.00 | $25.00 |
| 14 | Bit matls tack CT (40600290) | LB | 11,977 | $2.25 | $2.16 |
| 15 | HMA SC IL-9.5 D N70 (40604062) | TON | 3,098 | $159.00 | $135.68 |
| 16 | HMA surf rem 2 (44000157) | SY | 27,671 | $5.85 | $5.48 |
| 17 | Comb curb gutter rem (44000500) | LF | 29 | $125.00 | $245.00 |
| 18 | CL B patch T2 10 (44200970) | SY | 96 | $155.00 | $225.00 |
| 19 | CL B patch T4 10 (44200976) | SY | 930 | $155.00 | $220.00 |
| 20 | Dowel bars 1 1/2 (44201299) | EACH | 616 | $8.75 | $8.50 |
| 21 | CL D patch T1 10 (44201761) | SY | 70 | $250.00 | $247.58 |
| 22 | CL D patch T2 10 (44201765) | SY | 200 | $228.00 | $247.58 |
| 23 | CL D patch T3 10 (44201769) | SY | 150 | $216.00 | $247.58 |
| 24 | CL D patch T4 10 (44201771) | SY | 50 | $208.00 | $247.58 |
| 25 | Saw cuts (44213200) | LF | 1,253 | $7.75 | $7.50 |
| 26 | Tie bars 3/4 (44213204) | EACH | 300 | $5.25 | $5.00 |
| 27 | HMA shoulders (48203100) | TON | 264 | $183.00 | $190.45 |
| 28 | Water valves adjust (56109210) | EACH | 1 | $135.00 | $100.00 |
| 29 | Comb CC&G TY B-6.24 (60605000) | LF | 29 | $205.00 | $200.00 |
| 30 | Mobilization (67100100) | LS | 1 | $96,825 | $122,812 |
| 31 | Traf cont-prot 701306 (70100460) | LS | 1 | $14,500 | $0.01 |
| 32 | Short term pavt mking (70300100) | LF | 720 | $3.50 | $4.09 |
| 33 | SHRT TRM pavt MK rem (70300150) | SF | 240 | $10.00 | $0.01 |
| 34 | Sign panel T1 (72000100) | SF | 337 | $26.50 | $25.75 |
| 35 | Remov sin pan assy TA (72400100) | EACH | 42 | $142.00 | $200.00 |
| 36 | Teles STL sin support (72800100) | LF | 914.50 | $15.70 | $15.25 |
| 37 | THPL PVT MK LTR & sym (78000100) | SF | 485.40 | $21.95 | $21.87 |
| 38 | THPL PVT MK line 4 (78000200) | LF | 19,021 | $1.35 | $1.33 |
| 39 | THPL PVT MK line 8 (78000500) | LF | 4,525 | $4.20 | $4.21 |
| 40 | THPL PVT MK line 12 (78000600) | LF | 740 | $11.20 | $11.15 |
| 41 | THPL PVT MK line 24 (78000650) | LF | 2,293 | $17.60 | $17.61 |
| 42 | Pref PL PM TB STNRD LTR-sym (78003101) | SF | 52.20 | $50.35 | $50.31 |
| 43 | Pref PL PM TB STD L4 (78003111) | LF | 3,134 | $5.55 | $5.56 |
| 44 | Pref PL PM TB STD L8 (78003141) | LF | 592 | $11.85 | $11.87 |
| 45 | Pref PL PM TB STD L12 (78003151) | LF | 43 | $20.90 | $20.97 |
| 46 | Pref PL PM TB STD L24 (78003181) | LF | 171 | $26.05 | $26.03 |
| 47 | GRV RCSD PM LTR & sym (78011000) | SF | 52.20 | $17.20 | $17.13 |
| 48 | GRV RCSD PVT MRKG 7 (78011035) | LF | 3,134 | $1.95 | $1.93 |
| 49 | GRV RCSD PVT MRKG 11 (78011055) | LF | 592 | $5.15 | $5.12 |
| 50 | GRV RCSD PVT MRKG 16 (78011075) | LF | 43 | $7.10 | $7.05 |
| 51 | GRV RCSD PVT MRKG 28 (78011130) | LF | 171 | $8.90 | $8.87 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.