IDOT contract 76U30 bid tabulation
Section 82-1-B-1BJR-2. Let by Illinois DOT on April 25, 2025, St.Clair, District 08. 2 bids received; low bid $3,755,513 by Keeley & Sons, Inc..
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 44
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Keeley & Sons, Inc. | $3,755,513 | Low |
| 2 | The Kilian Corporation | $3,841,935 | +2.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Keeley & Sons, Inc. | 2. The Kilian Corporation |
|---|---|---|---|---|---|
| 1 | TC-prot 701401 SPL (X7010206) | EACH | 1 | $69,890 | $46,000 |
| 2 | Detour signing (X7200203) | LS | 1 | $5,980.00 | $3,000.00 |
| 3 | Deck slab rep (part) (Z0016200) | SY | 37.30 | $617.15 | $650.00 |
| 4 | Modular exp JT-SW 6 (Z0034806) | LF | 36 | $5,590.00 | $6,440.00 |
| 5 | Modular exp JT-SW 9 (Z0034809) | LF | 171 | $6,490.00 | $8,285.00 |
| 6 | Trainees (Z0076600) | HR | 1,500 | $0.80 | $0.80 |
| 7 | Trainees TPG (Z0076604) | HR | 1,500 | $15.00 | $15.00 |
| 8 | Bit matls tack CT (40600290) | LB | 7,977 | $0.72 | $0.70 |
| 9 | PCC surf rem butt JT (40600985) | SY | 1,083 | $25.50 | $25.00 |
| 10 | Temporary ramp (40600990) | SY | 72 | $0.02 | $0.01 |
| 11 | P SC SMA 9.5 E N80 (40605024) | TON | 1,675.20 | $204.00 | $200.00 |
| 12 | Protective coat (42001300) | SY | 202 | $6.85 | $5.00 |
| 13 | CL B patch T1 11 (44200978) | SY | 13.30 | $687.45 | $500.00 |
| 14 | CL B patch T2 11 (44200982) | SY | 10 | $587.90 | $500.00 |
| 15 | Conc rem (50102400) | CY | 80.70 | $3,690.00 | $3,000.00 |
| 16 | Conc sup-STR (50300255) | CY | 93.70 | $5,867.45 | $4,500.00 |
| 17 | Stud shear connectors (50500505) | EACH | 60 | $119.35 | $100.00 |
| 18 | Reinf bars, epoxy CTD (50800205) | LB | 13,759 | $3.95 | $2.50 |
| 19 | Bar splicers (50800515) | EACH | 65 | $29.80 | $34.00 |
| 20 | Mechanical splicers (50800530) | EACH | 1,000 | $59.85 | $82.00 |
| 21 | Pref JT strip seal (52000110) | LF | 42 | $617.80 | $595.00 |
| 22 | FLS waterproof system (58100210) | SY | 11,665 | $37.80 | $37.05 |
| 23 | Engr field office A (67000400) | CAL MO | 6 | $3,765.00 | $3,000.00 |
| 24 | Mobilization (67100100) | LS | 1 | $207,865 | $230,000 |
| 25 | Traf cont-prot 701402 (70100207) | EACH | 1 | $32,890 | $62,500 |
| 26 | Traf cont-prot 701446 (70100430) | EACH | 1 | $3,570.00 | $2,500.00 |
| 27 | Traf cont-prot 701406 (70100700) | LS | 1 | $1,020.00 | $0.01 |
| 28 | Traf cont-prot 701451 (70100820) | LS | 1 | $3,060.00 | $3,000.00 |
| 29 | Traf cont-prot 701456 (70100825) | LS | 1 | $5,100.00 | $0.01 |
| 30 | Changeable message SN (70107025) | CAL DAY | 578 | $51.00 | $60.00 |
| 31 | Short term pavt mking (70300100) | LF | 685 | $2.00 | $1.50 |
| 32 | SHRT TRM pavt MK rem (70300150) | SF | 228 | $5.00 | $7.54 |
| 33 | Temp PVT MK line 6 - paint (70300241) | LF | 5,730 | $0.02 | $0.01 |
| 34 | Temp PVT MK line 8 - paint (70300251) | LF | 1,588 | $0.02 | $0.01 |
| 35 | Temp PVT MK line 12 - paint (70300261) | LF | 397 | $0.02 | $0.01 |
| 36 | Temp conc barrier (70400100) | LF | 1,842 | $63.85 | $34.00 |
| 37 | Rel temp conc barrier (70400200) | LF | 1,480 | $13.90 | $7.50 |
| 38 | Imp attn temp NRN TL3 (70600251) | EACH | 2 | $5,715.85 | $5,000.00 |
| 39 | Imp attn rel NRN TL3 (70600352) | EACH | 1 | $2,990.00 | $1,500.00 |
| 40 | THPL PVT MK line 6 (78000400) | LF | 5,730 | $1.89 | $1.90 |
| 41 | THPL PVT MK line 8 (78000500) | LF | 1,588 | $6.99 | $7.00 |
| 42 | THPL PVT MK line 12 (78000600) | LF | 397 | $8.67 | $8.60 |
| 43 | Raised refl pavt MKR (78100100) | EACH | 35 | $183.60 | $182.00 |
| 44 | Raised ref PVT MK rem (78300200) | EACH | 35 | $0.02 | $0.01 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.