IDOT contract 76M52 bid tabulation

Section 26,45RS-3. Let by Illinois DOT on August 1, 2025, St.Clair, District 08. 2 bids received; low bid $2,621,744 by The Kilian Corporation.

Owner
Illinois DOT
Letting
01 AUG 2025
Pay items
87
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1The Kilian Corporation$2,621,744Low
2Christ Bros. Asphalt, Inc.$2,822,327+8.0%
IDOT contract 76M52: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. The Kilian Corporation2. Christ Bros. Asphalt, Inc.
1Man TA 4 dia SPL F&G (X6022230)EACH1$4,100.00$3,400.00
2Corrugated med rem (X6060500)SF594$26.00$22.00
3Row/property corners (X6660445)EACH22$800.00$500.00
4Rem RE-erect EX sign (X7240600)EACH3$850.00$150.00
5Paint PVT mark curb (X7800200)LF220$6.75$6.25
6Handhole to BE adjust (X8140115)EACH7$5,865.00$7,500.00
7DBL handhole adjust (X8140116)EACH3$9,125.00$10,500
8Accessible ped signal (X8760200)EACH20$2,715.00$2,275.00
9Ped pushbutton post (X8760201)EACH5$3,620.00$15,000
10Det loop repl (X8860105)LF2,789$25.25$20.25
11Construction layout (Z0013798)LS1$28,000$46,000
12RR prot liability ins (Z0048665)LS1$7,500.00$82,750
13Trainees (Z0076600)HR1,000$0.80$0.80
14Trainees TPG (Z0076604)HR1,000$15.00$15.00
15Seeding CL 1A (25000110)ACRE0.25$8,250.00$7,200.00
16Nitrogen fert nutr (25000400)LB23$5.25$4.00
17Phosphorus fert nutr (25000500)LB23$5.25$4.00
18Potassium fert nutr (25000600)LB23$5.25$4.00
19Agr ground limestone (25000700)TON0.50$515.00$450.00
20Mulch method 2 (25100115)ACRE0.25$8,250.00$7,200.00
21Agg base cse A 2 (35100120)SY66$38.00$34.00
22PCC bse cse 10 (35300500)SY66$172.00$165.00
23Bit matls tack CT (40600290)LB16,168$2.15$2.96
24Long joint sealant (40600370)LF12,567$3.50$2.75
25Matl transfer device (40600405)TON4,821$6.50$6.27
26Temporary ramp (40600990)SY978$0.01$0.01
27HMA BC IL-19.0 N70 (40603085)TON2,893$155.00$129.26
28P HMA SC IL-9.5 D N70 (40604162)TON1,929$188.00$149.45
29Protective coat (42001300)SY342$0.01$0.01
30PC conc sidewalk 5 (42400200)SF2,429$20.75$25.00
31Detectable warnings (42400800)SF175$59.00$59.00
32HMA surf rem 3 3/4 (44000164)SY23,890$11.50$10.95
33Comb curb gutter rem (44000500)LF496$24.00$31.00
34Sidewalk rem (44000600)SF2,387$6.50$10.00
35Median removal (44003100)SF359$6.50$10.00
36Welded wire reinf (44200050)SY263$19.50$20.00
37CL B patch T2 14 (44201019)SY169$380.00$375.00
38CL B patch T3 14 (44201023)SY148$376.00$375.00
39CL B patch T4 14 (44201025)SY116$372.00$375.00
40Dowel bars 1 1/2 (44201299)EACH581$29.50$30.00
41CL C patch T1 8 (44201325)SY4$110.00$94.00
42CL C patch T2 8 (44201329)SY67$110.00$94.00
43CL C patch T3 8 (44201333)SY69$110.00$94.00
44Saw cuts (44213200)LF1,933$6.25$10.00
45Tie bars 3/4 (44213204)EACH67$22.00$25.00
46HMA shoulders (48203100)TON211$185.00$139.26
47Conc curb TB (60600605)LF26$83.00$74.00
48Comb CC&G TB6.18 (60604400)LF298$85.00$74.00
49Comb CC&G TB6.18 VWGF (60604900)LF25$85.00$74.00
50Conc med TSB6.06 (60619200)SF433$39.50$32.00
51Engr field office A (67000400)CAL MO6$3,200.00$2,500.00
52Mobilization (67100100)LS1$235,200$262,640
53TR cont & prot 701501 (70102620)LS1$6,250.00$51,600
54TR cont & prot 701502 (70102622)LS1$146,000$127,119
55TR cont & prot 701701 (70102635)LS1$4,000.00$975.00
56TR cont & prot 701801 (70102640)LS1$14,000$16,900
57TR cont surveillance (70103815)CAL DAY11$750.00$750.00
58Changeable message SN (70107025)CAL DAY470$50.00$38.00
59Night work zone light (70200100)LS1$25,000$138,792
60Short term pavt mking (70300100)LF1,551$4.50$4.43
61SHRT TRM pavt MK rem (70300150)SF259$17.00$0.01
62Temp PVT MK LTR & sym paint (70300211)SF794$0.01$0.01
63Temp PVT MK line 4 - paint (70300221)LF16,173$0.01$0.01
64Temp PVT MK line 8 - paint (70300251)LF116$0.01$0.01
65Temp PVT MK line 12 - paint (70300261)LF872$0.01$0.01
66Temp PVT MK line 24 - paint (70300281)LF320$0.01$0.01
67Sign panel T1 (72000100)SF20$93.00$45.00
68Pref PL PM TD STD LTR/sym (78004600)SF794$38.00$36.25
69Pref PL PM TD STD L4 (78004620)LF16,173$4.35$7.50
70Pref PL PM TD STD L 8 (78004640)LF116$7.65$21.25
71Pref PL PM TD STD L12 (78004660)LF872$16.50$27.50
72Pref PL PM TD STD L24 (78004720)LF320$22.50$44.75
73GRV RCSD PVT MRKG 5 (78011025)LF16,173$1.00$1.00
74GRV RCSD PVT MRKG 9 (78011045)LF116$3.20$1.00
75GRV RCSD PVT MRKG 13 (78011065)LF872$5.65$1.00
76GRV RCSD PVT MRKG 25 (78011125)LF320$13.30$1.00
77Curb reflectors (78200020)EACH21$12.00$11.25
78Raised ref PVT MK rem (78300200)EACH190$0.01$0.01
79PVT MKG rem WTR blast (78300202)SF7,774$0.01$0.01
80Undrgrd C PVC 1 1/2 (81028340)LF29$325.00$200.00
81Elcbl C signal 14 2C (87301215)LF1,093$8.75$20.00
82Elcbl C egrdc 6 1C (87301900)LF91$0.01$5.00
83Conc FDN TY A (87800100)LF13$1.00$1,150.00
84Ped SH LED 1F BM CDT (88102717)EACH10$2,250.00$875.00
85Ped SH LED 1F PM W CT (88102719)EACH10$875.00$875.00
86Mod EX contr (89502200)EACH3$3,275.00$2,700.00
87Remov EX TS equip (89502375)EACH3$3,025.00$2,400.00
IDOT contract 76M52: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of August 1, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy