IDOT contract 76N05 bid tabulation
Section (47,113)RS-4. Let by Illinois DOT on April 25, 2025, St.Clair, District 08. 2 bids received; low bid $7,874,830 by Christ Bros. Asphalt, Inc..
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 60
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Christ Bros. Asphalt, Inc. | $7,874,830 | Low |
| 2 | The Kilian Corporation | $8,240,607 | +5.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Christ Bros. Asphalt, Inc. | 2. The Kilian Corporation |
|---|---|---|---|---|---|
| 1 | Surf rem var DP (SPL) (X4400102) | SY | 372 | $74.06 | $21.50 |
| 2 | HMA surf rem var DP (X4401198) | SY | 128,480 | $8.86 | $10.45 |
| 3 | Aggregate SHLDS SPL (X4811800) | SY | 266 | $122.26 | $72.00 |
| 4 | GDRL post repair (X6330801) | EACH | 16 | $155.00 | $162.00 |
| 5 | Construction layout (Z0013798) | LS | 1 | $48,475 | $47,500 |
| 6 | Trainees (Z0076600) | HR | 2,000 | $0.80 | $0.80 |
| 7 | Trainees TPG (Z0076604) | HR | 2,000 | $15.00 | $15.00 |
| 8 | Tree remov 6-15 (20100110) | UNIT | 200 | $120.00 | $155.00 |
| 9 | Tree remov over 15 (20100210) | UNIT | 40 | $120.00 | $155.00 |
| 10 | Bit matls tack CT (40600290) | LB | 86,725 | $2.73 | $1.95 |
| 11 | Long joint sealant (40600370) | LF | 43,704 | $3.38 | $3.25 |
| 12 | Matl transfer device (40600405) | TON | 22,872 | $5.23 | $6.50 |
| 13 | Temporary ramp (40600990) | SY | 2,098 | $0.01 | $0.01 |
| 14 | HMA BC IL-19.0 N70 (40603085) | TON | 13,723 | $131.28 | $141.00 |
| 15 | HMA SC IL-9.5 C N70 (40604052) | TON | 9,149 | $133.54 | $139.00 |
| 16 | Bit matls PR CT (40800025) | LB | 768 | $5.80 | $3.50 |
| 17 | Bit matls tack CT (40800029) | LB | 70 | $17.58 | $3.50 |
| 18 | Incidental HMA surf (40800050) | TON | 87 | $478.63 | $535.00 |
| 19 | Welded wire reinf (42000060) | SY | 1,669 | $20.00 | $17.75 |
| 20 | Gutter rem (44000400) | LF | 272 | $25.00 | $26.50 |
| 21 | CL B patch T4 17 (44201053) | SY | 1,425 | $338.00 | $339.00 |
| 22 | CL B patch T2 17 (44201055) | SY | 646 | $338.00 | $345.00 |
| 23 | CL B patch T3 17 (44201057) | SY | 244 | $338.00 | $342.00 |
| 24 | Dowel bars 1 1/2 (44201299) | EACH | 2,365 | $30.00 | $27.00 |
| 25 | Saw cuts (44213200) | LF | 6,153 | $10.00 | $7.50 |
| 26 | Tie bars 3/4 (44213204) | EACH | 293 | $25.00 | $22.00 |
| 27 | Agg wedge SHLD type B (48102100) | TON | 1,504 | $78.78 | $58.00 |
| 28 | HMA shoulders (48203100) | TON | 4,079 | $138.95 | $140.00 |
| 29 | Class SI conc outlet (60600095) | CY | 1 | $2,200.00 | $2,250.00 |
| 30 | Concrete gutter TY A (60602500) | LF | 260 | $110.00 | $119.00 |
| 31 | SPBGR TY A 6FT posts (63000001) | LF | 1,038 | $29.95 | $31.50 |
| 32 | SPGR att to culvert (63000030) | LF | 31 | $298.95 | $315.00 |
| 33 | Traf bar term T6 (63100085) | EACH | 1 | $4,015.50 | $4,220.00 |
| 34 | TR bar TRM T1 SPL tan (63100167) | EACH | 7 | $3,490.10 | $3,665.00 |
| 35 | Guardrail remov (63200310) | LF | 1,018 | $7.85 | $8.25 |
| 36 | Engr field office A (67000400) | CAL MO | 8 | $2,500.00 | $3,000.00 |
| 37 | Mobilization (67100100) | LS | 1 | $658,832 | $849,400 |
| 38 | Traf cont-prot 701201 (70100450) | LS | 1 | $78,000 | $79,450 |
| 39 | Traf cont-prot 701306 (70100460) | LS | 1 | $283,230 | $158,375 |
| 40 | Traf cont-prot 701336 (70100600) | LS | 1 | $0.01 | $0.01 |
| 41 | Changeable message SN (70107025) | CAL DAY | 28 | $120.00 | $120.00 |
| 42 | Short term pavt mking (70300100) | LF | 18,090 | $2.54 | $3.50 |
| 43 | SHRT TRM pavt MK rem (70300150) | SF | 1,527 | $0.01 | $5.00 |
| 44 | Temp PVT MK LTR & sym paint (70300211) | SF | 63 | $0.01 | $0.01 |
| 45 | Temp PVT MK line 6 - paint (70300241) | LF | 113,722 | $0.01 | $0.01 |
| 46 | Temp PVT MK line 8 - paint (70300251) | LF | 579 | $0.01 | $0.01 |
| 47 | Temp PVT MK line 12 - paint (70300261) | LF | 542 | $0.01 | $0.01 |
| 48 | Temp PVT MK line 24 - paint (70300281) | LF | 30 | $0.01 | $0.01 |
| 49 | Terminal marker - DA (72501000) | EACH | 7 | $25.00 | $26.30 |
| 50 | THPL PVT MK LTR & sym (78000100) | SF | 63 | $15.00 | $15.80 |
| 51 | THPL PVT MK line 6 (78000400) | LF | 113,722 | $0.83 | $0.80 |
| 52 | THPL PVT MK line 8 (78000500) | LF | 579 | $11.00 | $10.55 |
| 53 | THPL PVT MK line 12 (78000600) | LF | 542 | $14.00 | $12.65 |
| 54 | THPL PVT MK line 24 (78000650) | LF | 30 | $17.00 | $15.80 |
| 55 | Pref PL PM TD STD L 6 (78004630) | LF | 720 | $8.00 | $6.85 |
| 56 | GRV RCSD PVT MRKG 7 (78011035) | LF | 720 | $3.00 | $2.15 |
| 57 | Raised refl pavt MKR (78100100) | EACH | 590 | $43.23 | $36.00 |
| 58 | Grdrail ref type A (78200005) | EACH | 40 | $12.00 | $12.50 |
| 59 | Raised ref PVT MK rem (78300200) | EACH | 590 | $0.01 | $0.01 |
| 60 | PVT MKG rem WTR blast (78300202) | SF | 57,866 | $0.01 | $0.01 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.