IDOT contract 76R36 bid tabulation

Section 82-8-BJR-BDR-BP-1. Let by Illinois DOT on June 12, 2026, St. Clair, District 08. 2 bids received; low bid $4,888,194 by The Kilian Corporation.

Owner
Illinois DOT
Letting
12 JUN 2026
Pay items
45
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1The Kilian Corporation$4,888,194Low
2Keeley & Sons, Inc.$5,153,969+5.0%
IDOT contract 76R36: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. The Kilian Corporation2. Keeley & Sons, Inc.
1Struct steel remov (X5051204)LB16,540$1.80$1.75
2Width restrict sign (X7200201)LS1$7,500.00$2,856.00
3C&D lead PT CL RS N1 (Z0007101)LS1$222,000$227,560
4C&D lead PT CL RS N2 (Z0007102)LS1$240,000$255,518
5C&D lead PT CL RS N3 (Z0007103)LS1$146,000$164,117
6C&D lead PT CL RS N4 (Z0007104)LS1$158,000$175,968
7Clean & PT STL BR N1 (Z0010501)LS1$148,000$167,722
8Clean & PT STL BR N2 (Z0010502)LS1$160,000$177,697
9Clean & PT STL BR N3 (Z0010503)LS1$98,000$106,762
10Clean & PT STL BR N4 (Z0010504)LS1$106,000$119,662
11Trainees (Z0076600)HR1,500$0.80$0.80
12Trainees TPG (Z0076604)HR1,500$15.00$15.00
13P bit matls tack CT (40600295)LB897$5.00$5.10
14HMA surf rem butt JT (40600982)SY3,966$10.00$15.30
15P HMA SC IL-9.5 E N90 (40604174)TON439$190.00$255.00
16HMA shoulders (48203100)TON290$190.00$204.00
17Conc rem (50102400)CY57.40$3,550.00$3,890.00
18Conc sup-STR (50300255)CY64.70$6,350.00$5,350.40
19BR deck grooving (50300260)SY5,821$11.00$9.45
20Protective coat (50300300)SY6,197$5.00$4.24
21F & E struct steel (50500405)LB16,540$7.50$9.55
22Reinf bars, epoxy CTD (50800205)LB10,580$3.50$3.55
23Bar splicers (50800515)EACH116$75.00$53.50
24Pref JT strip seal (52000110)LF356$575.00$587.90
25Deck slab rep (FD-T2) (53016002)SY35$2,250.00$2,390.85
26BR deck scar 2" (53101007)SY6,031$58.00$69.80
27BR DK mic C ovl 4 1/4" (53101616)SY6,031$168.00$169.85
28Traf bar term T6 (63100085)EACH8$4,225.00$4,105.50
29Guardrail remov (63200310)LF296$17.50$17.09
30Engr field office A (67000400)CAL MO5$3,600.00$3,500.00
31Mobilization (67100100)LS1$293,100$318,000
32Traf cont-prot 701402 (70100207)EACH4$47,175$39,870
33Traf cont-prot 701406 (70100701)EACH4$0.01$1,980.00
34Pavt MK blkout tape 5 (70107005)LF15,625$2.50$1.69
35Changeable message SN (70107025)CAL DAY344$85.00$37.49
36SHRT TRM pavt MK rem (70300150)SF6,510$1.00$1.79
37Temp PVT MK line 6 - paint (70300241)LF5,233$0.01$1.53
38Temp conc barrier (70400100)LF2,954$56.00$63.85
39Rel temp conc barrier (70400200)LF2,954$7.00$12.55
40Imp attn temp NRD TL3 (70600250)EACH4$6,250.00$5,490.00
41Imp attn rel NRD TL3 (70600350)EACH4$900.00$2,380.00
42Mod ureth PM line 6 (78009006)LF5,233$1.55$1.53
43Raised refl pavt MKR (78100100)EACH34$118.00$117.30
44Raised ref PVT MK rem (78300200)EACH34$6.00$25.00
45PVT MKG rem WTR blast (78300202)SF2,574$0.01$2.55
IDOT contract 76R36: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of June 12, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy