IDOT contract 76R36 bid tabulation
Section 82-8-BJR-BDR-BP-1. Let by Illinois DOT on June 12, 2026, St. Clair, District 08. 2 bids received; low bid $4,888,194 by The Kilian Corporation.
- Owner
- Illinois DOT
- Letting
- 12 JUN 2026
- Pay items
- 45
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | The Kilian Corporation | $4,888,194 | Low |
| 2 | Keeley & Sons, Inc. | $5,153,969 | +5.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. The Kilian Corporation | 2. Keeley & Sons, Inc. |
|---|---|---|---|---|---|
| 1 | Struct steel remov (X5051204) | LB | 16,540 | $1.80 | $1.75 |
| 2 | Width restrict sign (X7200201) | LS | 1 | $7,500.00 | $2,856.00 |
| 3 | C&D lead PT CL RS N1 (Z0007101) | LS | 1 | $222,000 | $227,560 |
| 4 | C&D lead PT CL RS N2 (Z0007102) | LS | 1 | $240,000 | $255,518 |
| 5 | C&D lead PT CL RS N3 (Z0007103) | LS | 1 | $146,000 | $164,117 |
| 6 | C&D lead PT CL RS N4 (Z0007104) | LS | 1 | $158,000 | $175,968 |
| 7 | Clean & PT STL BR N1 (Z0010501) | LS | 1 | $148,000 | $167,722 |
| 8 | Clean & PT STL BR N2 (Z0010502) | LS | 1 | $160,000 | $177,697 |
| 9 | Clean & PT STL BR N3 (Z0010503) | LS | 1 | $98,000 | $106,762 |
| 10 | Clean & PT STL BR N4 (Z0010504) | LS | 1 | $106,000 | $119,662 |
| 11 | Trainees (Z0076600) | HR | 1,500 | $0.80 | $0.80 |
| 12 | Trainees TPG (Z0076604) | HR | 1,500 | $15.00 | $15.00 |
| 13 | P bit matls tack CT (40600295) | LB | 897 | $5.00 | $5.10 |
| 14 | HMA surf rem butt JT (40600982) | SY | 3,966 | $10.00 | $15.30 |
| 15 | P HMA SC IL-9.5 E N90 (40604174) | TON | 439 | $190.00 | $255.00 |
| 16 | HMA shoulders (48203100) | TON | 290 | $190.00 | $204.00 |
| 17 | Conc rem (50102400) | CY | 57.40 | $3,550.00 | $3,890.00 |
| 18 | Conc sup-STR (50300255) | CY | 64.70 | $6,350.00 | $5,350.40 |
| 19 | BR deck grooving (50300260) | SY | 5,821 | $11.00 | $9.45 |
| 20 | Protective coat (50300300) | SY | 6,197 | $5.00 | $4.24 |
| 21 | F & E struct steel (50500405) | LB | 16,540 | $7.50 | $9.55 |
| 22 | Reinf bars, epoxy CTD (50800205) | LB | 10,580 | $3.50 | $3.55 |
| 23 | Bar splicers (50800515) | EACH | 116 | $75.00 | $53.50 |
| 24 | Pref JT strip seal (52000110) | LF | 356 | $575.00 | $587.90 |
| 25 | Deck slab rep (FD-T2) (53016002) | SY | 35 | $2,250.00 | $2,390.85 |
| 26 | BR deck scar 2" (53101007) | SY | 6,031 | $58.00 | $69.80 |
| 27 | BR DK mic C ovl 4 1/4" (53101616) | SY | 6,031 | $168.00 | $169.85 |
| 28 | Traf bar term T6 (63100085) | EACH | 8 | $4,225.00 | $4,105.50 |
| 29 | Guardrail remov (63200310) | LF | 296 | $17.50 | $17.09 |
| 30 | Engr field office A (67000400) | CAL MO | 5 | $3,600.00 | $3,500.00 |
| 31 | Mobilization (67100100) | LS | 1 | $293,100 | $318,000 |
| 32 | Traf cont-prot 701402 (70100207) | EACH | 4 | $47,175 | $39,870 |
| 33 | Traf cont-prot 701406 (70100701) | EACH | 4 | $0.01 | $1,980.00 |
| 34 | Pavt MK blkout tape 5 (70107005) | LF | 15,625 | $2.50 | $1.69 |
| 35 | Changeable message SN (70107025) | CAL DAY | 344 | $85.00 | $37.49 |
| 36 | SHRT TRM pavt MK rem (70300150) | SF | 6,510 | $1.00 | $1.79 |
| 37 | Temp PVT MK line 6 - paint (70300241) | LF | 5,233 | $0.01 | $1.53 |
| 38 | Temp conc barrier (70400100) | LF | 2,954 | $56.00 | $63.85 |
| 39 | Rel temp conc barrier (70400200) | LF | 2,954 | $7.00 | $12.55 |
| 40 | Imp attn temp NRD TL3 (70600250) | EACH | 4 | $6,250.00 | $5,490.00 |
| 41 | Imp attn rel NRD TL3 (70600350) | EACH | 4 | $900.00 | $2,380.00 |
| 42 | Mod ureth PM line 6 (78009006) | LF | 5,233 | $1.55 | $1.53 |
| 43 | Raised refl pavt MKR (78100100) | EACH | 34 | $118.00 | $117.30 |
| 44 | Raised ref PVT MK rem (78300200) | EACH | 34 | $6.00 | $25.00 |
| 45 | PVT MKG rem WTR blast (78300202) | SF | 2,574 | $0.01 | $2.55 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.