IDOT contract 76J62 bid tabulation
Section (31,410,410-1)RS-4,(82-7K)RS-1. Let by Illinois DOT on April 25, 2025, St.Clair, District 08. 2 bids received; low bid $14,154,479 by Christ Bros. Asphalt, Inc..
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 56
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Christ Bros. Asphalt, Inc. | $14,154,479 | Low |
| 2 | The Kilian Corporation | $14,380,024 | +2.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Christ Bros. Asphalt, Inc. | 2. The Kilian Corporation |
|---|---|---|---|---|---|
| 1 | Long par dep rem 3 (X4405030) | LF | 33,617 | $6.87 | $14.50 |
| 2 | PCC surf rem 1/2 (X4406804) | SY | 87,507 | $5.98 | $3.20 |
| 3 | Long part depth patch (X4420900) | TON | 1,850 | $239.02 | $150.00 |
| 4 | Det loop repl (X8860105) | LF | 4,260 | $30.00 | $37.00 |
| 5 | Trainees (Z0076600) | HR | 3,000 | $0.80 | $0.80 |
| 6 | Trainees TPG (Z0076604) | HR | 3,000 | $15.00 | $15.00 |
| 7 | Bit matls tack CT (40600290) | LB | 57,219 | $2.94 | $1.75 |
| 8 | P bit matls tack CT (40600295) | LB | 151,352 | $2.94 | $1.50 |
| 9 | Long joint sealant (40600370) | LF | 59,296 | $3.42 | $3.25 |
| 10 | Matl transfer device (40600405) | TON | 25,988 | $6.22 | $6.50 |
| 11 | PCC surf rem butt JT (40600985) | SY | 111 | $5.98 | $30.00 |
| 12 | Temporary ramp (40600990) | SY | 598 | $0.01 | $0.01 |
| 13 | HMA BC IL-9.5FG N90 (40602975) | TON | 11,772 | $144.13 | $156.00 |
| 14 | P HMA SC IL-9.5 E N90 (40604174) | TON | 14,126 | $159.13 | $175.00 |
| 15 | HMA surf rem 2 1/2 (44000159) | SY | 117,091 | $5.98 | $8.65 |
| 16 | CL A patch T1 11 (44200561) | SY | 21 | $540.00 | $475.00 |
| 17 | CL A patch T2 11 (44200565) | SY | 663 | $341.00 | $325.00 |
| 18 | CL A patch T3 11 (44200569) | SY | 341 | $334.00 | $320.00 |
| 19 | CL A patch T4 11 (44200571) | SY | 5,215 | $319.00 | $305.00 |
| 20 | Patch reinforcement (44213000) | SY | 6,256 | $66.00 | $65.00 |
| 21 | Saw cuts (44213200) | LF | 17,316 | $6.00 | $5.00 |
| 22 | Tie bars 1 (44213202) | EACH | 1,561 | $21.00 | $20.00 |
| 23 | Agg wedge SHLD type B (48102100) | TON | 1,062 | $93.33 | $72.00 |
| 24 | HMA shoulders (48203100) | TON | 12,761 | $149.98 | $141.00 |
| 25 | SPBGR TY A 6FT posts (63000001) | LF | 2,587.50 | $35.22 | $34.50 |
| 26 | Traf bar term T2 (63100045) | EACH | 2 | $1,750.00 | $2,340.00 |
| 27 | Traf bar term T5 (63100070) | EACH | 2 | $1,750.00 | $1,685.00 |
| 28 | Traf bar term T6 (63100085) | EACH | 8 | $4,000.00 | $5,150.00 |
| 29 | TR bar TRM T1 SPL tan (63100167) | EACH | 8 | $4,000.00 | $3,575.00 |
| 30 | Guardrail remov (63200310) | LF | 2,575 | $10.00 | $6.00 |
| 31 | Shoulder rum strip 16 (64200116) | LF | 114,718 | $0.91 | $0.38 |
| 32 | Engr field office A (67000400) | CAL MO | 6 | $3,000.00 | $3,000.00 |
| 33 | Mobilization (67100100) | LS | 1 | $1,383,487 | $1,233,000 |
| 34 | Traf cont-prot 701421 (70100310) | LS | 1 | $585,925 | $0.01 |
| 35 | Traf cont-prot 701422 (70100315) | EACH | 1 | $100.00 | $985,000 |
| 36 | Traf cont-prot 701411 (70100420) | EACH | 8 | $3,500.00 | $3,500.00 |
| 37 | TR cont & prot 701601 (70102630) | LS | 1 | $100.00 | $0.01 |
| 38 | TR cont & prot 701701 (70102635) | LS | 1 | $100.00 | $18,750 |
| 39 | Changeable message SN (70107025) | CAL DAY | 564 | $88.00 | $75.00 |
| 40 | Short term pavt mking (70300100) | LF | 7,448 | $2.82 | $4.50 |
| 41 | SHRT TRM pavt MK rem (70300150) | SF | 1,800 | $0.01 | $8.00 |
| 42 | Temp PVT MK LTR & sym paint (70300211) | SF | 300 | $0.01 | $0.01 |
| 43 | Temp PVT MK line 6 - paint (70300241) | LF | 132,563 | $0.01 | $0.01 |
| 44 | Temp PVT MK line 8 - paint (70300251) | LF | 7,630 | $0.01 | $0.01 |
| 45 | Temp PVT MK line 12 - paint (70300261) | LF | 966 | $0.01 | $0.01 |
| 46 | Temp PVT MK line 24 - paint (70300281) | LF | 172 | $0.01 | $0.01 |
| 47 | Terminal marker - DA (72501000) | EACH | 8 | $35.00 | $44.00 |
| 48 | THPL PVT MK LTR & sym (78000100) | SF | 300 | $9.00 | $8.80 |
| 49 | THPL PVT MK line 6 (78000400) | LF | 132,563 | $0.95 | $0.90 |
| 50 | THPL PVT MK line 8 (78000500) | LF | 7,630 | $1.20 | $1.20 |
| 51 | THPL PVT MK line 12 (78000600) | LF | 966 | $12.00 | $11.10 |
| 52 | THPL PVT MK line 24 (78000650) | LF | 172 | $15.00 | $13.25 |
| 53 | Raised refl pavt MKR (78100100) | EACH | 966 | $47.62 | $40.00 |
| 54 | Grdrail ref type A (78200005) | EACH | 67 | $9.00 | $12.50 |
| 55 | Raised ref PVT MK rem (78300200) | EACH | 709 | $0.01 | $0.01 |
| 56 | Locate undergr cable (80300100) | LF | 270 | $12.50 | $25.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.