IDOT contract 76B42 bid tabulation
Section 26BR,11BR-1. Let by Illinois DOT on February 27, 2026, Marion, District 08. 3 bids received; low bid $3,575,562 by C-Hill Civil Contractors, Inc..
- Owner
- Illinois DOT
- Letting
- 27 FEB 2026
- Pay items
- 113
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | C-Hill Civil Contractors, Inc. | $3,575,562 | Low |
| 2 | Samron Midwest Contracting, Inc. | $4,095,404 | +15% |
| 3 | Keeley & Sons, Inc. | $4,699,926 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. C-Hill Civil Contractors, Inc. | 2. Samron Midwest Contracting, Inc. | 3. Keeley & Sons, Inc. |
|---|---|---|---|---|---|---|
| 1 | Stone riprap CL A4 SP (X2810108) | SY | 37 | $165.00 | $30.00 | $178.90 |
| 2 | HMA base cse var DP (X3550015) | TON | 126 | $233.00 | $200.00 | $226.89 |
| 3 | Bar terminators (X5080530) | EACH | 478 | $23.50 | $40.00 | $48.85 |
| 4 | Memb WTRPRF sys B STR (X5810103) | SY | 141 | $44.50 | $25.00 | $69.80 |
| 5 | Row/property corners (X6660445) | EACH | 2 | $525.00 | $3,200.00 | $297.40 |
| 6 | Traf cont-prot BLR 21 (X7011800) | LS | 1 | $4,800.00 | $25,000 | $10,200 |
| 7 | Detour signing (X7200203) | LS | 1 | $31,500 | $70,000 | $30,090 |
| 8 | Construction layout (Z0013798) | LS | 1 | $45,000 | $86,000 | $54,570 |
| 9 | Section corner MKRS (Z0064505) | EACH | 1 | $1,400.00 | $250.00 | $815.45 |
| 10 | Surv monument cov asy (Z0070100) | EACH | 3 | $210.00 | $550.00 | $815.45 |
| 11 | Trainees (Z0076600) | HR | 2,500 | $0.80 | $0.80 | $0.80 |
| 12 | Trainees TPG (Z0076604) | HR | 2,500 | $15.00 | $15.00 | $15.00 |
| 13 | Tree remov 6-15 (20100110) | UNIT | 138 | $45.50 | $40.00 | $48.90 |
| 14 | Tree remov over 15 (20100210) | UNIT | 54 | $52.50 | $40.00 | $73.40 |
| 15 | Earth excavation (20200100) | CY | 2,934 | $16.90 | $10.00 | $27.30 |
| 16 | Channel excavation (20300100) | CY | 1,380 | $28.00 | $15.00 | $49.85 |
| 17 | Furnished excavation (20400800) | CY | 1,930 | $21.60 | $40.00 | $49.00 |
| 18 | Seeding CL 2A (25000210) | ACRE | 2.50 | $1,740.00 | $5,000.00 | $4,080.00 |
| 19 | Nitrogen fert nutr (25000400) | LB | 225 | $1.27 | $1.50 | $4.08 |
| 20 | Phosphorus fert nutr (25000500) | LB | 225 | $1.27 | $1.50 | $4.08 |
| 21 | Potassium fert nutr (25000600) | LB | 225 | $1.27 | $1.50 | $4.08 |
| 22 | Mulch method 2 (25100115) | ACRE | 2.50 | $2,075.00 | $3,000.00 | $4,080.00 |
| 23 | Erosion contr blanket (25100630) | SY | 948 | $2.50 | $2.00 | $5.10 |
| 24 | Temp eros contr seed (28000250) | LB | 500 | $0.01 | $4.00 | $6.12 |
| 25 | Temp ditch checks (28000305) | LF | 420 | $11.00 | $10.00 | $8.16 |
| 26 | Perimeter eros bar (28000400) | LF | 3,007 | $5.00 | $5.00 | $3.06 |
| 27 | Stone riprap CL A4 (28100107) | SY | 626 | $67.75 | $70.00 | $67.55 |
| 28 | Stone riprap CL A5 (28100109) | SY | 1,230 | $86.50 | $100.00 | $73.20 |
| 29 | Filter fabric (28200200) | SY | 1,856 | $3.30 | $1.50 | $5.85 |
| 30 | Sub gran mat A (31100100) | TON | 6,904 | $34.00 | $45.00 | $36.80 |
| 31 | Sub gran mat C (31101900) | TON | 171 | $58.50 | $70.00 | $42.80 |
| 32 | Agg surf course TY B (40200800) | TON | 391 | $44.50 | $50.00 | $42.80 |
| 33 | Aggregate-temp access (40201000) | TON | 50 | $43.00 | $50.00 | $40.00 |
| 34 | Bit matls PR CT (40600275) | LB | 7,384 | $1.65 | $0.01 | $1.58 |
| 35 | Bit matls tack CT (40600290) | LB | 2,500 | $6.90 | $0.01 | $6.68 |
| 36 | Long joint sealant (40600370) | LF | 1,112 | $16.50 | $17.00 | $16.05 |
| 37 | HMA surf rem butt JT (40600982) | SY | 469 | $15.75 | $30.00 | $39.73 |
| 38 | HMA SC IL-9.5 C N70 (40604052) | TON | 116 | $260.00 | $310.00 | $251.71 |
| 39 | HMA pavt FD 11 (40701901) | SY | 1,978 | $164.75 | $105.00 | $160.07 |
| 40 | Welded wire reinf (42000060) | SY | 124 | $10.25 | $10.00 | $15.55 |
| 41 | PVT con PCC BR app SL (42000080) | SY | 124 | $204.00 | $200.00 | $367.90 |
| 42 | Protective coat (42001300) | SY | 124 | $6.95 | $1.00 | $3.95 |
| 43 | Pavement rem (44000100) | SY | 1,040 | $15.75 | $20.00 | $17.35 |
| 44 | Curb rem (44000300) | LF | 64 | $9.30 | $3.00 | $15.90 |
| 45 | Paved SHLD removal (44004250) | SY | 218 | $25.60 | $20.00 | $19.80 |
| 46 | Aggregate SHLDS B 6 (48101500) | SY | 494 | $25.30 | $25.00 | $17.80 |
| 47 | HMA shoulders 8 (48203029) | SY | 988 | $127.60 | $100.00 | $124.03 |
| 48 | Rem exist struct N1 (50100300) | EACH | 1 | $32,400 | $75,000 | $59,800 |
| 49 | Rem exist struct N2 (50100400) | EACH | 1 | $16,905 | $10,000 | $59,800 |
| 50 | Rem exist struct N3 (50100500) | EACH | 1 | $16,905 | $10,000 | $59,800 |
| 51 | Rem exist struct N4 (50100600) | EACH | 1 | $16,905 | $10,000 | $59,800 |
| 52 | Pipe culvert remov (50105220) | LF | 141 | $17.50 | $3.00 | $17.10 |
| 53 | Structure excavation (50200100) | CY | 20 | $46.20 | $85.00 | $93.20 |
| 54 | Cofferdam excavation (50200300) | CY | 332 | $28.00 | $0.01 | $63.65 |
| 55 | Cofferdam typ 1 loc 1 (50201101) | EACH | 1 | $0.01 | $0.01 | $59,800 |
| 56 | Cofferdam typ 1 loc 2 (50201102) | EACH | 1 | $0.01 | $0.01 | $59,800 |
| 57 | Floor drains (50300100) | EACH | 12 | $645.00 | $550.00 | $987.25 |
| 58 | Conc struct (50300225) | CY | 167.60 | $1,300.00 | $2,000.00 | $1,487.20 |
| 59 | Conc sup-STR (50300255) | CY | 208.40 | $2,175.00 | $2,325.00 | $1,890.35 |
| 60 | BR deck grooving (50300260) | SY | 862 | $12.70 | $10.00 | $10.20 |
| 61 | Protective coat (50300300) | SY | 951 | $4.25 | $1.50 | $3.95 |
| 62 | Conc supstr app slab (50301350) | CY | 106 | $525.00 | $750.00 | $547.80 |
| 63 | F & E struct steel (50500105) | LS | 1 | $451,000 | $543,000 | $592,890 |
| 64 | Stud shear connectors (50500505) | EACH | 3,744 | $3.70 | $4.00 | $5.15 |
| 65 | Reinf bars, epoxy CTD (50800205) | LB | 109,530 | $1.43 | $2.00 | $1.95 |
| 66 | Fur STL pile HP14X89 (51201900) | LF | 1,404 | $77.00 | $130.00 | $137.80 |
| 67 | Driving piles (51202305) | LF | 1,404 | $0.01 | $0.01 | $0.01 |
| 68 | Test pile ST HP14X89 (51203900) | EACH | 2 | $41,000 | $0.01 | $29,870 |
| 69 | Name plates (51500100) | EACH | 1 | $880.00 | $875.00 | $1,450.00 |
| 70 | Anchor bolts 3/4 (52100510) | EACH | 24 | $124.00 | $45.00 | $92.70 |
| 71 | Anchor bolts 1 (52100520) | EACH | 24 | $135.00 | $45.00 | $107.30 |
| 72 | Box cul end sec C1 (54001001) | EACH | 2 | $25,000 | $23,000 | $39,870 |
| 73 | Box cul end sec C2 (54001002) | EACH | 2 | $23,750 | $21,000 | $43,760 |
| 74 | Box cul end sec C3 (54001003) | EACH | 2 | $22,500 | $20,000 | $49,870 |
| 75 | PCBC 10X4 (54011004) | LF | 28 | $1,017.00 | $1,500.00 | $1,987.00 |
| 76 | PCBC 10X5 (54011005) | LF | 26 | $1,100.00 | $1,750.00 | $2,101.55 |
| 77 | PCBC 10X6 (54011006) | LF | 26 | $1,125.00 | $1,800.00 | $2,789.20 |
| 78 | P cul CL D 1 15 (542D0220) | LF | 30 | $74.00 | $65.00 | $59.80 |
| 79 | P cul CL D 1 24 (542D0229) | LF | 50 | $67.00 | $60.00 | $87.20 |
| 80 | P cul CL D 1 30 (542D0235) | LF | 64 | $90.00 | $65.00 | $107.20 |
| 81 | P cul CL D 1 eqrs 36 (542D5491) | LF | 58 | $97.00 | $80.00 | $117.80 |
| 82 | Metal FL end sec 15" (54262715) | EACH | 2 | $500.00 | $120.00 | $797.40 |
| 83 | Metal FL end sec 24" (54262724) | EACH | 2 | $700.00 | $240.00 | $947.30 |
| 84 | Metal FL end sec 30" (54262730) | EACH | 2 | $1,155.00 | $1,000.00 | $1,497.80 |
| 85 | Metal FL ES EQ RS 36" (54262836) | EACH | 2 | $1,575.00 | $1,250.00 | $1,892.40 |
| 86 | Granular backfill STR (58600101) | CY | 430 | $96.00 | $60.00 | $63.70 |
| 87 | Geocomposite wall DR (59100100) | SY | 211 | $27.00 | $8.00 | $39.80 |
| 88 | Conc HDWL for P drain (60100060) | EACH | 4 | $165.00 | $940.00 | $587.30 |
| 89 | P undr for struct 4 (60146304) | LF | 170 | $38.00 | $30.00 | $43.20 |
| 90 | SPBGR TY A 6FT posts (63000001) | LF | 200 | $36.75 | $40.00 | $35.70 |
| 91 | Traf bar term T6 (63100085) | EACH | 4 | $4,935.00 | $5,500.00 | $4,794.00 |
| 92 | TR bar TRM T1 SPL tan (63100167) | EACH | 4 | $3,360.00 | $3,700.00 | $3,264.00 |
| 93 | Guardrail remov (63200310) | LF | 531 | $8.00 | $6.00 | $7.90 |
| 94 | Shoulder rum strip 8 (64200108) | LF | 2,035 | $1.80 | $6.00 | $1.79 |
| 95 | Fur erect row markers (66600105) | EACH | 9 | $550.00 | $400.00 | $597.00 |
| 96 | RE-erect row markers (66600205) | EACH | 2 | $490.00 | $300.00 | $688.30 |
| 97 | Perm surv MKRS T1 (66700205) | EACH | 2 | $2,275.00 | $250.00 | $870.90 |
| 98 | Engr field office A (67000400) | CAL MO | 12 | $1,900.00 | $0.01 | $4,980.00 |
| 99 | Mobilization (67100100) | LS | 1 | $102,200 | $245,000 | $267,890 |
| 100 | Changeable message SN (70107025) | CAL DAY | 520 | $51.45 | $65.00 | $35.00 |
| 101 | Short term pavt mking (70300100) | LF | 192 | $2.10 | $2.50 | $10.00 |
| 102 | SHRT TRM pavt MK rem (70300150) | SF | 64 | $7.50 | $1.50 | $20.00 |
| 103 | Temp PVT MK line 4 - paint (70300221) | LF | 3,020 | $0.01 | $0.50 | $1.64 |
| 104 | Sign panel T1 (72000100) | SF | 6.30 | $45.00 | $45.00 | $147.70 |
| 105 | Object marker T3 (72500300) | EACH | 12 | $360.00 | $330.00 | $257.10 |
| 106 | Terminal marker - DA (72501000) | EACH | 4 | $52.50 | $60.00 | $51.00 |
| 107 | Teles STL sin support (72800100) | LF | 15 | $23.50 | $25.00 | $85.00 |
| 108 | Mod ureth PM line 6 (78009006) | LF | 3,020 | $5.75 | $5.50 | $4.59 |
| 109 | Raised refl pavt MKR (78100100) | EACH | 15 | $131.00 | $400.00 | $127.50 |
| 110 | Grdrail ref type A (78200005) | EACH | 8 | $10.50 | $12.00 | $10.20 |
| 111 | Barr wall ref type B (78200010) | EACH | 12 | $20.00 | $22.00 | $37.90 |
| 112 | Raised ref PVT MK rem (78300200) | EACH | 6 | $16.00 | $0.01 | $10.00 |
| 113 | PVT MKG rem grinding (78300201) | SF | 1,007 | $0.01 | $8.00 | $6.63 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.