IDOT contract 76A37 bid tabulation
Section 29-2BR. Let by Illinois DOT on February 27, 2026, Marion, District 08. 2 bids received; low bid $4,343,470 by Samron Midwest Contracting, Inc..
- Owner
- Illinois DOT
- Letting
- 27 FEB 2026
- Pay items
- 73
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Samron Midwest Contracting, Inc. | $4,343,470 | Low |
| 2 | Keeley & Sons, Inc. | $4,823,383 | +11% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Samron Midwest Contracting, Inc. | 2. Keeley & Sons, Inc. |
|---|---|---|---|---|---|
| 1 | Bar terminators (X5080530) | EACH | 422 | $28.00 | $47.85 |
| 2 | Drainage scuppr DS-11 (X5230174) | EACH | 6 | $1,900.00 | $2,780.00 |
| 3 | Traf cont & prot SPL (X7010216) | LS | 1 | $3,700.00 | $11,890 |
| 4 | Rem & rein sign panel (X7200075) | SF | 57 | $29.00 | $167.85 |
| 5 | Detour signing (X7200203) | LS | 1 | $34,000 | $11,315 |
| 6 | Construction layout (Z0013798) | LS | 1 | $75,000 | $63,750 |
| 7 | Trainees (Z0076600) | HR | 2,500 | $0.80 | $0.80 |
| 8 | Trainees TPG (Z0076604) | HR | 2,500 | $15.00 | $15.00 |
| 9 | Tree remov acres (20100500) | ACRE | 0.25 | $100,000 | $27,890 |
| 10 | Earth excavation (20200100) | CY | 409 | $60.00 | $38.85 |
| 11 | Channel excavation (20300100) | CY | 1,635 | $65.00 | $39.15 |
| 12 | Seeding CL 2A (25000210) | ACRE | 0.25 | $9,500.00 | $22,440 |
| 13 | Nitrogen fert nutr (25000400) | LB | 9 | $1.50 | $8.16 |
| 14 | Phosphorus fert nutr (25000500) | LB | 9 | $1.50 | $89.76 |
| 15 | Potassium fert nutr (25000600) | LB | 9 | $1.50 | $8.16 |
| 16 | Mulch method 2 (25100115) | ACRE | 0.25 | $4,000.00 | $12,240 |
| 17 | Temp eros contr seed (28000250) | LB | 9 | $25.00 | $18.36 |
| 18 | Temp ditch checks (28000305) | LF | 10 | $11.00 | $48.96 |
| 19 | Perimeter eros bar (28000400) | LF | 1,183 | $3.00 | $4.08 |
| 20 | Stone riprap CL A5 (28100109) | SY | 2,546 | $125.00 | $67.35 |
| 21 | Filter fabric (28200200) | SY | 2,546 | $4.00 | $6.85 |
| 22 | Agg subgrade impr 12 (30300112) | SY | 338 | $36.00 | $38.90 |
| 23 | Sub gran mat C (31102000) | CY | 7 | $128.00 | $217.90 |
| 24 | Bit matls PR CT (40600275) | LB | 1,396 | $2.00 | $4.65 |
| 25 | Bit matls tack CT (40600290) | LB | 335 | $0.01 | $22.00 |
| 26 | HMA pavt FD 11 (40701901) | SY | 255 | $325.00 | $446.74 |
| 27 | PVT con PCC BR app SL (42000080) | SY | 107 | $250.00 | $206.15 |
| 28 | Pavement rem (44000100) | SY | 782 | $25.00 | $18.65 |
| 29 | Aggregate SHLDS A 6 (48100500) | SY | 449 | $29.00 | $21.80 |
| 30 | HMA shoulders 8 (48203029) | SY | 406 | $197.00 | $247.37 |
| 31 | Rem exist struct (50100100) | EACH | 1 | $415,000 | $197,310 |
| 32 | Structure excavation (50200100) | CY | 369 | $26.00 | $33.50 |
| 33 | Cofferdam excavation (50200300) | CY | 97 | $112.00 | $79.80 |
| 34 | Rock exc struct (50200400) | CY | 50 | $270.00 | $497.80 |
| 35 | Cofferdam typ 2 loc 1 (50201121) | EACH | 1 | $0.01 | $187,550 |
| 36 | Cofferdam typ 2 loc 2 (50201122) | EACH | 1 | $0.01 | $187,550 |
| 37 | Floor drains (50300100) | EACH | 12 | $523.00 | $1,315.00 |
| 38 | Conc struct (50300225) | CY | 221.50 | $1,350.00 | $1,795.50 |
| 39 | Conc sup-STR (50300255) | CY | 326.60 | $1,850.00 | $1,897.10 |
| 40 | BR deck grooving (50300260) | SY | 1,010 | $10.00 | $28.21 |
| 41 | Protective coat (50300300) | SY | 1,427 | $1.50 | $5.95 |
| 42 | Conc supstr app slab (50301350) | CY | 94.80 | $712.00 | $497.85 |
| 43 | F & E struct steel (50500105) | LS | 1 | $1,100,000 | $1,297,650 |
| 44 | Stud shear connectors (50500505) | EACH | 6,732 | $4.00 | $4.25 |
| 45 | Reinf bars, epoxy CTD (50800205) | LB | 137,340 | $2.00 | $1.90 |
| 46 | Fur STL pile HP14X89 (51201900) | LF | 280 | $174.00 | $127.80 |
| 47 | Fur STL pile HP14X117 (51202100) | LF | 408 | $110.00 | $167.90 |
| 48 | Driving piles (51202305) | LF | 280 | $0.01 | $0.01 |
| 49 | Test pile ST HP14X89 (51203900) | EACH | 2 | $3,258.00 | $27,890 |
| 50 | Drill & set piles (IS) (51265001) | CF | 78 | $77.00 | $151.15 |
| 51 | Drill & set piles (IR) (51265002) | CF | 552 | $112.00 | $178.15 |
| 52 | Name plates (51500100) | EACH | 1 | $956.00 | $1,655.00 |
| 53 | Anchor bolts 3/4 (52100510) | EACH | 24 | $88.00 | $119.80 |
| 54 | Anchor bolts 1 (52100520) | EACH | 24 | $94.00 | $127.10 |
| 55 | Granular backfill STR (58600101) | CY | 234 | $77.00 | $73.45 |
| 56 | P undr for struct 4 (60146304) | LF | 136 | $38.00 | $47.80 |
| 57 | SPBGR TY A 6FT posts (63000001) | LF | 575 | $34.00 | $29.58 |
| 58 | Traf bar term T6 (63100085) | EACH | 4 | $4,964.00 | $4,386.00 |
| 59 | TR bar TRM T1 SPL tan (63100167) | EACH | 4 | $3,900.00 | $3,366.00 |
| 60 | Guardrail remov (63200310) | LF | 929 | $10.00 | $8.85 |
| 61 | Non SPL waste disposl (66900200) | CY | 104 | $90.00 | $136.28 |
| 62 | Soil disposal analy (66900530) | EACH | 1 | $1,700.00 | $2,250.00 |
| 63 | Reg sub P-const plan (66901001) | LS | 1 | $3,500.00 | $7,370.00 |
| 64 | Reg sub F con report (66901003) | LS | 1 | $1,200.00 | $7,370.00 |
| 65 | Reg sub mon (66901006) | CAL DAY | 10 | $1,300.00 | $300.00 |
| 66 | Engr field office A (67000400) | CAL MO | 8 | $1,900.00 | $4,780.00 |
| 67 | Mobilization (67100100) | LS | 1 | $261,000 | $288,450 |
| 68 | Changeable message SN (70107025) | CAL DAY | 260 | $63.00 | $43.35 |
| 69 | Terminal marker - DA (72501000) | EACH | 4 | $60.00 | $51.00 |
| 70 | Mod ureth PM line 6 (78009006) | LF | 957 | $13.00 | $10.97 |
| 71 | Raised refl pavt MKR (78100100) | EACH | 2 | $780.00 | $3,570.00 |
| 72 | Grdrail ref type A (78200005) | EACH | 18 | $12.00 | $10.20 |
| 73 | Barr wall ref type C (78200011) | EACH | 16 | $28.00 | $35.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.