IDOT contract 76T17 bid tabulation

Section 580-BR-1. Let by Illinois DOT on September 19, 2025, St.Clair, District 08. 2 bids received; low bid $13,758,278 by Keeley & Sons, Inc..

Owner
Illinois DOT
Letting
19 SEP 2025
Pay items
142
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Keeley & Sons, Inc.$13,758,278Low
2Millstone Weber LLC$16,029,615+17%
IDOT contract 76T17: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Keeley & Sons, Inc.2. Millstone Weber LLC
1Shoulder inlet with curb (X1200234)EACH2$11,335$7,400.00
2Swing gate removal (X2300024)EACH1$10,890$530.00
3Temp pavt removal (X4400110)SY1,806$21.85$8.00
4BR deck grooving long (X5030250)SY1,874$13.93$10.75
5Bar terminators (X5080530)EACH1,426$37.85$38.00
6Temp storm sewer 24 (X550A624)LF133$63.15$110.00
7Conc barrier base SPL (X6370048)LF61$89.75$220.00
8Conc bar wall SPL (X6370050)LF61$497.80$310.00
9Traf cont & prot SPL (X7010216)LS1$121,890$101,000
10Width restrict sign (X7200201)LS1$2,014.50$1,500.00
11RRPM reflector removl (X7830050)EACH58$25.50$20.00
12RRPM reflector replac (X7830052)EACH58$25.50$75.00
13Temp TR signal timing (X8900104)EACH1$31,008$15,000
14Approach slab rem (Z0004552)SY256$47.90$120.00
15Construction layout (Z0013798)LS1$76,500$322,000
16Tubular marker (Z0024475)EACH20$89.76$130.00
17Diamond grind BR sec (Z0029090)SY3,464$13.95$14.50
18Temp pavement (Z0062456)SY3,297$103.85$99.00
19Trainees (Z0076600)HR3,500$0.80$0.80
20Trainees TPG (Z0076604)HR3,500$15.00$15.00
21Earth excavation (20200100)CY3,320$27.85$19.25
22Furnished excavation (20400800)CY1,665$31.15$13.00
23Trench backfill (20800150)CY191$67.90$29.75
24Seeding CL 2A (25000210)ACRE2$4,080.00$2,000.00
25Nitrogen fert nutr (25000400)LB154$7.14$7.80
26Phosphorus fert nutr (25000500)LB154$7.14$7.80
27Potassium fert nutr (25000600)LB154$7.14$7.80
28Erosion contr blanket (25100630)SY8,264$3.17$2.50
29Temp eros contr seed (28000250)LB171$5.61$6.50
30Temp ditch checks (28000305)LF227$30.60$16.00
31Inlet & pipe protect (28000500)EACH17$224.40$140.00
32Stone riprap CL A1 (28100101)SY126$83.85$20.00
33Stone riprap CL A3 (28100105)SY38$97.80$31.00
34Stone riprap CL A4 (28100107)SY817$63.45$110.00
35Filter fabric (28200200)SY662$4.95$10.50
36Agg subgrade improve (30300001)CY136$57.60$51.00
37Agg subgrade impr 12 (30300112)SY10,434$23.95$18.72
38Sub gran mat B 4 (31101200)SY1,576$11.80$8.20
39Stab subbase 4 (31200100)SY10,434$36.66$36.00
40HMA surf rem butt JT (40600982)SY461$39.74$39.00
41HMA SC IL-9.5 D N90 (40604064)TON40$304.49$300.00
42Bit matls tack CT (40800029)LB5,231$0.02$0.01
43Welded wire reinf (42000060)SY391$15.65$29.75
44PVT con PCC BR app SL (42000080)SY559$177.80$190.00
45PCC PVT 10 1/2 jointd (42000511)SY5,693$113.85$160.00
46PC conc sidewalk 5 (42400200)SF161$21.45$15.75
47Detectable warnings (42400800)SF25$157.85$71.00
48Pavement rem (44000100)SY6,350$24.48$23.00
49Paved SHLD removal (44004250)SY2,751$10.20$12.75
50Aggregate SHLDS B 8 (48101600)SY573$18.95$17.75
51HMA shoulders 10 1/2 (48203039)SY671$161.10$160.00
52PCC shoulders 10 1/2 (48300510)SY3,102$103.45$150.00
53Rem exist struct N1 (50100300)EACH1$175,000$415,000
54Rem exist struct N2 (50100400)EACH1$175,000$410,000
55Structure excavation (50200100)CY2,095$29.85$36.00
56Cofferdam excavation (50200300)CY5,753$37.85$36.00
57Cofferdam typ 2 loc 1 (50201121)EACH1$163,455$470,000
58Cofferdam typ 2 loc 2 (50201122)EACH1$163,455$480,000
59Cofferdam typ 2 loc 3 (50201123)EACH1$163,455$415,000
60Cofferdam typ 2 loc 4 (50201124)EACH1$163,455$415,000
61Conc struct (50300225)CY1,116$847.65$1,300.00
62Conc sup-STR (50300255)CY1,066$1,665.45$1,600.00
63Seal coat conc (50300265)CY2,051$257.85$120.00
64Protective coat (50300300)SY4,090$4.90$3.50
65Conc supstr app slab (50301350)CY336$449.70$760.00
66F&E PP con beam IL36N (50401315)LF2,838$511.35$550.00
67Reinf bars, epoxy CTD (50800205)LB574,320$1.85$1.50
68Mechanical splicers (50800530)EACH34$111.45$60.00
69Fur STL pile HP14X89 (51201900)LF5,659$117.45$110.00
70Fur STL pile HP14X102 (51202000)LF2,817$123.90$110.00
71Driving piles (51202305)LF8,476$0.01$0.01
72Test pile ST HP14X89 (51203900)EACH1$33,890$2,700.00
73Name plates (51500100)EACH2$1,650.00$2,000.00
74Temp SHT piling (52200010)SF1,131$43.85$29.50
75Concrete collar (54248510)CY1$1,980.00$910.00
76Metal FL end sec 12" (54262712)EACH5$697.85$440.00
77Metal FL end sec 24" (54262724)EACH1$1,120.00$890.00
78Storm sew CL A 1 12 (550A0050)LF447$63.65$110.00
79Storm sew CL A 2 6 (550A0326)LF6$79.80$150.00
80Storm sew CL A 2 12 (550A0340)LF161$61.45$120.00
81Storm sewer rem 6 (55100200)LF6$147.90$34.00
82Storm sewer rem 12 (55100500)LF161$21.65$26.00
83Storm sewer rem 24 (55101200)LF211$27.90$15.75
84Granular backfill STR (58600101)CY958$57.90$73.00
85Pipe drains CS 12 (60103500)LF271$59.80$43.00
86P undr for struct 4 (60146304)LF314$13.65$23.50
87Man TA 4 dia T1F OL (60218300)EACH1$4,680.00$4,100.00
88Man TA 4 dia T1F CL (60218400)EACH3$4,675.00$4,500.00
89Man TA 4 dia T6F&G (60218900)EACH1$4,675.00$5,100.00
90Man TA 4 dia T8G (60219000)EACH1$4,675.00$5,100.00
91Man TA 4 dia T20F&G (60219510)EACH1$4,980.00$5,100.00
92Man TA 6 dia T1F CL (60223800)EACH1$6,315.45$8,700.00
93Inlets TA T3F&G (60235700)EACH1$3,780.00$3,600.00
94Inlets TA T6F&G (60236100)EACH1$3,870.00$3,600.00
95Inlets TA T8G (60236200)EACH2$3,870.00$4,000.00
96Inlets TA T20F&G (60237420)EACH1$3,980.00$4,000.00
97Remov manholes (60500040)EACH1$589.15$1,100.00
98Remov inlets (60500060)EACH1$589.15$1,100.00
99Comb CC&G TY B-6.24 (60605000)LF35$77.80$85.00
100Comb CC&G TM6.24 (60610400)LF611$53.65$75.00
101Conc median surf 4 (60618300)SF2,009$8.85$11.00
102SPBGR TY A 6FT posts (63000001)LF263$31.62$30.00
103Traf bar term T6 (63100085)EACH3$3,748.50$4,600.00
104TR bar TRM T1 SPL tan (63100167)EACH3$3,442.50$3,800.00
105Guardrail remov (63200310)LF689$8.93$5.00
106Imp atten FRD wid TL3 (64300370)EACH1$42,381$45,000
107Non SPL waste disposl (66900200)CY2,980$130.97$82.00
108Soil disposal analy (66900530)EACH1$1,479.00$1,400.00
109Reg sub P-const plan (66901001)LS1$2,244.00$2,500.00
110Reg sub F con report (66901003)LS1$2,244.00$2,700.00
111Reg sub mon (66901006)CAL DAY29$1,122.00$950.00
112Engr field office A (67000400)CAL MO30$4,980.00$5,100.00
113Mobilization (67100100)LS1$825,000$960,000
114Changeable message SN (70107025)CAL DAY530$37.23$88.00
115SHRT TRM pavt MK rem (70300150)SF12,186$1.53$0.75
116Temp PVT MK L4 T4 tape (70307120)LF36,283$1.02$3.30
117Temp PVT MK L24 T4 tape (70307210)LF11$10.20$25.00
118Temp conc barrier (70400100)LF6,338$39.02$37.00
119Pin temp conc barrier (70400125)EACH780$30.86$27.75
120Rel temp conc barrier (70400200)LF4,375$2.30$4.40
121Imp attn temp FRN TL2 (70600255)EACH2$10,200$11,300
122Imp attn rel FRN TL2 (70600322)EACH6$2,218.50$2,400.00
123Sign panel T1 (72000100)SF16$25.50$110.00
124Sign panel T2 (72000200)SF36$20.91$100.00
125Remov sin pan assy TA (72400100)EACH5$190.45$750.00
126Remov sin pan assy TB (72400200)EACH5$190.45$750.00
127Reloc sign panel T1 (72400710)SF62$16.32$73.00
128Object marker T1 (72500100)EACH1$127.50$50.00
129Terminal marker - DA (72501000)EACH4$42.84$44.00
130Teles STL sin support (72800100)LF196$19.89$49.00
131THPL PVT MK line 4 (78000200)LF373$1.02$1.00
132THPL PVT MK line 6 (78000400)LF10,662$1.56$1.50
133THPL PVT MK line 12 (78000600)LF132$5.10$5.00
134THPL PVT MK line 24 (78000650)LF84$10.20$10.00
135Mod ureth PM LTR-sym (78009000)SF94$15.30$15.00
136Mod ureth PM line 6 (78009006)LF11,348$1.64$1.60
137Mod ureth PM line 12 (78009012)LF717$15.30$15.00
138Raised refl pavt MKR (78100100)EACH87$76.50$150.00
139Grdrail ref type A (78200005)EACH4$12.24$10.00
140Barr wall ref type C (78200011)EACH4$15.30$10.00
141Raised ref PVT MK rem (78300200)EACH35$10.20$60.00
142PVT MKG rem WTR blast (78300202)SF5,411$2.04$2.00
IDOT contract 76T17: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of September 19, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way