A. C. Pavement Striping Co. submitted 95 bids on Illinois DOT contracts in the data, from 15 JAN 2021 to 18 SEP 2026, and was the low bidder on 29 of them (31%). When it was not low, its total sat a median +23% above the low bid.
- Owner
- Illinois DOT
- Low bid volume
- $28,000,450
- Latest bid
- 18 SEP 2026
- Data through
- 18 SEP 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2021 | 30 | 7 | 23% |
| 2022 | 15 | 4 | 27% |
| 2023 | 11 | 2 | 18% |
| 2024 | 11 | 4 | 36% |
| 2025 | 13 | 6 | 46% |
| 2026 | 15 | 6 | 40% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 06 | 28 | 13 | 46% |
| District 04 | 14 | 5 | 36% |
| District 03 | 12 | 3 | 25% |
| District 05 | 12 | 1 | 8% |
| District 07 | 10 | 2 | 20% |
| District 08 | 7 | 3 | 43% |
| District 02 | 7 | 1 | 14% |
| District 01 | 3 | 0 | 0% |
| District 09 | 2 | 1 | 50% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Short term pavt mking | 70300100 | LF | 53 | 46 (87%) | $0.67 | $1.01 |
| Raised ref PVT MK rem | 78300200 | EACH | 49 | 42 (86%) | $12.00 | $15.00 |
| Trainees TPG | Z0076604 | HR | 23 | 23 (100%) | $15.00 | $15.00 |
| Trainees | Z0076600 | HR | 23 | 23 (100%) | $0.80 | $0.80 |
| Engr field office A | 67000400 | CAL MO | 22 | 16 (73%) | $2,200.00 | $2,550.00 |
| Mod ureth PM line 24 | 78009024 | LF | 39 | 14 (36%) | $6.00 | $8.00 |
| Bit matls tack CT | 40600290 | LB | 25 | 14 (56%) | $0.65 | $0.01 |
| Mod ureth PM line 6 | 78009006 | LF | 46 | 13 (28%) | $1.14 | $1.90 |
| Mod ureth PM LTR-sym | 78009000 | SF | 43 | 13 (30%) | $6.00 | $7.00 |
| Mod ureth PM line 12 | 78009012 | LF | 41 | 13 (32%) | $2.94 | $4.50 |
| Changeable message SN | 70107025 | CAL DAY | 40 | 11 (28%) | $105.00 | $55.00 |
| Raised refl pavt MKR | 78100100 | EACH | 49 | 10 (20%) | $38.00 | $48.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Microsurfacing Contractors, LLC, a Division of Byrne and Jones Holding Company | 54 | 21 of 54 |
| RoadSafe Traffic Systems, Inc. | 38 | 26 of 38 |
| Beniach Construction Co., Inc. | 31 | 20 of 31 |
| Varsity Striping & Construction Co. | 24 | 16 of 24 |
| Precision Pavement Markings Inc. | 17 | 13 of 17 |
| Missouri Petroleum Products Company LLC | 13 | 7 of 13 |
| Asphalt Stone Company | 12 | 5 of 12 |
| STF, LLC d/b/a Traffic Control Company | 11 | 7 of 11 |
| America's Parking ReMarking, LLC. | 7 | 6 of 7 |
| Marking Specialists Corporation | 5 | 2 of 5 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 18 SEP 2026 | 46691 | District 07 | Section D7 | 4 of 4 | $1,118,877 | +36% |
| 31 JUL 2026 | 93860 | District 06 | Project Number: Numa-444 / /, section 25-00048-00-PP | 1 of 2 | $586,823 | Low, 14% under the second |
| 12 JUN 2026 | 76U54 | District 08 | Section (107,108)RS-4 | 2 of 3 | $861,289 | +4.0% |
| 12 JUN 2026 | 89892 | District 04 | Project Number: Pvhm-146 / /, section 26-00000-00-PP | 1 of 1 | $1,647,297 | Low |
| 12 JUN 2026 | 93858 | District 06 | Project Number: 4F1E-236 / /, section 24-00146-01-PP | 1 of 3 | $578,700 | Low, 6.0% under the second |
| 24 APR 2026 | 46670 | District 08 | Section D8 | 1 of 4 | $202,951 | Low, 72% under the second |
| 24 APR 2026 | 46671 | District 03 | Section D3 | 5 of 5 | $2,329,665 | +38% |
| 24 APR 2026 | 46672 | District 02 | Section D2 | 4 of 4 | $4,995,100 | +75% |
| 24 APR 2026 | 68K12 | District 04 | Section 90(6,7)RS-2 | 2 of 3 | $2,460,685 | +18% |
| 24 APR 2026 | 70H87 | District 05 | Section (74,10-70,71,73)I | 3 of 3 | $531,506 | +36% |
| 27 FEB 2026 | 46677 | District 06 | Section D6-HT | 4 of 5 | $2,786,801 | +73% |
| 27 FEB 2026 | 72469 | District 06 | Section (2,3)Q-2 | 2 of 2 | $806,524 | +9.0% |
| 16 JAN 2026 | 72383 | District 06 | Section 134Q | 1 of 3 | $639,547 | Low, 2.0% under the second |
| 16 JAN 2026 | 72420 | District 06 | Section (F,DX)Q | 1 of 3 | $527,386 | Low, 7.0% under the second |
| 16 JAN 2026 | 95989 | District 07 | Project Number: H4Qy-595 / /, section 25-00299-00-RS | 2 of 3 | $1,016,741 | +3.0% |
| 19 SEP 2025 | 46668 | District 07 | Section D7 | 5 of 5 | $1,193,258 | +66% |
| 13 JUN 2025 | 46664 | District 04 | Section D4 | 3 of 4 | $2,082,261 | +5.0% |
| 25 APR 2025 | 46659 | District 02 | Section D2 | 3 of 3 | $4,388,250 | +27% |
| 25 APR 2025 | 70H56 | District 05 | Section (74-3)I | 3 of 3 | $561,424 | +63% |
| 25 APR 2025 | 74C50 | District 07 | Section D7 | 2 of 3 | $781,798 | +4.0% |
| 07 MAR 2025 | 66R05 | District 03 | Section CONTRAST | 1 of 3 | $936,906 | Low, 8.0% under the second |
| 07 MAR 2025 | 66R06 | District 03 | Section CONTRAST | 3 of 5 | $327,566 | +22% |
| 07 MAR 2025 | 68J17 | District 04 | Section 118RS-4;119RS-5 | 1 of 3 | $1,625,964 | Low, 19% under the second |
| 07 MAR 2025 | 70H33 | District 05 | Section (200)RS-4,(201)RS-2 | 1 of 3 | $997,903 | Low, 4.0% under the second |
| 07 MAR 2025 | 76T83 | District 08 | Section 68R-1-(2,3,4)RS | 1 of 2 | $879,340 | Low, 4.0% under the second |
How this record was read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.