A. C. Pavement Striping Co.: IDOT bid record

A. C. Pavement Striping Co. submitted 95 bids on Illinois DOT contracts in the data, from 15 JAN 2021 to 18 SEP 2026, and was the low bidder on 29 of them (31%). When it was not low, its total sat a median +23% above the low bid.

Owner
Illinois DOT
Low bid volume
$28,000,450
Latest bid
18 SEP 2026
Data through
18 SEP 2026
95Bids
29Low bids
31Win rate, percent
+23%Median gap to the low bid when not low, 66 bids

By year

YearBidsLow bidsWin rate
202130723%
202215427%
202311218%
202411436%
202513646%
202615640%
A. C. Pavement Striping Co., IDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
District 06281346%
District 0414536%
District 0312325%
District 051218%
District 0710220%
District 087343%
District 027114%
District 01300%
District 092150%
A. C. Pavement Striping Co., IDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Short term pavt mking70300100LF5346 (87%)$0.67$1.01
Raised ref PVT MK rem78300200EACH4942 (86%)$12.00$15.00
Trainees TPGZ0076604HR2323 (100%)$15.00$15.00
TraineesZ0076600HR2323 (100%)$0.80$0.80
Engr field office A67000400CAL MO2216 (73%)$2,200.00$2,550.00
Mod ureth PM line 2478009024LF3914 (36%)$6.00$8.00
Bit matls tack CT40600290LB2514 (56%)$0.65$0.01
Mod ureth PM line 678009006LF4613 (28%)$1.14$1.90
Mod ureth PM LTR-sym78009000SF4313 (30%)$6.00$7.00
Mod ureth PM line 1278009012LF4113 (32%)$2.94$4.50
Changeable message SN70107025CAL DAY4011 (28%)$105.00$55.00
Raised refl pavt MKR78100100EACH4910 (20%)$38.00$48.00
A. C. Pavement Striping Co., IDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
18 SEP 202646691District 07Section D74 of 4$1,118,877+36%
31 JUL 202693860District 06Project Number: Numa-444 / /, section 25-00048-00-PP1 of 2$586,823Low, 14% under the second
12 JUN 202676U54District 08Section (107,108)RS-42 of 3$861,289+4.0%
12 JUN 202689892District 04Project Number: Pvhm-146 / /, section 26-00000-00-PP1 of 1$1,647,297Low
12 JUN 202693858District 06Project Number: 4F1E-236 / /, section 24-00146-01-PP1 of 3$578,700Low, 6.0% under the second
24 APR 202646670District 08Section D81 of 4$202,951Low, 72% under the second
24 APR 202646671District 03Section D35 of 5$2,329,665+38%
24 APR 202646672District 02Section D24 of 4$4,995,100+75%
24 APR 202668K12District 04Section 90(6,7)RS-22 of 3$2,460,685+18%
24 APR 202670H87District 05Section (74,10-70,71,73)I3 of 3$531,506+36%
27 FEB 202646677District 06Section D6-HT4 of 5$2,786,801+73%
27 FEB 202672469District 06Section (2,3)Q-22 of 2$806,524+9.0%
16 JAN 202672383District 06Section 134Q1 of 3$639,547Low, 2.0% under the second
16 JAN 202672420District 06Section (F,DX)Q1 of 3$527,386Low, 7.0% under the second
16 JAN 202695989District 07Project Number: H4Qy-595 / /, section 25-00299-00-RS2 of 3$1,016,741+3.0%
19 SEP 202546668District 07Section D75 of 5$1,193,258+66%
13 JUN 202546664District 04Section D43 of 4$2,082,261+5.0%
25 APR 202546659District 02Section D23 of 3$4,388,250+27%
25 APR 202570H56District 05Section (74-3)I3 of 3$561,424+63%
25 APR 202574C50District 07Section D72 of 3$781,798+4.0%
07 MAR 202566R05District 03Section CONTRAST1 of 3$936,906Low, 8.0% under the second
07 MAR 202566R06District 03Section CONTRAST3 of 5$327,566+22%
07 MAR 202568J17District 04Section 118RS-4;119RS-51 of 3$1,625,964Low, 19% under the second
07 MAR 202570H33District 05Section (200)RS-4,(201)RS-21 of 3$997,903Low, 4.0% under the second
07 MAR 202576T83District 08Section 68R-1-(2,3,4)RS1 of 2$879,340Low, 4.0% under the second
A. C. Pavement Striping Co.: latest IDOT bids in the data

How this record was read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy