Asphalt Stone Company: IDOT bid record

Asphalt Stone Company submitted 14 bids on Illinois DOT contracts in the data, from 15 JAN 2021 to 29 APR 2022, and was the low bidder on 3 of them (21%). When it was not low, its total sat a median +13% above the low bid.

Owner
Illinois DOT
Low bid volume
$3,415,844
Latest bid
29 APR 2022
Data through
18 SEP 2026
14Bids
3Low bids
21Win rate, percent
+13%Median gap to the low bid when not low, 11 bids

By year

YearBidsLow bidsWin rate
20214250%
202210110%
Asphalt Stone Company, IDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
District 067229%
District 04400%
District 07100%
District 0811100%
District 05100%
Asphalt Stone Company, IDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Raised refl pavt MKR78100100EACH1313 (100%)$29.75$48.00
Trainees TPGZ0076604HR88 (100%)$15.00$15.00
TraineesZ0076600HR88 (100%)$0.80$0.80
Short term pavt mking70300100LF147 (50%)$0.92$1.01
Paint PVT MK line 478001110LF66 (100%)$0.12$1.00
Mod ureth PM line 578009005LF55 (100%)$0.66$1.10
Fibr mod asp CRK seal40500001LF55 (100%)$0.45$0.55
Pavmt MRKG rem WTR BL78300202SF64 (67%)$1.33$2.10
Bit matls FSX0300010LB54 (80%)$0.62$0.95
Bump removal40400020EACH103 (30%)$125.90$150.00
Fibr mod asp CRK seal40400001LF73 (43%)$0.63$0.75
Raised ref PVT MK rem78300200EACH132 (15%)$17.89$15.00
Asphalt Stone Company, IDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

Asphalt Stone Company, IDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
29 APR 202268G30District 04Section (109,3 of 3$781,625+13%
29 APR 202268G31District 04Section (38-1)RS-12 of 3$778,203+6.0%
29 APR 202268G32District 04Section 125RS-62 of 3$318,937+15%
29 APR 202268G34District 04Section (17,16)RS-5;15RS-82 of 3$588,994+6.0%
29 APR 202270E03District 05Section (9,10,11)RS-4,(9-1,9)RS-13 of 3$2,241,614+25%
29 APR 202293784District 06Project Number: Hwvq-638 / /, section 20-00068-00-PP4 of 4$2,312,550+10%
11 MAR 202272M23District 06Section (144)Q,1 of 4$1,084,462Low, 2.0% under the second
11 MAR 202272M24District 06Section (124,3 of 4$1,340,317+4.0%
21 JAN 202272M19District 06Section (1-7)Q-12 of 4$2,087,258+13%
21 JAN 202272M20District 06Section (24,25,26)Q3 of 4$2,826,257+14%
05 MAR 202172L89District 06Section (3,4,5)Q1 of 4$1,346,742Low, 0.0% under the second
05 MAR 202172L91District 06Section (16,5 of 5$732,045+35%
15 JAN 202174949District 07Section (L,K)PVMT4 of 5$533,296+6.0%
15 JAN 202176N69District 08Section 3R-2(5,7-1)RS-41 of 5$984,640Low, 3.0% under the second
Asphalt Stone Company: latest IDOT bids in the data

How this record was read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy