Precision Pavement Markings Inc.: IDOT bid record
Precision Pavement Markings Inc. submitted 42 bids on Illinois DOT contracts in the data, from 23 APR 2021 to 12 JUN 2026, and was the low bidder on 11 of them (26%). When it was not low, its total sat a median +24% above the low bid.
- Owner
- Illinois DOT
- Low bid volume
- $16,053,722
- Latest bid
- 12 JUN 2026
- Data through
- 18 SEP 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2021 | 3 | 0 | 0% |
| 2022 | 5 | 3 | 60% |
| 2023 | 10 | 3 | 30% |
| 2024 | 8 | 2 | 25% |
| 2025 | 8 | 2 | 25% |
| 2026 | 8 | 1 | 13% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 01 | 12 | 5 | 42% |
| District 02 | 10 | 3 | 30% |
| District 03 | 10 | 2 | 20% |
| District 04 | 7 | 1 | 14% |
| District 07 | 1 | 0 | 0% |
| District 06 | 1 | 0 | 0% |
| District 08 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| GRV RCSD PM LTR & sym | 78011000 | SF | 8 | 7 (88%) | $2.85 | $5.00 |
| Mod ureth PM line 6 | 78009006 | LF | 20 | 6 (30%) | $0.93 | $1.90 |
| Mod ureth PM LTR-sym | 78009000 | SF | 18 | 6 (33%) | $5.97 | $7.00 |
| Raised ref PVT MK rem | 78300200 | EACH | 11 | 6 (55%) | $32.00 | $15.00 |
| Aerial speed CHK MK | Z0008758 | LF | 10 | 6 (60%) | $27.50 | $35.00 |
| Mod ureth PM line 24 | 78009024 | LF | 19 | 5 (26%) | $6.00 | $8.00 |
| Mod ureth PM line 8 | 78009008 | LF | 18 | 5 (28%) | $1.55 | $2.25 |
| Mod ureth PM line 4 | 78009004 | LF | 17 | 5 (29%) | $0.65 | $1.69 |
| Paint PVT MK line 4 | 78001110 | LF | 14 | 5 (36%) | $0.14 | $1.00 |
| Raised refl pavt MKR | 78100100 | EACH | 11 | 5 (45%) | $41.50 | $48.00 |
| THPL PVT MK line 24 | 78000650 | LF | 11 | 5 (45%) | $5.75 | $6.00 |
| THPL PVT MK line 6 | 78000400 | LF | 11 | 5 (45%) | $1.15 | $1.40 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| RoadSafe Traffic Systems, Inc. | 36 | 15 of 36 |
| A. C. Pavement Striping Co. | 17 | 4 of 17 |
| Varsity Striping & Construction Co. | 14 | 10 of 14 |
| STF, LLC d/b/a Traffic Control Company | 12 | 6 of 12 |
| Marking Specialists Corporation | 11 | 3 of 11 |
| America's Parking ReMarking, LLC. | 11 | 9 of 11 |
| Superior Road Striping, Inc. | 5 | 2 of 5 |
| P & P Construction Co. | 4 | 4 of 4 |
| Preform Traffic Control Systems, Ltd. | 3 | 0 of 3 |
| Maintenance Coatings Co. | 2 | 2 of 2 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 12 JUN 2026 | 46678 | District 04 | Section D4 | 2 of 4 | $3,698,523 | +20% |
| 12 JUN 2026 | 46679 | District 04 | Section D4 | 1 of 3 | $1,560,696 | Low, 0.0% under the second |
| 24 APR 2026 | 46670 | District 08 | Section D8 | 3 of 4 | $435,258 | +114% |
| 24 APR 2026 | 46671 | District 03 | Section D3 | 4 of 5 | $2,109,300 | +25% |
| 24 APR 2026 | 46672 | District 02 | Section D2 | 3 of 4 | $3,857,500 | +35% |
| 24 APR 2026 | 68K54 | District 04 | Section D4 | 3 of 4 | $597,666 | +14% |
| 27 FEB 2026 | 46673 | District 02 | Section D2 | 3 of 5 | $2,435,000 | +6.0% |
| 27 FEB 2026 | 46677 | District 06 | Section D6-HT | 3 of 5 | $1,810,357 | +12% |
| 19 SEP 2025 | 46668 | District 07 | Section D7 | 4 of 5 | $908,898 | +26% |
| 13 JUN 2025 | 46664 | District 04 | Section D4 | 4 of 4 | $2,917,385 | +47% |
| 25 APR 2025 | 46659 | District 02 | Section D2 | 2 of 3 | $4,268,750 | +24% |
| 25 APR 2025 | 66R26 | District 03 | Section CONTRAST | 1 of 4 | $847,344 | Low, 6.0% under the second |
| 25 APR 2025 | 68J36 | District 04 | Section D4 | 3 of 4 | $843,706 | +124% |
| 07 MAR 2025 | 66R06 | District 03 | Section CONTRAST | 2 of 5 | $316,442 | +18% |
| 17 JAN 2025 | 46655 | District 03 | Section D3 | 3 of 5 | $1,991,560 | +16% |
| 17 JAN 2025 | 61L03 | District 01 | Project Number: Njtk-202 / /, section 22-00557-00-SP | 1 of 3 | $545,288 | Low, 0.0% under the second |
| 14 JUN 2024 | 46630 | District 01 | Section D | 3 of 4 | $1,706,200 | +44% |
| 14 JUN 2024 | 46631 | District 01 | Section D | 2 of 3 | $4,799,305 | +6.0% |
| 14 JUN 2024 | 46647 | District 01 | Section D | 2 of 4 | $3,036,500 | +1.0% |
| 14 JUN 2024 | 46648 | District 01 | Section D | 2 of 3 | $1,818,450 | 0.0% |
| 14 JUN 2024 | 46649 | District 01 | Section D | 2 of 4 | $899,000 | +1.0% |
| 26 APR 2024 | 46642 | District 02 | Section D2 | 1 of 3 | $4,661,960 | Low, 3.0% under the second |
| 26 APR 2024 | 46645 | District 02 | Section D2 | 1 of 2 | $998,000 | Low, 75% under the second |
| 26 APR 2024 | 68H91 | District 04 | Section D4 | 2 of 3 | $950,166 | +146% |
| 17 NOV 2023 | 46635 | District 03 | Section D | 3 of 4 | $2,232,270 | +25% |
How this record was read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.