IDOT contract 74829 bid tabulation
Section (2,2Z). Let by Illinois DOT on July 31, 2026, Moultrie, District 07. 2 bids received; low bid $3,050,707 by Howell Paving, Inc..
- Owner
- Illinois DOT
- Letting
- 31 JUL 2026
- Pay items
- 142
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Howell Paving, Inc. | $3,050,707 | Low |
| 2 | Ne-Co Asphalt Co., Inc. | $3,316,240 | +9.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Howell Paving, Inc. | 2. Ne-Co Asphalt Co., Inc. |
|---|---|---|---|---|---|
| 1 | Rem & rel SN P&P assy (X2600012) | EACH | 6 | $250.80 | $1,500.00 |
| 2 | Temporary ramp SPL (X4060995) | SY | 1,006 | $30.99 | $65.00 |
| 3 | Surf rem var DP (SPL) (X4400102) | SY | 1,396 | $40.68 | $15.00 |
| 4 | HMA surf rem var DP (X4401198) | SY | 91 | $4.99 | $25.00 |
| 5 | Meter vaults adj (X6026634) | EACH | 1 | $690.00 | $690.00 |
| 6 | FR & lids adjust SPL (X6030310) | EACH | 11 | $4,240.00 | $4,240.00 |
| 7 | Comb LTG control (X8250091) | EACH | 1 | $3,400.00 | $3,400.00 |
| 8 | Accessible ped signal (X8760200) | EACH | 8 | $1,700.00 | $1,700.00 |
| 9 | Conc curb repair (Z0012500) | LF | 70 | $65.00 | $65.00 |
| 10 | RR prot liability ins (Z0048665) | LS | 1 | $6,876.88 | $6,500.00 |
| 11 | Prot reset survey MRK (Z0049799) | EACH | 10 | $748.21 | $3,500.00 |
| 12 | Conc retain wall rem (Z0075498) | CY | 3 | $326.00 | $326.00 |
| 13 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 |
| 14 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 |
| 15 | Earth excavation (20200100) | CY | 87 | $47.00 | $47.00 |
| 16 | Trench backfill (20800150) | CY | 163 | $63.00 | $63.00 |
| 17 | Topsoil F & P var DP (21101600) | SY | 133 | $22.30 | $22.30 |
| 18 | Sodding (25200100) | SY | 133 | $215.00 | $215.00 |
| 19 | Sub gran mat B 4 (31101200) | SY | 184 | $16.00 | $16.00 |
| 20 | Agg base repair (35800200) | TON | 16 | $70.25 | $70.25 |
| 21 | Bit matls tack CT (40600290) | LB | 20,472 | $1.06 | $1.25 |
| 22 | Long joint sealant (40600370) | LF | 14,527 | $3.72 | $4.00 |
| 23 | HMA surf rem butt JT (40600982) | SY | 150 | $4.41 | $25.00 |
| 24 | Temporary ramp (40600990) | SY | 129 | $46.42 | $25.00 |
| 25 | P HMA BC IL-9.5FG N90 (40603219) | TON | 2,243 | $137.51 | $139.00 |
| 26 | P HMA SC IL-9.5 D N90 (40604164) | TON | 2,669 | $141.34 | $139.00 |
| 27 | Incidental HMA surf (40800050) | TON | 117 | $477.91 | $300.00 |
| 28 | PCC PVT 8 jointed (42000301) | SY | 125 | $142.00 | $142.00 |
| 29 | PCC PVT 10 jointed (42000501) | SY | 979 | $149.00 | $149.00 |
| 30 | PCC driveway pavt 8 (42300400) | SY | 36 | $101.00 | $101.00 |
| 31 | PC conc sidewalk 6 (42400300) | SF | 7,594 | $13.75 | $13.75 |
| 32 | Detectable warnings (42400800) | SF | 657 | $25.00 | $25.00 |
| 33 | Pavement rem (44000100) | SY | 969 | $43.25 | $43.25 |
| 34 | HMA surf rem 1 1/2 (44000155) | SY | 5,117 | $3.08 | $4.00 |
| 35 | HMA surf rem 2 1/2 (44000159) | SY | 25,813 | $4.20 | $4.00 |
| 36 | Drive pavement rem (44000200) | SY | 141 | $52.75 | $52.75 |
| 37 | Comb curb gutter rem (44000500) | LF | 1,139 | $25.00 | $25.00 |
| 38 | Sidewalk rem (44000600) | SF | 7,584 | $6.10 | $6.10 |
| 39 | CL D patch T1 11 (44201773) | SY | 4 | $170.17 | $300.00 |
| 40 | CL D patch T2 11 (44201777) | SY | 1,256.90 | $170.43 | $220.00 |
| 41 | CL D patch T3 11 (44201781) | SY | 181.30 | $170.45 | $220.00 |
| 42 | CL D patch T4 11 (44201783) | SY | 49.30 | $170.51 | $220.00 |
| 43 | CL D patch T1 12 (44201785) | SY | 8 | $177.16 | $300.00 |
| 44 | CL D patch T2 12 (44201789) | SY | 515 | $177.36 | $225.00 |
| 45 | CL D patch T3 12 (44201794) | SY | 146 | $177.37 | $225.00 |
| 46 | CL D patch T4 12 (44201796) | SY | 278 | $177.36 | $225.00 |
| 47 | Agg wedge SHLD type B (48102100) | TON | 140 | $113.93 | $132.64 |
| 48 | HMA shoulders (48203100) | TON | 211 | $238.13 | $132.00 |
| 49 | Conc STR retain wall (52200900) | CY | 3 | $2,205.00 | $2,205.00 |
| 50 | Storm sew CL A 2 12 (550A0340) | LF | 50 | $132.50 | $132.50 |
| 51 | Storm sew CL A 2 15 (550A0360) | LF | 125 | $140.80 | $140.80 |
| 52 | Storm sew CL A 2 18 (550A0380) | LF | 34 | $149.50 | $149.50 |
| 53 | Storm sewer rem 12 (55100500) | LF | 168 | $27.50 | $27.50 |
| 54 | Storm sewer rem 15 (55100700) | LF | 44 | $27.50 | $27.50 |
| 55 | Storm sewer rem 18 (55100900) | LF | 35 | $27.50 | $27.50 |
| 56 | Water valves adjust (56109210) | EACH | 4 | $195.00 | $195.00 |
| 57 | Man TA 4 dia T1F CL (60218400) | EACH | 3 | $4,825.00 | $4,825.00 |
| 58 | Man TA 4 dia T3F&G (60218500) | EACH | 1 | $5,035.00 | $5,035.00 |
| 59 | Man TA 4 dia (60220200) | EACH | 4 | $4,877.00 | $4,877.00 |
| 60 | Inlets TA T3F&G (60235700) | EACH | 2 | $2,825.25 | $2,825.25 |
| 61 | Inlets TB T3F&G (60240220) | EACH | 2 | $3,770.00 | $3,770.00 |
| 62 | Inlets adjust (60260100) | EACH | 6 | $610.00 | $610.00 |
| 63 | Comb CC&G TB6.12 (60603800) | LF | 495 | $62.00 | $62.00 |
| 64 | Comb CC&G TB6.18 (60604400) | LF | 765 | $65.50 | $65.50 |
| 65 | Non SPL waste disposl (66900200) | CY | 34 | $705.30 | $300.00 |
| 66 | Soil disposal analy (66900530) | EACH | 5 | $1,100.00 | $1,200.00 |
| 67 | Reg sub P-const plan (66901001) | LS | 1 | $2,200.00 | $3,000.00 |
| 68 | Reg sub F con report (66901003) | LS | 1 | $2,200.00 | $1,000.00 |
| 69 | Reg sub mon (66901006) | CAL DAY | 3 | $1,125.00 | $1,500.00 |
| 70 | Engr field office A (67000400) | CAL MO | 6 | $3,454.57 | $3,500.00 |
| 71 | Engr field lab (67000600) | CAL MO | 6 | $1,754.57 | $3,500.00 |
| 72 | Mobilization (67100100) | LS | 1 | $97,624 | $98,000 |
| 73 | Traf cont-prot 701201 (70100450) | LS | 1 | $8,100.00 | $125,000 |
| 74 | Traf cont-prot 701306 (70100460) | LS | 1 | $0.01 | $65,000 |
| 75 | TR cont & prot 701501 (70102620) | LS | 1 | $53,217 | $28,000 |
| 76 | TR cont & prot 701502 (70102622) | LS | 1 | $40,800 | $32,000 |
| 77 | TR cont & prot 701801 (70102640) | LS | 1 | $16,500 | $16,500 |
| 78 | Changeable message SN (70107025) | CAL DAY | 42 | $125.00 | $125.00 |
| 79 | Short term pavt mking (70300100) | LF | 8,998 | $1.16 | $3.00 |
| 80 | SHRT TRM pavt MK rem (70300150) | SF | 2,999 | $0.01 | $3.00 |
| 81 | Temp PVT MK LTR & sym paint (70300211) | SF | 1,170 | $3.00 | $2.50 |
| 82 | Temp PVT MK line 4 - paint (70300221) | LF | 19,371 | $0.37 | $0.23 |
| 83 | Temp PVT MK line 6 - paint (70300241) | LF | 1,835 | $2.00 | $0.35 |
| 84 | Temp PVT MK line 12 - paint (70300261) | LF | 22 | $3.00 | $0.70 |
| 85 | Temp PVT MK line 24 - paint (70300281) | LF | 127 | $4.00 | $3.00 |
| 86 | Sign panel T1 (72000100) | SF | 12.50 | $250.00 | $250.00 |
| 87 | Sign panel T2 (72000200) | SF | 30 | $150.00 | $150.00 |
| 88 | THPL PVT MK LTR & sym (78000100) | SF | 1,170 | $8.50 | $6.00 |
| 89 | THPL PVT MK line 4 (78000200) | LF | 19,371 | $0.84 | $0.80 |
| 90 | THPL PVT MK line 6 (78000400) | LF | 1,835 | $3.50 | $1.21 |
| 91 | THPL PVT MK line 12 (78000600) | LF | 22 | $10.00 | $2.42 |
| 92 | THPL PVT MK line 24 (78000650) | LF | 127 | $12.00 | $4.85 |
| 93 | Mod ureth PM line 6 (78009006) | LF | 416 | $20.00 | $14.86 |
| 94 | Mod ureth PM line 24 (78009024) | LF | 60 | $25.00 | $59.50 |
| 95 | GRV RCSD PM LTR & sym (78011000) | SF | 1,170 | $4.00 | $5.50 |
| 96 | GRV RCSD PVT MRKG 5 (78011025) | LF | 19,371 | $0.54 | $0.40 |
| 97 | GRV RCSD PVT MRKG 7 (78011035) | LF | 1,835 | $2.00 | $0.60 |
| 98 | GRV RCSD PVT MRKG 13 (78011065) | LF | 22 | $4.00 | $3.00 |
| 99 | GRV RCSD PVT MRKG 25 (78011125) | LF | 127 | $5.00 | $6.00 |
| 100 | Raised refl pavt MKR (78100100) | EACH | 344 | $53.24 | $37.76 |
| 101 | Raised ref PVT MK rem (78300200) | EACH | 66 | $29.16 | $10.00 |
| 102 | Serv install TY A (80500100) | EACH | 1 | $9,000.00 | $12,000 |
| 103 | Undrgrd C PVC 3/4 (81028310) | LF | 57 | $36.00 | $36.00 |
| 104 | Undrgrd C PVC 1 1/2 (81028340) | LF | 83 | $38.00 | $38.00 |
| 105 | Undrgrd C PVC 2 (81028350) | LF | 191 | $40.00 | $40.00 |
| 106 | Undrgrd C PVC 4 (81028390) | LF | 214 | $60.00 | $78.00 |
| 107 | Undrgrd C PVC 5 (81028400) | LF | 2 | $100.00 | $100.00 |
| 108 | Handhole C conc (81400730) | EACH | 5 | $1,800.00 | $1,800.00 |
| 109 | DBL handhole C conc (81400740) | EACH | 1 | $3,350.00 | $3,350.00 |
| 110 | Gulfbox junction (81500100) | EACH | 1 | $1,400.00 | $1,400.00 |
| 111 | EC C XLP use 1C 10 (81702110) | LF | 705 | $5.00 | $5.00 |
| 112 | Lum LED rdwy H (82110008) | EACH | 2 | $1,250.00 | $1,250.00 |
| 113 | Main EX TR sig instal (85000200) | EACH | 1 | $5,100.00 | $5,100.00 |
| 114 | Fac T4 cab (85700200) | EACH | 1 | $25,000 | $30,900 |
| 115 | Elcbl C signal 14 3C (87301225) | LF | 915 | $3.00 | $3.00 |
| 116 | Elcbl C signal 14 5C (87301245) | LF | 1,342 | $4.50 | $4.50 |
| 117 | Elcbl C signal 14 7C (87301255) | LF | 1,319 | $5.00 | $5.00 |
| 118 | Elcbl C lead 14 1PR (87301305) | LF | 1,427 | $4.00 | $4.00 |
| 119 | Elcbl C serv 6 2C (87301805) | LF | 60 | $35.00 | $35.00 |
| 120 | Elcbl C egrdc 6 1C (87301900) | LF | 701 | $5.00 | $5.00 |
| 121 | TS post galvs 12 (87502460) | EACH | 3 | $3,400.00 | $3,400.00 |
| 122 | TS post galvs 14 (87502480) | EACH | 2 | $3,700.00 | $3,700.00 |
| 123 | TS post galvs 16 (87502500) | EACH | 3 | $4,425.00 | $4,425.00 |
| 124 | Ped P-B post galvs T1 (87601100) | EACH | 8 | $2,400.00 | $2,400.00 |
| 125 | STL comb maa&P 34 (87702900) | EACH | 1 | $32,000 | $33,000 |
| 126 | STL comb maa&P 42 (87702940) | EACH | 1 | $33,000 | $34,000 |
| 127 | Conc FDN TY A (87800100) | LF | 24 | $600.00 | $825.00 |
| 128 | Conc FDN TY C (87800150) | LF | 3.50 | $1,650.00 | $1,650.00 |
| 129 | Conc FDN TY E 36D (87800415) | LF | 26 | $675.00 | $675.00 |
| 130 | SH P LED 1F 3S BM (88040070) | EACH | 8 | $930.00 | $930.00 |
| 131 | SH P LED 1F 3S mam (88040090) | EACH | 4 | $1,060.00 | $1,060.00 |
| 132 | SH P LED 1F 4S BM (88040110) | EACH | 2 | $1,175.00 | $1,175.00 |
| 133 | SH P LED 1F 4S mam (88040120) | EACH | 2 | $1,260.00 | $1,260.00 |
| 134 | Ped SH P LED 1F BM CT (88102825) | EACH | 8 | $900.00 | $900.00 |
| 135 | TS backplate L F plas (88200410) | EACH | 16 | $400.00 | $400.00 |
| 136 | Det loop T1 (88600100) | LF | 595 | $30.00 | $30.00 |
| 137 | Temp TR sig install (89000100) | EACH | 1 | $42,500 | $22,348 |
| 138 | Rem elcbl FR con (89502300) | LF | 329 | $1.00 | $1.00 |
| 139 | Remov EX TS equip (89502375) | EACH | 1 | $7,000.00 | $7,000.00 |
| 140 | Remov EX handhole (89502380) | EACH | 5 | $1,550.00 | $1,550.00 |
| 141 | Remov EX DBL handhole (89502382) | EACH | 1 | $1,800.00 | $1,800.00 |
| 142 | Remov EX conc FDN (89502385) | EACH | 7 | $1,600.00 | $1,600.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of July 31, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.