MYS, Incorporated submitted 197 bids on Illinois DOT contracts in the data, from 15 JAN 2021 to 18 SEP 2026, and was the low bidder on 35 of them (18%). When it was not low, its total sat a median +28% above the low bid.

Owner
Illinois DOT
Low bid volume
$16,836,202
Latest bid
18 SEP 2026
Data through
18 SEP 2026
197Bids
35Low bids
18Win rate, percent
+28%Median gap to the low bid when not low, 159 bids

By year

YearBidsLow bidsWin rate
202144920%
202222941%
202326935%
20244512%
20252628%
202634515%
MYS, Incorporated, IDOT: bids and low bids by year of letting

By district

DistrictBidsLow bidsWin rate
District 011743319%
District 03700%
District 06500%
District 02400%
District 073133%
District 053133%
District 08100%
MYS, Incorporated, IDOT: bids and low bids by district

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Trainees TPGZ0076604HR2929 (100%)$15.00$15.00
Bit matls tack CT40600290LB6628 (42%)$0.02$0.01
TraineesZ0076600HR2222 (100%)$0.80$0.80
Litter pickingX0326643MI6716 (24%)$989.00$914.50
Conc rem50102400CY5812 (21%)$2,319.85$2,400.00
SHRT TRM pavt MK rem70300150SF4910 (20%)$1.00$1.20
Pref JT strip seal52000110LF329 (28%)$259.11$263.11
Deck slab rep (FD-T2)Z0016002SY289 (32%)$1,900.00$1,850.00
Non SPL waste disposl66900200CY528 (15%)$113.70$92.99
Sidewalk rem44000600SF518 (16%)$4.31$3.00
Engrs FLD ofc TY A D1X6700407CAL MO458 (18%)$3,082.67$3,250.00
Engr field office A67000400CAL MO278 (30%)$2,000.00$2,550.00
MYS, Incorporated, IDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

MYS, Incorporated, IDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
18 SEP 202680B49District 01Section (CIP-617)6 of 6$1,081,010+42%
31 JUL 202662X43District 01Section 68B-14 of 4$366,003+26%
31 JUL 202662Y20District 01Section 2025-1070-BDR,BJR5 of 5$1,802,882+46%
31 JUL 202680B44District 01Section (1313VB-VC-WPGM)5 of 5$2,651,845+29%
31 JUL 202680B78District 01Section 2025-2036-I1 of 2$1,409,040Low, 3.0% under the second
12 JUN 202662T46District 01Section FAU4 of 4$672,946+12%
12 JUN 202662X28District 01Section (FXB-1R)3 of 3$374,769+51%
12 JUN 202662X52District 01Section 2024-1015-SCR3 of 4$336,737+27%
12 JUN 202666T41District 03Section LITTER5 of 6$90,048+81%
12 JUN 202666T42District 03Section LITTER6 of 6$131,840+75%
12 JUN 202670H72District 05Section MBPM1 of 4$267,850Low, 28% under the second
12 JUN 202680B58District 01Section 2025-2022-DR1 of 1$652,635Low
24 APR 202662X31District 01Section (0404-1023K)C,BR2 of 3$236,344+75%
24 APR 202662Y30District 01Section (60B&C-NRM)BDR,BJR2 of 4$798,954+2.0%
24 APR 202680B46District 01Section (99-5HB-3)4 of 4$908,473+56%
24 APR 202680B48District 01Section (1010B-89)2 of 4$1,209,633+9.0%
24 APR 202680B76District 01Section 2025-2038-I,PP,DR2 of 2$1,474,413+34%
24 APR 202680B79District 01Section 2025-2035-LR5 of 5$868,854+38%
24 APR 202680B80District 01Section 2025-2034-LR4 of 5$234,381+55%
27 FEB 202661M25District 01Project Number: H406-985 / /, section 16-11107-01-BR3 of 7$1,866,929+20%
27 FEB 202662X53District 01Section 2024-1014-CR1 of 1$899,287Low
27 FEB 202662Y17District 01Section (551X-B)BDR,BJR1 of 6$1,272,505Low, 4.0% under the second
27 FEB 202662Y26District 01Section (143VB-R-1(90))BR6 of 7$1,494,140+25%
27 FEB 202680B83District 01Section 2025-2031-LR9 of 10$267,123+67%
27 FEB 202680B84District 01Section 2025-2030-LR8 of 8$352,040+67%
MYS, Incorporated: latest IDOT bids in the data

How this record was read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy