IDOT contract 62Y17 bid tabulation
Section (551X-B)BDR,BJR. Let by Illinois DOT on February 27, 2026, Cook, District 01. 6 bids received; low bid $1,272,505 by MYS, Incorporated.
- Owner
- Illinois DOT
- Letting
- 27 FEB 2026
- Pay items
- 57
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | MYS, Incorporated | $1,272,505 | Low |
| 2 | Martam Construction Incorporated | $1,319,529 | +4.0% |
| 3 | D. Construction, Inc. | $1,420,334 | +12% |
| 4 | Rausch Infrastructure, LLC | $1,499,139 | +18% |
| 5 | Areatha Construction Co., Inc. | $1,567,874 | +23% |
| 6 | Lorig Construction Company | $1,618,211 | +27% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. MYS, Incorporated | 2. Martam Construction Incorporated | 3. D. Construction, Inc. | 4. Rausch Infrastructure, LLC | 5. Areatha Construction Co., Inc. | 6. Lorig Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Graffiti removal (X0300062) | SY | 89 | $199.19 | $200.00 | $90.00 | $213.00 | $179.50 | $200.00 |
| 2 | Clean reseal RLF JNT (X0326766) | LF | 156 | $94.32 | $45.00 | $60.00 | $108.00 | $108.50 | $85.00 |
| 3 | Stream gauge (X0327638) | EACH | 1 | $3,190.64 | $1,500.00 | $2,000.00 | $3,200.00 | $2,729.30 | $3,600.00 |
| 4 | BR deck grooving long (X5030250) | SY | 2,087 | $6.66 | $5.30 | $8.25 | $5.00 | $4.80 | $5.75 |
| 5 | Clean/paint bearings (X5060700) | EACH | 102 | $737.94 | $800.00 | $1,700.00 | $790.00 | $2,200.00 | $1,425.00 |
| 6 | CLN BRDG scups/DNSPTS (X5230154) | EACH | 24 | $277.42 | $500.00 | $600.00 | $484.00 | $350.00 | $500.00 |
| 7 | Drainage scuppers adj (X5230172) | EACH | 24 | $765.02 | $1,200.00 | $1,300.00 | $1,586.00 | $867.90 | $1,100.00 |
| 8 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $3,166.42 | $3,600.00 | $5,000.00 | $5,500.00 | $2,500.00 | $3,500.00 |
| 9 | Traf cont & prot SPL (X7010216) | LS | 1 | $39,472 | $126,000 | $31,500 | $37,000 | $18,826 | $160,000 |
| 10 | Temp info signing (X7200061) | SF | 196 | $11.10 | $12.00 | $35.00 | $17.00 | $15.00 | $12.00 |
| 11 | RRPM reflector removl (X7830050) | EACH | 35 | $11.10 | $12.00 | $17.50 | $17.00 | $10.00 | $15.00 |
| 12 | RRPM reflector replac (X7830052) | EACH | 23 | $13.32 | $14.00 | $50.00 | $297.00 | $20.00 | $25.00 |
| 13 | Det loop repl (X8860105) | LF | 159 | $40.37 | $43.00 | $45.00 | $43.00 | $47.00 | $48.00 |
| 14 | Appr slab repair (PD) (Z0001800) | SY | 32 | $708.78 | $850.00 | $600.00 | $1,400.00 | $810.25 | $825.00 |
| 15 | Debris removal (Z0015550) | CY | 30 | $387.63 | $120.00 | $200.00 | $600.00 | $462.10 | $150.00 |
| 16 | Drainage STR cleaned (Z0018500) | EACH | 2 | $1,664.52 | $600.00 | $750.00 | $1,700.00 | $1,500.00 | $1,000.00 |
| 17 | Diamond grind BR sec (Z0029090) | SY | 2,035 | $11.85 | $8.50 | $10.25 | $9.00 | $10.20 | $9.00 |
| 18 | Bit matls tack CT (40600290) | LB | 360 | $1.60 | $1.00 | $0.01 | $0.80 | $0.75 | $1.00 |
| 19 | Long joint sealant (40600370) | LF | 400 | $15.34 | $20.00 | $31.81 | $22.00 | $18.75 | $19.00 |
| 20 | HMA surf rem butt JT (40600982) | SY | 800 | $1.65 | $16.00 | $40.00 | $18.00 | $15.75 | $10.00 |
| 21 | P HMA SC IL-9.5 E N70 (40604172) | TON | 77 | $310.08 | $380.00 | $200.00 | $416.00 | $415.00 | $440.00 |
| 22 | Pavement rem (44000100) | SY | 128 | $30.67 | $26.00 | $40.00 | $117.00 | $4.95 | $15.00 |
| 23 | Comb curb gutter rem (44000500) | LF | 320 | $19.34 | $9.00 | $10.00 | $29.00 | $39.80 | $42.00 |
| 24 | Conc rem (50102400) | CY | 22.20 | $2,496.78 | $2,300.00 | $2,500.00 | $2,800.00 | $2,195.25 | $2,600.00 |
| 25 | Conc sup-STR (50300255) | CY | 23.50 | $3,550.97 | $3,200.00 | $3,000.00 | $4,000.00 | $3,322.40 | $3,200.00 |
| 26 | Protective coat (50300300) | SY | 3,022 | $0.74 | $1.00 | $2.00 | $6.00 | $3.05 | $2.00 |
| 27 | Reinf bars, epoxy CTD (50800205) | LB | 2,800 | $6.55 | $4.00 | $4.00 | $3.00 | $3.60 | $4.00 |
| 28 | Bar splicers (50800515) | EACH | 24 | $41.88 | $63.00 | $50.00 | $168.00 | $50.15 | $82.00 |
| 29 | Alum railing TY L (50900105) | LF | 30 | $53.60 | $60.00 | $315.00 | $57.00 | $48.30 | $200.00 |
| 30 | Pref JT strip seal (52000110) | LF | 236 | $225.57 | $265.00 | $290.00 | $320.00 | $397.20 | $278.00 |
| 31 | Deck slab rep (FD-T2) (53016002) | SY | 1 | $2,219.36 | $4,500.00 | $2,500.00 | $13,000 | $4,891.80 | $4,000.00 |
| 32 | BR deck scar 3/4 (53101002) | SY | 2,146 | $46.18 | $44.00 | $50.00 | $49.00 | $60.85 | $54.00 |
| 33 | BR DK LTX C oly 2 3/4 (53101410) | SY | 2,146 | $116.40 | $122.00 | $115.00 | $122.00 | $132.65 | $132.00 |
| 34 | STR rep con DP = < 5 (53212754) | SF | 604 | $172.00 | $190.00 | $155.00 | $214.00 | $268.55 | $325.00 |
| 35 | STR rep con DP over 5 (53212755) | SF | 16 | $277.42 | $200.00 | $300.00 | $220.00 | $310.65 | $550.00 |
| 36 | Concrete sealer (58700300) | SF | 620 | $5.19 | $4.00 | $2.00 | $2.00 | $3.35 | $6.00 |
| 37 | FR & grates adjust (60300105) | EACH | 2 | $1,114.02 | $600.00 | $900.00 | $1,400.00 | $1,000.00 | $1,800.00 |
| 38 | Comb CC&G TB6.12 (60603800) | LF | 320 | $74.81 | $38.00 | $52.00 | $89.00 | $99.40 | $120.00 |
| 39 | Mobilization (67100100) | LS | 1 | $110,529 | $78,000 | $85,250 | $90,000 | $103,838 | $90,000 |
| 40 | Changeable message SN (70107025) | CAL DAY | 168 | $22.19 | $22.00 | $50.00 | $35.00 | $30.00 | $20.00 |
| 41 | SHRT TRM pavt MK rem (70300150) | SF | 3,521 | $0.32 | $0.30 | $2.00 | $0.60 | $1.50 | $0.30 |
| 42 | Temp PVT MK L4 T4 tape (70307120) | LF | 6,843 | $1.50 | $1.50 | $2.50 | $1.50 | $1.20 | $1.40 |
| 43 | Temp PVT MK L6 T4 tape (70307130) | LF | 1,480 | $1.91 | $1.90 | $8.00 | $2.20 | $1.80 | $1.80 |
| 44 | Temp PVT MK L8 T4 tape (70307140) | LF | 502 | $2.66 | $2.60 | $12.00 | $2.90 | $2.40 | $2.60 |
| 45 | Temp PVT MK L12 T4 tape (70307160) | LF | 191 | $4.33 | $4.20 | $15.00 | $4.50 | $3.60 | $4.00 |
| 46 | Temp conc barrier (70400100) | LF | 1,021 | $38.84 | $25.00 | $30.00 | $55.00 | $37.20 | $26.00 |
| 47 | Rel temp conc barrier (70400200) | LF | 972 | $12.21 | $7.00 | $20.00 | $7.00 | $8.50 | $5.00 |
| 48 | Imp attn temp FRN TL2 (70600255) | EACH | 4 | $4,735.00 | $4,700.00 | $6,500.00 | $5,000.00 | $4,267.00 | $4,400.00 |
| 49 | Imp attn rel FRN TL2 (70600322) | EACH | 2 | $3,451.10 | $2,300.00 | $2,500.00 | $2,500.00 | $2,111.00 | $2,200.00 |
| 50 | THPL PVT MK LTR & sym (78000100) | SF | 221 | $9.99 | $10.00 | $8.25 | $8.90 | $7.50 | $9.00 |
| 51 | THPL PVT MK line 4 (78000200) | LF | 2,963 | $1.39 | $1.40 | $1.38 | $1.40 | $1.25 | $1.25 |
| 52 | THPL PVT MK line 8 (78000500) | LF | 80 | $2.22 | $2.50 | $2.92 | $3.10 | $2.65 | $2.00 |
| 53 | THPL PVT MK line 24 (78000650) | LF | 60 | $9.99 | $10.00 | $8.25 | $8.90 | $7.50 | $9.00 |
| 54 | Pref PL PM TD STD L 7 (78004635) | LF | 144 | $12.93 | $13.00 | $19.80 | $21.40 | $18.00 | $12.00 |
| 55 | Mod ureth PM line 4 (78009004) | LF | 1,298 | $4.16 | $4.00 | $3.85 | $4.10 | $3.50 | $4.00 |
| 56 | GRV RCSD PVT MRKG 8 (78011040) | LF | 144 | $8.60 | $8.00 | $11.00 | $11.90 | $10.00 | $8.00 |
| 57 | PVT MKG rem WTR blast (78300202) | SF | 1,594 | $2.77 | $3.00 | $5.50 | $4.10 | $2.85 | $2.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.