IDOT contract 80B76 bid tabulation

Section 2025-2038-I,PP,DR. Let by Illinois DOT on April 24, 2026, Will, District 01. 2 bids received; low bid $1,101,862 by D. Construction, Inc..

Owner
Illinois DOT
Letting
24 APR 2026
Pay items
71
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1D. Construction, Inc.$1,101,862Low
2MYS, Incorporated$1,474,413+34%
IDOT contract 80B76: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. D. Construction, Inc.2. MYS, Incorporated
1Reloc exist tanks (X0321835)EACH1$7,500.00$5,003.39
2Engrs FLD ofc TY A D1 (X6700407)CAL MO12$12,000$3,164.39
3TR C-prot expressways (X7011015)LS1$18,000$18,057
4Temp info signing (X7200061)SF100$30.00$27.72
5Rem & rein sign panel (X7200075)SF8$1,000.00$138.62
6Conc step remov (Z0012455)EACH1$400.00$6,105.11
7STR rep con DP = < 5 (Z0012754)SF20$500.00$415.86
8F&I static scale comp (Z0025710)LS1$233,200$371,503
9Earth excavation (20200100)CY130$35.00$109.15
10Rem & disp uns matl (20201200)CY5$150.00$332.87
11Furnished excavation (20400800)CY1,480$28.00$92.19
12Trench backfill (20800150)CY23$60.00$144.17
13Topsoil exc & plac (21101505)CY400$25.00$55.45
14Topsoil F & P 4 (21101615)SY4,005$6.50$8.00
15Seeding CL 2A (25000210)ACRE0.50$2,321.00$2,441.94
16Seeding CL 4A (25000312)ACRE0.50$1,331.00$2,333.27
17Seeding CL 5 (25000320)ACRE0.50$2,662.00$6,729.20
18Nitrogen fert nutr (25000400)LB30$3.30$3.88
19Phosphorus fert nutr (25000500)LB30$3.30$3.88
20Potassium fert nutr (25000600)LB30$3.30$3.88
21Mowing (25000750)ACRE1$110.00$859.45
22Erosion contr blanket (25100630)SY3,973$2.20$2.16
23Temp eros contr seed (28000250)LB247$5.50$6.65
24Perimeter eros bar (28000400)LF42$27.50$19.96
25Agg subgrade impr 12 (30300112)SY196$30.00$83.46
26Welded wire reinf (42000060)SY100$25.00$15.45
27PC conc sidewalk 5 (42400200)SF690$14.00$19.91
28Detectable warnings (42400800)SF10$100.00$49.45
29Comb curb gutter rem (44000500)LF20$30.00$30.05
30Sidewalk rem (44000600)SF442$5.00$3.58
31Median removal (44003100)SF698$6.00$11.54
32Paved SHLD removal (44004250)SY739$16.00$38.21
33CL B patch T2 13 (44201007)SY223$300.00$425.59
34CL B patch T3 13 (44201011)SY20$300.00$364.61
35CL B patch T4 13 (44201013)SY80$300.00$356.45
36Dowel bars 1 1/2 (44201299)EACH650$20.00$67.54
37Saw cuts (44213200)LF1,114$6.00$5.54
38Tie bars 3/4 (44213204)EACH287$20.00$51.46
39HMA shoulders 8 (48203029)SY224$67.00$94.26
40Rem exist sup-STR (50101500)EACH1$31,000$51,747
41Conc rem (50102400)CY15$1,550.00$560.68
42Conc headwall removal (50104400)EACH3$500.00$907.04
43Pipe culvert remov (50105220)LF61$20.00$44.36
44Conc struct (50300225)CY11.20$2,200.00$4,990.34
45Protective coat (50300300)SY75$1.00$2.74
46Conc supstr app slab (50301350)CY3.80$1,000.00$869.77
47F & E struct steel (50500405)LB4,780$10.00$0.02
48Reinf bars, epoxy CTD (50800205)LB1,560$3.00$7.69
49PRC flar end sec 24 (54213669)EACH1$2,200.00$2,661.52
50Storm sew CL A 2 12 (550A0340)LF154$89.00$177.43
51Storm sew CL A 2 18 (550A0380)LF97$98.00$188.52
52Storm sew CL A 2 24 (550A0410)LF163$114.00$243.97
53Man TA 5 dia T1F CL (60221100)EACH1$5,220.00$6,653.79
54Man TA 6 dia T1F CL (60223800)EACH1$6,230.00$9,426.20
55Inlets TA T24F&G (60237470)EACH3$2,440.00$2,772.41
56Comb CC&G TY B-6.24 (60605000)LF490$50.00$50.25
57Conc med TSM6.12 (60622800)SF688$30.00$37.54
58Non SPL waste disposl (66900200)CY700$80.00$144.46
59Soil disposal analy (66900530)EACH2$3,850.00$1,607.99
60Reg sub P-const plan (66901001)LS1$2,750.00$3,437.79
61Reg sub F con report (66901003)LS1$2,750.00$1,330.75
62Reg sub mon (66901006)CAL DAY10$1,000.00$804.00
63Mobilization (67100100)LS1$61,200$85,929
64SHRT TRM pavt MK rem (70300150)SF400$4.00$3.33
65Temp PVT MK L8 T4 tape (70307140)LF600$5.00$2.66
66Teles STL sin support (72800100)LF15$30.00$19.96
67Base tel STL sin supp (73100100)EACH1$300.00$250.00
68Mod ureth PM LTR-sym (78009000)SF21$71.50$5.54
69Mod ureth PM line 6 (78009006)LF532$12.25$2.66
70Mod ureth PM line 12 (78009012)LF54$49.50$4.93
71Mod ureth PM line 24 (78009024)LF12$107.25$10.20
IDOT contract 80B76: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy