IDOT contract 62X52 bid tabulation
Section 2024-1015-SCR. Let by Illinois DOT on June 12, 2026, Dupage, District 01. 4 bids received; low bid $266,169 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 12 JUN 2026
- Pay items
- 48
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $266,169 | Low |
| 2 | Alliance Contractors, Inc. | $303,313 | +14% |
| 3 | MYS, Incorporated | $336,737 | +27% |
| 4 | Herlihy Mid-Continent Company | $419,836 | +58% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Alliance Contractors, Inc. | 3. MYS, Incorporated | 4. Herlihy Mid-Continent Company |
|---|---|---|---|---|---|---|---|
| 1 | Cofferdam typ 1 IS WW (X5021512) | EACH | 1 | $0.01 | $5,000.00 | $31,322 | $36,000 |
| 2 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 12 | $5,000.00 | $500.00 | $2,283.51 | $5,860.00 |
| 3 | Traf cont & prot SPL (X7010216) | LS | 1 | $33,500 | $8,000.00 | $22,492 | $78,000 |
| 4 | Temp info signing (X7200061) | SF | 89 | $30.00 | $16.00 | $22.23 | $20.00 |
| 5 | RRPM reflector removl (X7830050) | EACH | 9 | $20.00 | $12.00 | $8.89 | $8.00 |
| 6 | RRPM reflector replac (X7830052) | EACH | 9 | $82.50 | $15.00 | $17.79 | $75.00 |
| 7 | Construction layout (Z0013798) | LS | 1 | $5,000.00 | $1.00 | $2,106.44 | $6,200.00 |
| 8 | Porous gran embank (20700220) | CY | 35.60 | $60.00 | $100.00 | $258.20 | $110.00 |
| 9 | Seeding CL 2A (25000210) | ACRE | 0.25 | $5,324.00 | $4,800.00 | $5,335.56 | $4,800.00 |
| 10 | Seeding CL 4 (25000310) | ACRE | 0.25 | $5,324.00 | $4,800.00 | $5,335.56 | $4,800.00 |
| 11 | Nitrogen fert nutr (25000400) | LB | 23 | $3.30 | $6.00 | $6.67 | $6.00 |
| 12 | Phosphorus fert nutr (25000500) | LB | 23 | $3.30 | $6.00 | $6.67 | $6.00 |
| 13 | Potassium fert nutr (25000600) | LB | 23 | $3.30 | $6.00 | $6.67 | $6.00 |
| 14 | Erosion contr blanket (25100630) | SY | 52 | $55.00 | $6.00 | $6.67 | $6.00 |
| 15 | Temp ditch checks (28000305) | LF | 10 | $55.00 | $50.00 | $55.58 | $50.00 |
| 16 | Perimeter eros bar (28000400) | LF | 30 | $55.00 | $25.00 | $27.79 | $25.00 |
| 17 | Agg subgrade improve (30300001) | CY | 2 | $250.00 | $100.00 | $354.39 | $480.00 |
| 18 | Agg subgrade impr 12 (30300112) | SY | 23 | $100.00 | $25.00 | $47.72 | $68.50 |
| 19 | HMA base cse 8 (35501316) | SY | 6 | $0.01 | $961.43 | $881.63 | $1,000.00 |
| 20 | Bit matls tack CT (40600290) | LB | 11 | $0.01 | $0.02 | $14.33 | $0.10 |
| 21 | HMA SC IL-9.5 D N50 (40604060) | TON | 1 | $2,500.00 | $1,603.94 | $2,005.71 | $650.00 |
| 22 | Pavement rem (44000100) | SY | 6 | $175.00 | $100.00 | $329.23 | $218.00 |
| 23 | Paved SHLD removal (44004250) | SY | 18 | $90.00 | $100.00 | $125.33 | $112.00 |
| 24 | HMA shoulders 10 (48203037) | SY | 18 | $300.00 | $1,152.86 | $80.88 | $1,000.00 |
| 25 | Conc rem (50102400) | CY | 10.20 | $800.00 | $100.00 | $135.23 | $650.00 |
| 26 | Structure excavation (50200100) | CY | 35 | $75.00 | $100.00 | $453.66 | $115.00 |
| 27 | Reinf bars, epoxy CTD (50800205) | LB | 600 | $10.00 | $5.00 | $9.39 | $7.50 |
| 28 | Temp soil reten systm (52200020) | SF | 160 | $70.00 | $100.00 | $241.03 | $159.00 |
| 29 | STR rep con DP = < 5 (53212754) | SF | 64 | $200.00 | $290.00 | $350.42 | $243.00 |
| 30 | STR rep con DP over 5 (53212755) | SF | 16 | $300.00 | $290.00 | $503.06 | $1,200.00 |
| 31 | Expan bolts 3/4 (54002020) | EACH | 27 | $100.00 | $50.00 | $143.27 | $750.00 |
| 32 | Conc box cul (54003000) | CY | 2.50 | $5,000.00 | $40,000 | $12,393 | $4,600.00 |
| 33 | Concrete sealer (58700300) | SF | 7 | $3.00 | $10.00 | $2.99 | $35.00 |
| 34 | Non SPL waste disposl (66900200) | CY | 35 | $100.00 | $140.00 | $157.56 | $95.00 |
| 35 | Soil disposal analy (66900530) | EACH | 1 | $1,595.00 | $1,450.00 | $1,611.78 | $1,785.00 |
| 36 | Reg sub P-const plan (66901001) | LS | 1 | $3,410.00 | $3,100.00 | $3,445.89 | $3,400.00 |
| 37 | Reg sub F con report (66901003) | LS | 1 | $1,320.00 | $1,200.00 | $1,333.89 | $500.00 |
| 38 | Reg sub mon (66901006) | CAL DAY | 20 | $1,000.00 | $680.00 | $755.87 | $715.00 |
| 39 | Mobilization (67100100) | LS | 1 | $15,500 | $39,507 | $27,900 | $25,000 |
| 40 | Changeable message SN (70107025) | CAL DAY | 70 | $50.00 | $30.00 | $44.47 | $40.00 |
| 41 | SHRT TRM pavt MK rem (70300150) | SF | 1,530 | $0.01 | $0.40 | $1.00 | $0.90 |
| 42 | Temp PVT MK L4 T4 tape (70307120) | LF | 4,635 | $0.01 | $1.30 | $1.45 | $1.30 |
| 43 | Temp conc barrier (70400100) | LF | 225 | $35.00 | $30.00 | $46.67 | $24.00 |
| 44 | Imp attn temp NRD TL3 (70600250) | EACH | 2 | $6,500.00 | $3,600.00 | $4,223.99 | $3,800.00 |
| 45 | Reloc sin pan assy TA (72400500) | EACH | 1 | $104.50 | $350.00 | $105.60 | $95.00 |
| 46 | THPL PVT MK line 4 (78000200) | LF | 1,575 | $2.59 | $2.01 | $2.61 | $2.35 |
| 47 | THPL PVT MK line 12 (78000600) | LF | 220 | $11.88 | $9.00 | $12.01 | $10.80 |
| 48 | PVT MKG rem WTR blast (78300202) | SF | 740 | $4.40 | $4.50 | $4.45 | $4.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.