IDOT contract 80B48 bid tabulation
Section (1010B-89). Let by Illinois DOT on April 24, 2026, Cook, District 01. 4 bids received; low bid $1,108,954 by Martam Construction Incorporated.
- Owner
- Illinois DOT
- Letting
- 24 APR 2026
- Pay items
- 70
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Martam Construction Incorporated | $1,108,954 | Low |
| 2 | MYS, Incorporated | $1,209,633 | +9.0% |
| 3 | Lorig Construction Company | $1,306,297 | +18% |
| 4 | Areatha Construction Co., Inc. | $1,314,393 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Martam Construction Incorporated | 2. MYS, Incorporated | 3. Lorig Construction Company | 4. Areatha Construction Co., Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Masonry reconstruct (X0325154) | SY | 8 | $1,440.00 | $2,038.13 | $800.00 | $1,250.00 |
| 2 | Clean reseal RLF JNT (X0326766) | LF | 122 | $38.00 | $105.41 | $90.00 | $135.25 |
| 3 | CC&G RMVL repl > 10FT (X4400503) | LF | 260 | $68.00 | $101.93 | $155.00 | $115.55 |
| 4 | BR deck grooving long (X5030250) | SY | 968 | $9.00 | $8.19 | $10.00 | $7.90 |
| 5 | Clean/paint bearings (X5060700) | EACH | 16 | $3,500.00 | $3,661.60 | $3,300.00 | $4,114.50 |
| 6 | Traf cont & prot SPL (X7010216) | LS | 1 | $100,000 | $24,156 | $145,000 | $31,490 |
| 7 | Temp info signing (X7200061) | SF | 51.40 | $24.00 | $17.75 | $24.00 | $15.00 |
| 8 | Appr slab repair (FD) (Z0001700) | SY | 10 | $1,450.00 | $1,475.40 | $2,000.00 | $1,642.65 |
| 9 | Appr slab repair (PD) (Z0001800) | SY | 3 | $1,250.00 | $2,105.73 | $1,900.00 | $1,303.90 |
| 10 | Debris removal (Z0015550) | CY | 20 | $150.00 | $533.00 | $300.00 | $1,149.65 |
| 11 | Diamond grind BR sec (Z0029090) | SY | 887 | $12.00 | $13.31 | $13.00 | $19.90 |
| 12 | Polymer concrete (Z0041895) | CF | 11 | $1,150.00 | $1,523.32 | $1,800.00 | $2,590.85 |
| 13 | Earth excavation (20200100) | CY | 20 | $180.00 | $136.98 | $175.00 | $202.70 |
| 14 | Perimeter eros bar (28000400) | LF | 845 | $8.00 | $4.99 | $7.00 | $6.40 |
| 15 | Inlet & pipe protect (28000500) | EACH | 9 | $200.00 | $194.18 | $400.00 | $300.00 |
| 16 | Inlet filters (28000510) | EACH | 4 | $250.00 | $166.44 | $400.00 | $300.00 |
| 17 | Bit matls tack CT (40600290) | LB | 444 | $0.10 | $0.11 | $4.00 | $4.00 |
| 18 | Long joint sealant (40600370) | LF | 130 | $80.00 | $83.22 | $125.00 | $125.00 |
| 19 | HMA surf rem butt JT (40600982) | SY | 344 | $22.00 | $22.19 | $62.00 | $4.80 |
| 20 | HMA SC IL-9.5 D N70 (40604062) | TON | 73 | $645.00 | $638.01 | $500.00 | $490.00 |
| 21 | Conc rem (50102400) | CY | 39.20 | $2,300.00 | $1,997.23 | $2,700.00 | $2,077.35 |
| 22 | Conc sup-STR (50300255) | CY | 42.90 | $3,200.00 | $3,606.12 | $2,400.00 | $3,106.80 |
| 23 | Protective coat (50300300) | SY | 1,255 | $1.00 | $2.74 | $3.00 | $3.55 |
| 24 | Reinf bars, epoxy CTD (50800205) | LB | 6,830 | $4.00 | $4.86 | $3.00 | $3.60 |
| 25 | Bar splicers (50800515) | EACH | 76 | $53.00 | $48.35 | $65.00 | $64.10 |
| 26 | Pref JT strip seal (52000110) | LF | 124 | $285.00 | $371.71 | $330.00 | $591.45 |
| 27 | Deck slab rep (FD-T1) (53016001) | SY | 1 | $4,500.00 | $2,066.51 | $3,000.00 | $9,980.95 |
| 28 | BR deck scar 3/4 (53101002) | SY | 915 | $48.00 | $78.59 | $111.00 | $155.25 |
| 29 | BR DK LTX C oly 2 3/4 (53101410) | SY | 915 | $132.00 | $181.66 | $180.00 | $230.00 |
| 30 | STR rep con DP = < 5 (53212754) | SF | 126 | $220.00 | $277.39 | $450.00 | $214.45 |
| 31 | STR rep con DP over 5 (53212755) | SF | 25 | $240.00 | $360.61 | $450.00 | $261.35 |
| 32 | Man adjust (60255500) | EACH | 3 | $500.00 | $953.56 | $2,200.00 | $1,100.00 |
| 33 | Inlets adjust (60260100) | EACH | 4 | $500.00 | $781.61 | $1,500.00 | $1,100.00 |
| 34 | SPBGR TY A 6FT posts (63000001) | LF | 437.50 | $35.00 | $35.47 | $33.00 | $31.95 |
| 35 | Traf bar term T6A (63100087) | EACH | 4 | $4,200.00 | $4,281.85 | $4,800.00 | $3,859.00 |
| 36 | TR bar TRM T1 SPL tan (63100167) | EACH | 4 | $3,600.00 | $3,677.13 | $3,600.00 | $3,314.00 |
| 37 | Guardrail remov (63200310) | LF | 837.50 | $9.00 | $9.28 | $5.00 | $8.35 |
| 38 | Non SPL waste disposl (66900200) | CY | 20 | $95.00 | $144.54 | $100.00 | $298.70 |
| 39 | Soil disposal analy (66900530) | EACH | 1 | $1,400.00 | $2,219.15 | $2,500.00 | $1,875.00 |
| 40 | Reg sub P-const plan (66901001) | LS | 1 | $7,500.00 | $3,439.68 | $3,100.00 | $3,400.00 |
| 41 | Reg sub F con report (66901003) | LS | 1 | $1,500.00 | $1,331.49 | $1,200.00 | $500.00 |
| 42 | Reg sub mon (66901006) | CAL DAY | 6 | $100.00 | $754.51 | $800.00 | $715.00 |
| 43 | Engr field office A (67000400) | CAL MO | 6 | $4,500.00 | $3,772.83 | $4,000.00 | $2,500.00 |
| 44 | Mobilization (67100100) | LS | 1 | $66,000 | $96,479 | $70,000 | $78,900 |
| 45 | Changeable message SN (70107025) | CAL DAY | 108 | $38.00 | $33.29 | $35.00 | $30.00 |
| 46 | Short term pavt mking (70300100) | LF | 148 | $2.00 | $1.11 | $2.00 | $1.00 |
| 47 | SHRT TRM pavt MK rem (70300150) | SF | 3,532.20 | $0.35 | $0.55 | $0.35 | $0.75 |
| 48 | Temp PVT MK LTR & sym T4 tape (70307100) | SF | 36.40 | $16.00 | $4.99 | $15.00 | $3.75 |
| 49 | Temp PVT MK L4 T4 tape (70307120) | LF | 11,281 | $1.40 | $1.50 | $1.35 | $1.20 |
| 50 | Temp PVT MK L6 T4 tape (70307130) | LF | 28 | $3.00 | $2.22 | $2.50 | $1.80 |
| 51 | Temp PVT MK L8 T4 tape (70307140) | LF | 198 | $3.00 | $2.77 | $3.00 | $2.40 |
| 52 | Temp PVT MK L12 T4 tape (70307160) | LF | 459 | $5.00 | $4.33 | $4.00 | $3.60 |
| 53 | Temp PVT MK L24 T4 tape (70307210) | LF | 84 | $16.00 | $8.32 | $15.00 | $7.20 |
| 54 | Temp conc barrier (70400100) | LF | 708 | $35.00 | $52.33 | $28.00 | $38.00 |
| 55 | Rel temp conc barrier (70400200) | LF | 804 | $12.00 | $11.77 | $6.00 | $12.00 |
| 56 | Imp attn temp FRN TL2 (70600255) | EACH | 2 | $5,100.00 | $7,545.11 | $4,800.00 | $4,816.00 |
| 57 | Imp attn rel FRN TL2 (70600322) | EACH | 4 | $2,400.00 | $665.74 | $2,400.00 | $2,228.00 |
| 58 | Terminal marker - DA (72501000) | EACH | 4 | $40.00 | $55.48 | $50.00 | $35.00 |
| 59 | THPL PVT MK LTR & sym (78000100) | SF | 188 | $9.00 | $8.21 | $8.00 | $7.00 |
| 60 | THPL PVT MK line 4 (78000200) | LF | 3,340 | $1.50 | $1.39 | $1.25 | $1.45 |
| 61 | THPL PVT MK line 12 (78000600) | LF | 138 | $6.00 | $4.11 | $5.00 | $3.80 |
| 62 | THPL PVT MK line 24 (78000650) | LF | 44 | $12.00 | $8.21 | $10.00 | $5.75 |
| 63 | Pref PL PM TD STD L4 (78004620) | LF | 364 | $8.00 | $8.65 | $7.00 | $16.00 |
| 64 | Pref PL PM TD STD L 7 (78004635) | LF | 204 | $10.00 | $17.36 | $9.00 | $24.00 |
| 65 | Mod ureth PM line 12 (78009012) | LF | 90 | $27.00 | $63.25 | $25.00 | $55.00 |
| 66 | GRV RCSD PVT MRKG 5 (78011025) | LF | 364 | $6.00 | $8.32 | $5.00 | $3.60 |
| 67 | GRV RCSD PVT MRKG 8 (78011040) | LF | 204 | $9.00 | $11.65 | $8.00 | $5.45 |
| 68 | Grdrail ref type A (78200005) | EACH | 12 | $15.00 | $11.10 | $10.00 | $10.00 |
| 69 | PVT MKG rem WTR blast (78300202) | SF | 1,323 | $7.00 | $4.99 | $6.00 | $3.50 |
| 70 | Main EX TR sig instal (85000200) | EACH | 1 | $15,000 | $7,225.68 | $4,000.00 | $1,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 24, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.