IDOT contract 62V45 bid tabulation

Section FAP. Let by Illinois DOT on July 31, 2026, Cook, District 01. 4 bids received; low bid $1,062,900 by D. Construction, Inc..

Owner
Illinois DOT
Letting
31 JUL 2026
Pay items
73
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1D. Construction, Inc.$1,062,900Low
2K-Five Construction Corporation$1,136,281+7.0%
3Gallagher Asphalt Corporation$1,174,699+11%
4Iroquois Paving Corporation$1,276,162+20%
IDOT contract 62V45: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. D. Construction, Inc.2. K-Five Construction Corporation3. Gallagher Asphalt Corporation4. Iroquois Paving Corporation
1Temporary ramp SPL (X4060995)SY48$0.01$25.00$70.00$0.01
2CC&G RMVL repl < = 10 (X4400501)LF10$82.50$75.00$75.00$178.00
3CC&G RMVL repl > 10FT (X4400503)LF280$60.50$65.00$55.00$121.00
4Part depth patch SPL (X4421003)EACH3$500.00$500.00$1,500.00$159.00
5FR & lids adjust SPL (X6030310)EACH1$1,320.00$6,300.00$1,200.00$2,350.00
6Engrs FLD ofc TY A D1 (X6700407)CAL MO6$5,000.00$3,500.00$3,800.00$3,750.00
7Traf cont & prot SPL (X7010216)LS1$68,575$45,000$50,000$68,000
8Temp info signing (X7200061)SF114$30.00$25.00$25.00$16.50
9Det loop repl (X8860105)LF327$41.25$37.50$38.00$35.00
10Temp TR signal timing (X8900104)EACH1$302.50$275.00$275.00$1,400.00
11Construction layout (Z0013798)LS1$7,500.00$7,500.00$15,000$6,250.00
12Drainage STR cleaned (Z0018500)EACH2$1,650.00$1,500.00$1,500.00$1,035.00
13RR prot liability ins (Z0048665)LS1$4,153.60$3,500.00$4,300.00$0.01
14Earth excavation (20200100)CY13$93.50$150.00$85.00$150.00
15Topsoil F & P 4 (21101615)SY65$49.50$50.00$5.00$46.50
16Sodding salt tolerant (25200110)SY65$148.50$50.00$195.00$10.35
17Bit matls tack CT (40600290)LB5,783$0.01$0.01$1.50$0.01
18Long joint sealant (40600370)LF5,116$3.14$2.70$4.00$3.45
19Mix CR JTS flangewys (40600400)TON13$2.25$50.00$550.00$0.01
20HMA surf rem butt JT (40600982)SY81$25.00$0.01$0.01$0.01
21HMA BC IL-9.5 N70 (40602985)TON960$84.00$100.00$122.90$99.50
22P HMA SC SMA 9.5 F N80 (40605026)TON840$128.00$135.00$174.40$143.00
23Protective coat (42001300)SY44$2.20$5.00$2.00$6.00
24HMA surf rem 3 3/4 (44000164)SY8,567$3.25$5.50$6.40$4.80
25CL B patch T1 13 (44201003)SY25$275.00$10.00$250.00$370.00
26CL B patch T2 13 (44201007)SY199$275.00$285.00$250.00$370.00
27CL B patch T3 13 (44201011)SY273$242.00$285.00$220.00$370.00
28CL B patch T4 13 (44201013)SY495$242.00$285.00$220.00$370.00
29Dowel bars 1 1/2 (44201299)EACH608$15.40$40.00$14.00$0.01
30CL D patch T1 13 (44201798)SY10$250.00$150.00$460.00$260.00
31CL D patch T2 13 (44201803)SY95$145.00$70.00$230.00$180.00
32CL D patch T3 13 (44201807)SY94$145.00$60.00$170.00$170.00
33CL D patch T4 13 (44201809)SY518$140.00$55.00$130.00$145.00
34Tie bars 1/2 (44213198)EACH528$6.60$15.00$6.00$0.01
35Saw cuts (44213200)LF5,000$3.30$8.00$3.00$0.01
36Crack routing (pavt) (45100100)LF99,809$0.11$0.10$0.10$0.10
37Crack filling (45100200)LB28,515$3.03$3.45$3.10$3.10
38JT CR RT PCC pav/SHLD (45200100)LF21,082$0.11$0.20$0.15$0.13
39JT or crack filling (45200300)LB6,023$3.34$3.45$5.55$5.75
40Inlets adjust (60260100)EACH9$495.00$800.00$450.00$585.00
41Inlets reconst (60262700)EACH1$2,200.00$2,500.00$2,000.00$2,885.00
42FR & lids T1 CL (60406100)EACH1$495.00$1,000.00$450.00$1,350.00
43Non SPL waste disposl (66900200)CY13$137.50$100.00$125.00$89.00
44Soil disposal analy (66900530)EACH1$1,750.00$1,450.00$1,600.00$1,550.00
45Reg sub P-const plan (66901001)LS1$2,250.00$3,100.00$3,500.00$2,275.00
46Reg sub F con report (66901003)LS1$2,250.00$1,200.00$500.00$2,275.00
47Reg sub mon (66901006)CAL DAY4$1,000.00$680.00$715.00$1,600.00
48Mobilization (67100100)LS1$63,500$60,200$55,553$60,000
49TR cont & prot 701601 (70102630)LS1$0.01$100.00$100.00$4,150.00
50TR cont & prot 701602 (70102632)LS1$0.01$100.00$100.00$1.05
51TR cont & prot 701701 (70102637)EACH1$0.01$100.00$100.00$1.05
52Pavt MK blkout tape 6 (70107006)LF802$0.01$2.00$2.00$2.00
53Changeable message SN (70107025)CAL DAY6$500.00$75.00$75.00$103.00
54Short term pavt mking (70300100)LF10,197$0.01$0.50$0.01$3.00
55SHRT TRM pavt MK rem (70300150)SF850$0.01$6.00$0.01$0.35
56Temp PVT MK LTR & sym paint (70300211)SF376$0.01$1.40$1.40$0.01
57Temp PVT MK line 4 - paint (70300221)LF2,572$0.01$0.46$0.50$0.01
58Temp PVT MK line 6 - paint (70300241)LF414$0.01$0.72$0.75$0.01
59Temp PVT MK line 12 - paint (70300261)LF2,458$0.01$1.40$1.40$0.01
60Temp PVT MK L4 T4 tape (70307120)LF17,351$0.01$1.30$1.30$1.40
61THPL PVT MK LTR & sym (78000100)SF188$7.43$9.00$7.00$9.25
62THPL PVT MK line 4 (78000200)LF1,286$1.38$1.50$1.30$1.30
63THPL PVT MK line 6 (78000400)LF207$2.20$3.00$2.00$3.10
64Pref PL PM TD STD L 7 (78004635)LF1,740$9.35$8.75$8.50$8.55
65Mod ureth PM LTR-sym (78009000)SF1,716$6.60$6.50$6.00$6.50
66Mod ureth PM line 4 (78009004)LF14,783$0.55$0.75$0.50$0.80
67Mod ureth PM line 6 (78009006)LF8,390$1.10$1.50$1.00$1.50
68Mod ureth PM line 8 (78009008)LF1,239$1.38$3.00$1.25$3.10
69Mod ureth PM line 12 (78009012)LF2,528$3.30$3.00$3.00$3.10
70Mod ureth PM line 24 (78009024)LF1,445$6.60$7.00$6.00$7.25
71GRV RCSD PVT MRKG 8 (78011040)LF1,089$1.65$2.00$1.50$1.80
72Raised refl pavt MKR (78100100)EACH130$52.80$55.00$48.00$51.75
73Raised ref PVT MK rem (78300200)EACH130$10.00$25.00$0.01$0.01
IDOT contract 62V45: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of July 31, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy