Curran Contracting Company: IDOT bid record
Curran Contracting Company submitted 144 bids on Illinois DOT contracts in the data, from 05 MAR 2021 to 18 SEP 2026, and was the low bidder on 43 of them (30%). When it was not low, its total sat a median +10% above the low bid.
- Owner
- Illinois DOT
- Low bid volume
- $106,659,757
- Latest bid
- 18 SEP 2026
- Data through
- 18 SEP 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2021 | 23 | 5 | 22% |
| 2022 | 28 | 11 | 39% |
| 2023 | 14 | 5 | 36% |
| 2024 | 29 | 8 | 28% |
| 2025 | 30 | 11 | 37% |
| 2026 | 20 | 3 | 15% |
By district
| District | Bids | Low bids | Win rate |
|---|---|---|---|
| District 01 | 77 | 16 | 21% |
| District 03 | 40 | 21 | 53% |
| District 02 | 27 | 6 | 22% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Bit matls tack CT | 40600290 | LB | 125 | 80 (64%) | $0.01 | $0.01 |
| THPL PVT MK line 4 | 78000200 | LF | 102 | 74 (73%) | $0.72 | $0.88 |
| Short term pavt mking | 70300100 | LF | 98 | 71 (72%) | $0.40 | $1.01 |
| THPL PVT MK line 24 | 78000650 | LF | 87 | 61 (70%) | $5.00 | $6.00 |
| THPL PVT MK line 12 | 78000600 | LF | 86 | 58 (67%) | $2.50 | $3.10 |
| THPL PVT MK line 6 | 78000400 | LF | 83 | 58 (70%) | $1.15 | $1.40 |
| THPL PVT MK LTR & sym | 78000100 | SF | 82 | 54 (66%) | $5.00 | $5.75 |
| Trainees TPG | Z0076604 | HR | 42 | 42 (100%) | $15.00 | $15.00 |
| Raised refl pavt MKR | 78100100 | EACH | 68 | 40 (59%) | $38.50 | $48.00 |
| Temp info signing | Z0030850 | SF | 60 | 38 (63%) | $14.05 | $18.00 |
| Trainees | Z0076600 | HR | 38 | 38 (100%) | $0.80 | $0.80 |
| SHRT TRM pavt MK rem | 70300150 | SF | 92 | 36 (39%) | $2.00 | $1.20 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Peter Baker & Son Co. | 54 | 38 of 54 |
| Builders Paving, LLC | 37 | 20 of 37 |
| Rock Road Companies, Inc. | 34 | 16 of 34 |
| Plote Construction, Inc. | 29 | 15 of 29 |
| Payne & Dolan, Inc. | 22 | 14 of 22 |
| Schroeder Asphalt Services, Inc. | 18 | 7 of 18 |
| William Charles Construction Company, LLC | 15 | 7 of 15 |
| Geske and Sons, Inc. | 15 | 11 of 15 |
| Martin & Company Excavating | 14 | 8 of 14 |
| Arrow Road Construction Co. | 13 | 5 of 13 |
Latest bids
| Let | Contract | District | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 18 SEP 2026 | 62X33 | District 01 | Section 2024-999-RS | 2 of 2 | $5,077,000 | +15% |
| 18 SEP 2026 | 64V52 | District 02 | Section 6RS | 3 of 3 | $3,743,691 | +28% |
| 31 JUL 2026 | 66T53 | District 03 | Section (124)RS-4 | 1 of 2 | $2,389,089 | Low, 2.0% under the second |
| 12 JUN 2026 | 61L30 | District 01 | Campton Hills, section 24-00012-00-FP | 4 of 4 | $3,758,911 | +30% |
| 12 JUN 2026 | 61M42 | District 01 | Sugar Grove, section 25-00037-00-RS | 4 of 4 | $831,076 | +27% |
| 12 JUN 2026 | 61M43 | District 01 | Sugar Grove, section 25-00038-00-RS | 4 of 4 | $874,971 | +26% |
| 12 JUN 2026 | 80B23 | District 01 | Section 2025-2002-RS | 3 of 3 | $3,464,641 | +9.0% |
| 12 JUN 2026 | 80C45 | District 01 | Section 2025-2102-RS | 2 of 4 | $1,622,323 | +1.0% |
| 12 JUN 2026 | 80D46 | District 01 | Section 2026-2181-C,HBK | 1 of 7 | $1,087,000 | Low, 5.0% under the second |
| 24 APR 2026 | 80B10 | District 01 | Section 2025-1098-RS | 3 of 3 | $1,245,265 | +5.0% |
| 24 APR 2026 | 80C85 | District 01 | Section 2025-2127-R,C,TS,SW | 2 of 4 | $50,591,713 | +2.0% |
| 24 APR 2026 | 85793 | District 02 | Project Number: 8Pwj-710 / /, section 25-00358-00-RS | 2 of 3 | $1,624,626 | +9.0% |
| 27 FEB 2026 | 61M19 | District 01 | Bull Valley, section 22-00009-00-RS | 6 of 6 | $682,645 | +25% |
| 27 FEB 2026 | 61M23 | District 01 | Lakewood, section 22-00016-00-RS | 5 of 5 | $953,197 | +22% |
| 27 FEB 2026 | 64U03 | District 02 | Section (103-1,2)RA&RS | 2 of 2 | $14,968,831 | +3.0% |
| 27 FEB 2026 | 66P67 | District 03 | Section (19,20)RS-5 | 2 of 2 | $3,692,365 | +2.0% |
| 16 JAN 2026 | 61L94 | District 01 | Woodstock, section 24-00116-00-RS | 6 of 7 | $1,111,123 | +20% |
| 16 JAN 2026 | 61M07 | District 01 | Spring Grove, section 23-00021-00-RS | 1 of 4 | $910,908 | Low, 13% under the second |
| 16 JAN 2026 | 80B29 | District 01 | Section 2025-2010-RS | 4 of 4 | $1,294,618 | +28% |
| 16 JAN 2026 | 80B50 | District 01 | Section 2025-2069-RS | 5 of 5 | $2,377,927 | +32% |
| 19 SEP 2025 | 87846 | District 03 | Oswego, section 23-00052-02-PV | 4 of 4 | $12,644,154 | +18% |
| 13 JUN 2025 | 61L50 | District 01 | Johnsburg, section 23-00017-00-RS | 3 of 4 | $1,935,020 | +10% |
| 13 JUN 2025 | 61L51 | District 01 | Prairie Grove, section 24-00012-00-RS | 3 of 4 | $739,647 | +26% |
| 13 JUN 2025 | 61L59 | District 01 | Hampshire, section 24-00022-00-RS | 1 of 4 | $308,598 | Low, 0.0% under the second |
| 13 JUN 2025 | 62L61 | District 01 | Section 2020-083-RS | 1 of 4 | $2,693,463 | Low, 14% under the second |
How this record was read
IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
- Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.