IDOT contract 61L50 bid tabulation
Johnsburg, section 23-00017-00-RS. Let by Illinois DOT on June 13, 2025, Mchenry, District 01. 4 bids received; low bid $1,758,088 by Geske and Sons, Inc..
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 61
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Geske and Sons, Inc. | $1,758,088 | Low |
| 2 | Peter Baker & Son Co. | $1,848,218 | +5.0% |
| 3 | Curran Contracting Company | $1,935,020 | +10% |
| 4 | Payne & Dolan, Inc. | $2,089,955 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Geske and Sons, Inc. | 2. Peter Baker & Son Co. | 3. Curran Contracting Company | 4. Payne & Dolan, Inc. |
|---|---|---|---|---|---|---|---|
| 1 | Washout basin (X0326806) | LS | 1 | $1,836.00 | $1,800.00 | $1,800.00 | $1,800.00 |
| 2 | Explor trench SPL (X2130010) | LF | 50 | $101.09 | $439.04 | $98.15 | $65.00 |
| 3 | HMA driveway pavt 3 (X4060280) | SY | 680 | $30.65 | $50.00 | $35.00 | $55.94 |
| 4 | HMA surf rem SPL (X4400196) | SY | 599 | $15.60 | $1.00 | $10.00 | $0.01 |
| 5 | Curb rem&repl > 10FT (X4400223) | LF | 13 | $68.09 | $66.75 | $100.00 | $66.75 |
| 6 | CC&G RMVL repl < = 10 (X4400501) | LF | 95 | $68.09 | $66.75 | $66.75 | $66.75 |
| 7 | CC&G RMVL repl > 10FT (X4400503) | LF | 2,717 | $54.01 | $52.95 | $52.95 | $52.95 |
| 8 | Pipe culvert rem SPL (X5015225) | LF | 123 | $28.43 | $57.29 | $27.60 | $50.00 |
| 9 | FR & lids adjust SPL (X6030310) | EACH | 6 | $950.00 | $1,350.00 | $921.00 | $1,850.00 |
| 10 | Temp info signing (X7200061) | SF | 103 | $16.80 | $16.00 | $16.00 | $20.00 |
| 11 | Construction layout (Z0013798) | LS | 1 | $5,000.00 | $5,800.00 | $17,000 | $5,000.00 |
| 12 | Earth excavation (20200100) | CY | 154 | $117.66 | $115.35 | $100.00 | $115.35 |
| 13 | Rem & disp uns matl (20201200) | CY | 95 | $139.28 | $136.55 | $200.00 | $136.55 |
| 14 | Furnished excavation (20400800) | CY | 14 | $86.70 | $85.00 | $100.00 | $85.00 |
| 15 | Trench backfill (20800150) | CY | 51 | $80.03 | $95.00 | $77.70 | $23.00 |
| 16 | Topsoil F & P 4 (21101615) | SY | 1,059 | $5.35 | $5.00 | $0.10 | $0.10 |
| 17 | Seeding CL 2A (25000210) | ACRE | 0.25 | $3,210.00 | $3,000.00 | $24,200 | $24,200 |
| 18 | Nitrogen fert nutr (25000400) | LB | 23 | $1.18 | $1.10 | $1.00 | $1.00 |
| 19 | Potassium fert nutr (25000600) | LB | 23 | $1.18 | $1.10 | $1.00 | $1.00 |
| 20 | Erosion contr blanket (25100630) | SY | 1,059 | $1.28 | $1.20 | $1.00 | $1.00 |
| 21 | Perimeter eros bar (28000400) | LF | 612 | $4.05 | $3.75 | $3.00 | $3.00 |
| 22 | Inlet filters (28000510) | EACH | 9 | $188.00 | $150.00 | $200.00 | $450.00 |
| 23 | Agg base cse B 4 (35101600) | SY | 385 | $11.73 | $11.50 | $11.50 | $11.50 |
| 24 | Bit matls tack CT (40600290) | LB | 33,175 | $0.01 | $0.01 | $0.01 | $0.01 |
| 25 | Long joint sealant (40600370) | LF | 18,849 | $2.98 | $3.71 | $3.20 | $2.90 |
| 26 | Mix CR JTS flangewys (40600400) | TON | 50 | $75.00 | $75.00 | $200.00 | $420.00 |
| 27 | HMA surf rem butt JT (40600982) | SY | 530 | $15.64 | $1.00 | $20.00 | $0.01 |
| 28 | HMA BC IL-19.0 N70 (40603085) | TON | 6,195 | $74.50 | $75.00 | $76.00 | $69.00 |
| 29 | HMA SC IL-9.5 D N70 (40604062) | TON | 4,820 | $84.15 | $78.00 | $82.00 | $78.00 |
| 30 | Incidental HMA surf (40800050) | TON | 75 | $84.15 | $250.00 | $125.00 | $168.00 |
| 31 | PC conc sidewalk 5 (42400200) | SF | 6,375 | $11.58 | $11.35 | $11.35 | $11.35 |
| 32 | Detectable warnings (42400800) | SF | 332 | $37.74 | $37.00 | $37.00 | $37.00 |
| 33 | HMA surf rem 3 1/2 (44000163) | SY | 49,148 | $3.11 | $3.75 | $3.90 | $5.25 |
| 34 | Drive pavement rem (44000200) | SY | 717 | $15.94 | $12.00 | $9.00 | $30.00 |
| 35 | Sidewalk rem (44000600) | SF | 2,915 | $4.13 | $4.05 | $4.05 | $4.05 |
| 36 | CL D patch T2 6 (44201717) | SY | 495 | $39.37 | $25.00 | $85.00 | $77.00 |
| 37 | CL D patch T3 6 (44201721) | SY | 495 | $39.37 | $25.00 | $65.00 | $61.00 |
| 38 | CL D patch T4 6 (44201723) | SY | 615 | $39.37 | $25.00 | $45.00 | $53.00 |
| 39 | Aggregate SHLDS B (48101200) | TON | 652 | $52.65 | $53.00 | $41.00 | $127.00 |
| 40 | PRC flar end sec 12 (54213657) | EACH | 2 | $2,143.43 | $513.00 | $2,081.00 | $4,785.00 |
| 41 | Storm sew CL A 1 12 (550A0050) | LF | 208 | $75.50 | $101.80 | $73.30 | $190.00 |
| 42 | Contr low-streng matl (59300100) | CY | 91 | $597.40 | $237.82 | $580.00 | $250.00 |
| 43 | CB TA 4 dia T8G (60200805) | EACH | 1 | $3,831.60 | $1,620.00 | $3,720.00 | $8,950.00 |
| 44 | Inlets TB T8G (60240301) | EACH | 1 | $3,100.30 | $420.00 | $3,010.00 | $5,150.00 |
| 45 | Mobilization (67100100) | LS | 1 | $27,390 | $108,860 | $115,000 | $190,000 |
| 46 | TR cont & prot 701501 (70102620) | LS | 1 | $18,060 | $45,400 | $20,000 | $15,255 |
| 47 | TR cont & prot 701502 (70102622) | LS | 1 | $1.00 | $1.00 | $1.00 | $100.00 |
| 48 | TR cont & prot 701701 (70102635) | LS | 1 | $1.00 | $1.00 | $1.00 | $100.00 |
| 49 | TR cont & prot 701801 (70102640) | LS | 1 | $1.00 | $1.00 | $1.00 | $100.00 |
| 50 | Short term pavt mking (70300100) | LF | 19,135 | $0.01 | $0.01 | $0.25 | $0.01 |
| 51 | SHRT TRM pavt MK rem (70300150) | SF | 16,789 | $0.01 | $0.01 | $0.01 | $0.01 |
| 52 | THPL PVT MK LTR & sym (78000100) | SF | 630 | $5.25 | $5.00 | $5.00 | $5.80 |
| 53 | THPL PVT MK line 4 (78000200) | LF | 45,289 | $0.84 | $0.80 | $0.80 | $0.80 |
| 54 | THPL PVT MK line 6 (78000400) | LF | 1,925 | $1.05 | $1.00 | $1.00 | $1.15 |
| 55 | THPL PVT MK line 12 (78000600) | LF | 1,798 | $1.31 | $1.25 | $1.25 | $2.90 |
| 56 | THPL PVT MK line 24 (78000650) | LF | 279 | $5.25 | $5.00 | $5.00 | $5.80 |
| 57 | GRV RCSD PM LTR & sym (78011000) | SF | 630 | $2.10 | $2.00 | $2.00 | $5.00 |
| 58 | GRV RCSD PVT MRKG 5 (78011025) | LF | 45,289 | $0.36 | $0.35 | $0.35 | $0.40 |
| 59 | GRV RCSD PVT MRKG 7 (78011035) | LF | 1,925 | $0.63 | $0.60 | $0.60 | $0.60 |
| 60 | GRV RCSD PVT MRKG 13 (78011065) | LF | 1,798 | $1.05 | $1.00 | $1.00 | $2.50 |
| 61 | GRV RCSD PVT MRKG 25 (78011125) | LF | 279 | $2.10 | $2.00 | $2.00 | $5.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.