Payne & Dolan, Inc.: IDOT bid record

Payne & Dolan, Inc. submitted 40 bids on Illinois DOT contracts in the data, from 05 MAR 2021 to 24 APR 2026, and was the low bidder on 7 of them (18%). When it was not low, its total sat a median +12% above the low bid.

Owner
Illinois DOT
Low bid volume
$17,057,433
Latest bid
24 APR 2026
Data through
18 SEP 2026
40Bids
7Low bids
18Win rate, percent
+12%Median gap to the low bid when not low, 33 bids

By year

YearBidsLow bidsWin rate
20215120%
2022700%
20233133%
20248225%
202511327%
2026600%
Payne & Dolan, Inc., IDOT: bids and low bids by year of letting

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Bit matls tack CT40600290LB3827 (71%)$0.01$0.01
Long joint sealant40600370LF2926 (90%)$2.69$3.30
THPL PVT MK line 478000200LF3623 (64%)$0.73$0.88
Raised refl pavt MKR78100100EACH2723 (85%)$34.50$48.00
THPL PVT MK line 2478000650LF3520 (57%)$5.75$6.00
THPL PVT MK line 1278000600LF3120 (65%)$2.50$3.10
THPL PVT MK LTR & sym78000100SF3018 (60%)$5.62$5.75
THPL PVT MK line 678000400LF3216 (50%)$1.14$1.40
HMA SC IL-9.5 D N7040604062TON2516 (64%)$80.00$108.16
Trainees TPGZ0076604HR1616 (100%)$15.00$15.00
TraineesZ0076600HR1515 (100%)$0.80$0.80
Grading & shap SHLDRSX2020110UNIT2114 (67%)$36.00$93.00
Payne & Dolan, Inc., IDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

Payne & Dolan, Inc., IDOT: the firms on the same contracts most often

Latest bids

LetContractDistrictProjectRankIts bidAgainst the low bid
24 APR 202680B10District 01Section 2025-1098-RS2 of 3$1,229,750+4.0%
27 FEB 202661M19District 01Bull Valley, section 22-00009-00-RS2 of 6$567,402+4.0%
27 FEB 202680B75District 01Section 2025-2039-RS,SW2 of 2$3,721,570+13%
16 JAN 202661L94District 01Woodstock, section 24-00116-00-RS4 of 7$961,899+4.0%
16 JAN 202661M07District 01Spring Grove, section 23-00021-00-RS3 of 4$1,197,995+32%
16 JAN 202680B29District 01Section 2025-2010-RS2 of 4$1,049,780+4.0%
13 JUN 202561L50District 01Johnsburg, section 23-00017-00-RS4 of 4$2,089,955+19%
13 JUN 202562V39District 01Section FAP1 of 2$1,630,685Low, 24% under the second
13 JUN 202562V58District 01Section FAP2 of 2$4,562,141+29%
25 APR 202561L32District 01Zion, section 22-00094-00-RS2 of 2$994,994+11%
25 APR 202562V38District 01Section FAP2 of 2$809,000+18%
25 APR 202562V75District 01Section FAP2 of 3$2,277,984+17%
07 MAR 202562R96District 01Section FAP2 of 3$1,279,700+1.0%
07 MAR 202562T83District 01Section FAP2 of 3$653,559+5.0%
07 MAR 202562U91District 01Section FAP1 of 3$2,424,972Low, 1.0% under the second
07 MAR 202562X36District 01Section 2024-1002-N1 of 1$348,412Low
17 JAN 202561L00District 01Wonder Lake, section 24-00013-00-RS3 of 5$679,976+10%
26 APR 202462L16District 01Section 2020-044-RS2 of 3$5,169,576+1.0%
26 APR 202462M25District 01Section 2020-187-SW1 of 2$7,564,874Low, 39% under the second
08 MAR 202461K14District 01Harvard, section 21-00068-00-RS5 of 5$747,000+43%
08 MAR 202462T59District 01Section FAP3 of 3$9,746,978+47%
08 MAR 202462T60District 01Section FAP2 of 3$3,619,926+4.0%
08 MAR 202462T62District 01Section FAP2 of 3$1,474,210+21%
08 MAR 202462T63District 01Section FAP4 of 4$1,235,000+7.0%
19 JAN 202461J98District 01Spring Grove, section 21-00018-00-RS1 of 4$1,194,568Low, 5.0% under the second
Payne & Dolan, Inc.: latest IDOT bids in the data

How this record was read

IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

  • Every bid counted here matched its published total to within one dollar; IDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way