IDOT contract 61L94 bid tabulation
Woodstock, section 24-00116-00-RS. Let by Illinois DOT on January 16, 2026, Mchenry, District 01. 7 bids received; low bid $928,920 by Geske and Sons, Inc..
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 60
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Geske and Sons, Inc. | $928,920 | Low |
| 2 | Builders Paving, LLC | $944,198 | +2.0% |
| 3 | Peter Baker & Son Co. | $953,167 | +3.0% |
| 4 | Payne & Dolan, Inc. | $961,899 | +4.0% |
| 5 | Schroeder Asphalt Services, Inc. | $1,104,117 | +19% |
| 6 | Curran Contracting Company | $1,111,123 | +20% |
| 7 | Plote Construction, Inc. | $1,139,000 | +23% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Geske and Sons, Inc. | 2. Builders Paving, LLC | 3. Peter Baker & Son Co. | 4. Payne & Dolan, Inc. | 5. Schroeder Asphalt Services, Inc. | 6. Curran Contracting Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Prun safety/equip CLR (K1004595) | LS | 1 | $1,080.00 | $5,000.00 | $9,652.00 | $18,000 | $18,000 | $14,400 |
| 2 | Constructn layout SPL (X0320050) | LS | 1 | $500.00 | $10,000 | $4,500.00 | $5,000.00 | $7,500.00 | $8,500.00 |
| 3 | Structure adj (X0326862) | EACH | 8 | $945.00 | $650.00 | $650.00 | $650.00 | $750.00 | $800.00 |
| 4 | Bike path rem (X0327036) | SY | 45 | $28.35 | $27.00 | $27.00 | $27.00 | $15.00 | $27.00 |
| 5 | PC conc sidewalk 5 SP (X4240430) | SF | 1,803 | $11.43 | $12.00 | $11.10 | $11.10 | $12.30 | $11.10 |
| 6 | Temp info signing (X7200061) | SF | 52 | $13.75 | $12.50 | $12.50 | $18.00 | $22.00 | $12.50 |
| 7 | RCSD refl pavt marker (X7810300) | EACH | 23 | $234.00 | $100.00 | $100.00 | $100.00 | $250.00 | $100.00 |
| 8 | Drain util STR recon (Z0017700) | EACH | 5 | $1,260.00 | $1,200.00 | $1,200.00 | $1,200.00 | $1,350.00 | $1,450.00 |
| 9 | Rem & disp uns matl (20201200) | CY | 793 | $24.00 | $0.10 | $45.00 | $46.50 | $55.00 | $50.00 |
| 10 | Geotech fab F/GR stab (21001000) | SY | 1,770 | $2.20 | $1.00 | $1.05 | $2.70 | $3.00 | $3.00 |
| 11 | Topsoil F & P 4 (21101615) | SY | 708 | $0.11 | $0.10 | $0.10 | $0.10 | $15.75 | $0.10 |
| 12 | Seeding CL 1A (25000110) | ACRE | 0.15 | $21,296 | $19,360 | $19,360 | $19,360 | $8,500.00 | $19,360 |
| 13 | Nitrogen fert nutr (25000400) | LB | 14 | $1.10 | $1.00 | $1.00 | $1.00 | $5.00 | $1.00 |
| 14 | Phosphorus fert nutr (25000500) | LB | 14 | $1.10 | $1.00 | $1.00 | $1.00 | $5.00 | $1.00 |
| 15 | Potassium fert nutr (25000600) | LB | 14 | $1.10 | $1.00 | $1.00 | $1.00 | $5.00 | $1.00 |
| 16 | Erosion contr blanket (25100630) | SY | 708 | $3.85 | $3.50 | $3.50 | $3.50 | $3.00 | $3.50 |
| 17 | Inlet filters (28000510) | EACH | 15 | $147.00 | $140.00 | $140.00 | $140.00 | $165.00 | $170.00 |
| 18 | Agg subgrade improve (30300001) | CY | 793 | $32.46 | $20.00 | $45.00 | $61.50 | $62.00 | $65.00 |
| 19 | Preparation of base (35800100) | SY | 6,117 | $1.85 | $1.50 | $1.95 | $2.00 | $1.25 | $3.50 |
| 20 | Agg base repair (35800200) | TON | 711 | $5.00 | $15.00 | $26.00 | $29.00 | $32.00 | $20.00 |
| 21 | Aggregate-temp access (40201000) | TON | 70 | $15.00 | $30.00 | $26.00 | $74.00 | $30.00 | $25.00 |
| 22 | Bit matls PR CT (40600275) | LB | 27,526 | $0.01 | $0.01 | $0.01 | $0.10 | $0.01 | $0.01 |
| 23 | Bit matls tack CT (40600290) | LB | 8,582 | $0.01 | $0.01 | $0.01 | $0.10 | $0.01 | $0.50 |
| 24 | Mix CR JTS flangewys (40600400) | TON | 5 | $150.00 | $300.00 | $110.00 | $775.00 | $350.00 | $500.00 |
| 25 | HMA surf rem butt JT (40600982) | SY | 180 | $30.14 | $10.00 | $1.00 | $26.00 | $10.00 | $25.00 |
| 26 | HMA BC IL-19.0 N50 (40603080) | TON | 3,429 | $73.45 | $73.00 | $79.15 | $78.00 | $87.00 | $78.50 |
| 27 | HMA SC IL-9.5 D N50 (40604060) | TON | 2,202 | $88.70 | $85.00 | $84.05 | $91.20 | $86.50 | $86.50 |
| 28 | Detectable warnings (42400800) | SF | 167 | $38.11 | $37.00 | $37.00 | $37.00 | $42.00 | $37.00 |
| 29 | Pavement rem (44000100) | SY | 12,234 | $5.24 | $6.00 | $5.40 | $4.25 | $5.00 | $6.00 |
| 30 | HMA surf rem 3 3/4 (44000164) | SY | 8,637 | $4.38 | $6.00 | $4.71 | $3.75 | $4.15 | $5.25 |
| 31 | Comb curb gutter rem (44000500) | LF | 1,000 | $15.09 | $14.50 | $14.65 | $14.65 | $16.50 | $14.65 |
| 32 | Sidewalk rem (44000600) | SF | 1,234 | $4.12 | $4.00 | $4.00 | $4.00 | $4.50 | $4.00 |
| 33 | CL D patch T2 5 (44201705) | SY | 387 | $25.84 | $20.00 | $34.00 | $35.00 | $53.00 | $70.00 |
| 34 | CL D patch T3 5 (44201709) | SY | 387 | $25.84 | $20.00 | $34.00 | $35.00 | $53.00 | $60.00 |
| 35 | CL D patch T4 5 (44201711) | SY | 387 | $25.84 | $20.00 | $34.00 | $35.00 | $51.00 | $50.00 |
| 36 | FR & grates T12 (60404900) | EACH | 12 | $1,249.50 | $1,190.00 | $1,190.00 | $1,190.00 | $1,375.00 | $1,445.00 |
| 37 | FR & lids T1 OL (60406000) | EACH | 1 | $441.00 | $420.00 | $420.00 | $420.00 | $500.00 | $510.00 |
| 38 | Comb CC&G TB6.12 (60603800) | LF | 1,000 | $41.20 | $42.00 | $40.00 | $40.00 | $45.00 | $40.00 |
| 39 | Mobilization (67100100) | LS | 1 | $61,335 | $88,000 | $35,039 | $9,000.00 | $28,000 | $70,000 |
| 40 | TR cont & prot 701501 (70102620) | LS | 1 | $3,352.80 | $5,000.00 | $3,048.00 | $5,000.00 | $3,250.00 | $20,000 |
| 41 | TR cont & prot 701502 (70102622) | LS | 1 | $3,483.70 | $5,000.00 | $3,167.00 | $1.00 | $3,250.00 | $3,500.00 |
| 42 | TR cont & prot 701701 (70102635) | LS | 1 | $1.10 | $1.00 | $915.00 | $1.00 | $3,250.00 | $1.00 |
| 43 | TR cont & prot 701801 (70102640) | LS | 1 | $1,006.50 | $1,000.00 | $1.00 | $1,900.00 | $3,250.00 | $3,500.00 |
| 44 | Short term pavt mking (70300100) | LF | 9,700 | $0.20 | $1.00 | $0.01 | $0.01 | $2.00 | $0.10 |
| 45 | SHRT TRM pavt MK rem (70300150) | SF | 3,233 | $0.50 | $0.01 | $0.01 | $0.30 | $3.00 | $1.00 |
| 46 | THPL PVT MK LTR & sym (78000100) | SF | 213 | $5.98 | $3.90 | $3.90 | $3.90 | $6.50 | $3.90 |
| 47 | THPL PVT MK line 4 (78000200) | LF | 19,123 | $0.68 | $0.65 | $0.65 | $0.65 | $0.77 | $0.65 |
| 48 | THPL PVT MK line 6 (78000400) | LF | 1,355 | $0.83 | $1.00 | $1.00 | $1.00 | $0.89 | $1.00 |
| 49 | THPL PVT MK line 12 (78000600) | LF | 1,763 | $3.45 | $1.95 | $1.95 | $1.95 | $3.75 | $1.95 |
| 50 | THPL PVT MK line 24 (78000650) | LF | 120 | $5.98 | $3.90 | $3.90 | $3.90 | $6.40 | $3.90 |
| 51 | GRV RCSD PM LTR & sym (78011000) | SF | 213 | $2.86 | $6.00 | $6.00 | $6.00 | $6.50 | $6.00 |
| 52 | GRV RCSD PVT MRKG 5 (78011025) | LF | 19,290 | $0.52 | $0.30 | $0.30 | $0.30 | $0.57 | $0.30 |
| 53 | GRV RCSD PVT MRKG 7 (78011035) | LF | 1,355 | $0.62 | $2.00 | $2.00 | $2.00 | $0.67 | $2.00 |
| 54 | GRV RCSD PVT MRKG 13 (78011065) | LF | 1,763 | $2.03 | $3.00 | $3.00 | $3.00 | $2.25 | $3.00 |
| 55 | GRV RCSD PVT MRKG 25 (78011125) | LF | 120 | $3.17 | $6.00 | $6.00 | $6.00 | $3.40 | $6.00 |
| 56 | HD handhole (81400200) | EACH | 1 | $7,374.86 | $5,200.00 | $5,172.00 | $5,172.00 | $5,800.00 | $5,172.00 |
| 57 | Main EX TR sig instal (85000200) | EACH | 1 | $2,208.13 | $3,000.00 | $3,000.00 | $3,000.00 | $3,400.00 | $3,000.00 |
| 58 | Drill EX HD handhole (87900205) | EACH | 1 | $568.03 | $650.00 | $650.00 | $650.00 | $800.00 | $650.00 |
| 59 | Det loop T1 (88600100) | LF | 588 | $36.84 | $33.00 | $32.56 | $33.00 | $38.00 | $32.56 |
| 60 | Remov EX handhole (89502380) | EACH | 1 | $1,648.00 | $1,750.00 | $1,750.00 | $1,750.00 | $1,950.00 | $1,750.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.