IDOT contract 62R96 bid tabulation
Section FAP. Let by Illinois DOT on March 7, 2025, Mchenry, District 01. 3 bids received; low bid $1,270,720 by Peter Baker & Son Co..
- Owner
- Illinois DOT
- Letting
- 07 MAR 2025
- Pay items
- 34
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Peter Baker & Son Co. | $1,270,720 | Low |
| 2 | Payne & Dolan, Inc. | $1,279,700 | +1.0% |
| 3 | Curran Contracting Company | $1,410,863 | +11% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Peter Baker & Son Co. | 2. Payne & Dolan, Inc. | 3. Curran Contracting Company |
|---|---|---|---|---|---|---|
| 1 | Grading & shap SHLDRS (X2020110) | UNIT | 323 | $50.00 | $12.00 | $82.00 |
| 2 | Centerln rum strip 16 (X6420114) | LF | 16,707 | $0.75 | $0.35 | $1.50 |
| 3 | Engrs FLD ofc TY A D1 (X6700407) | CAL MO | 6 | $1,000.00 | $1,700.00 | $2,400.00 |
| 4 | HS THPL PM LN 4 (X7800815) | LF | 21,119 | $0.45 | $0.40 | $0.45 |
| 5 | Temp info signing (Z0030850) | SF | 70.20 | $18.00 | $18.00 | $12.00 |
| 6 | Bit matls tack CT (40600290) | LB | 29,228 | $0.01 | $0.10 | $0.50 |
| 7 | Long joint sealant (40600370) | LF | 17,219 | $3.40 | $2.70 | $2.95 |
| 8 | Mix CR JTS flangewys (40600400) | TON | 98 | $150.00 | $300.00 | $140.00 |
| 9 | HMA surf rem butt JT (40600982) | SY | 147 | $1.00 | $4.50 | $15.00 |
| 10 | HMA SC IL-9.5 D N70 (40604062) | TON | 5,456 | $85.00 | $85.50 | $99.00 |
| 11 | HMA surf rem 1 1/2 (44000155) | SY | 64,951 | $2.45 | $2.50 | $3.20 |
| 12 | CL D patch T2 14 (44201815) | SY | 1,250 | $55.00 | $50.00 | $90.00 |
| 13 | CL D patch T3 14 (44201819) | SY | 1,250 | $55.00 | $50.00 | $75.00 |
| 14 | Agg wedge SHLD type B (48102100) | TON | 270 | $55.00 | $57.00 | $52.00 |
| 15 | Pipe culv cleaned 12 (60920012) | LF | 346 | $10.00 | $10.00 | $10.00 |
| 16 | Shoulder rum strip 16 (64200116) | LF | 32,545 | $0.40 | $0.35 | $1.50 |
| 17 | Mobilization (67100100) | LS | 1 | $288,710 | $278,000 | $100,000 |
| 18 | Traf cont-prot 701201 (70100450) | LS | 1 | $9,735.00 | $7,600.00 | $1.00 |
| 19 | Traf cont-prot 701306 (70100460) | LS | 1 | $1.00 | $1.00 | $1.00 |
| 20 | Traf cont-prot 701336 (70100600) | LS | 1 | $1.00 | $1.00 | $75,000 |
| 21 | TR cont & prot 701701 (70102635) | LS | 1 | $1.00 | $1.00 | $1.00 |
| 22 | Short term pavt mking (70300100) | LF | 27,810 | $0.01 | $1.00 | $0.15 |
| 23 | SHRT TRM pavt MK rem (70300150) | SF | 3,090 | $0.01 | $1.10 | $0.50 |
| 24 | Temp PVT MK LTR & sym paint (70300211) | SF | 252 | $0.01 | $0.01 | $0.01 |
| 25 | Temp PVT MK line 4 - paint (70300221) | LF | 163,656 | $0.01 | $0.01 | $0.01 |
| 26 | Temp PVT MK line 6 - paint (70300241) | LF | 966 | $0.01 | $0.01 | $0.01 |
| 27 | Temp PVT MK line 24 - paint (70300281) | LF | 372 | $0.01 | $0.01 | $0.01 |
| 28 | THPL PVT MK LTR & sym (78000100) | SF | 84 | $6.00 | $6.50 | $6.00 |
| 29 | THPL PVT MK line 4 (78000200) | LF | 33,433 | $0.75 | $0.90 | $0.75 |
| 30 | THPL PVT MK line 6 (78000400) | LF | 322 | $1.15 | $3.00 | $1.15 |
| 31 | THPL PVT MK line 24 (78000650) | LF | 124 | $6.00 | $6.50 | $6.00 |
| 32 | Raised refl pavt MKR (78100100) | EACH | 424 | $38.50 | $43.00 | $38.50 |
| 33 | Raised ref PVT MK rem (78300200) | EACH | 374 | $19.00 | $21.50 | $17.00 |
| 34 | PVT MKG rem WTR blast (78300202) | SF | 18,677 | $0.50 | $0.50 | $0.05 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of March 7, 2025. Compiled by Mirage Metrics.