Prairie Grove, section 24-00012-00-RS. Let by Illinois DOT on June 13, 2025, Mchenry, District 01. 4 bids received; low bid $588,609 by Geske and Sons, Inc..
- Owner
- Illinois DOT
- Letting
- 13 JUN 2025
- Pay items
- 36
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Geske and Sons, Inc. | $588,609 | Low |
| 2 | Peter Baker & Son Co. | $661,180 | +12% |
| 3 | Curran Contracting Company | $739,647 | +26% |
| 4 | Builders Paving, LLC | $832,376 | +41% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Geske and Sons, Inc. | 2. Peter Baker & Son Co. | 3. Curran Contracting Company | 4. Builders Paving, LLC |
|---|---|---|---|---|---|---|---|
| 1 | HMA driveway pavt 3 (X4060280) | SY | 346 | $13.90 | $54.50 | $55.00 | $40.00 |
| 2 | Temp info signing (X7200061) | SF | 52 | $16.80 | $20.00 | $20.00 | $16.00 |
| 3 | Rem & disp uns matl (20201200) | CY | 202 | $10.00 | $17.00 | $30.00 | $30.00 |
| 4 | Geotech fab F/GR stab (21001000) | SY | 605 | $2.00 | $1.20 | $2.00 | $2.00 |
| 5 | Topsoil F & P 4 (21101615) | SY | 340 | $5.50 | $5.00 | $5.00 | $11.00 |
| 6 | Seeding CL 2A (25000210) | ACRE | 0.25 | $8,250.00 | $7,500.00 | $7,500.00 | $4,000.00 |
| 7 | Nitrogen fert nutr (25000400) | LB | 24 | $2.20 | $2.00 | $2.00 | $3.00 |
| 8 | Phosphorus fert nutr (25000500) | LB | 24 | $2.20 | $2.00 | $2.00 | $3.00 |
| 9 | Potassium fert nutr (25000600) | LB | 24 | $2.20 | $2.00 | $2.00 | $3.00 |
| 10 | Erosion contr blanket (25100630) | SY | 340 | $5.50 | $5.00 | $5.00 | $3.00 |
| 11 | Supple watering (25200200) | UNIT | 7 | $1.10 | $1.00 | $1.00 | $25.00 |
| 12 | Agg subgrade improve (30300001) | CY | 202 | $15.00 | $35.00 | $30.00 | $30.00 |
| 13 | Bit matls tack CT (40600290) | LB | 16,790 | $0.01 | $0.01 | $0.10 | $0.01 |
| 14 | Long joint sealant (40600370) | LF | 8,580 | $2.79 | $3.45 | $3.00 | $3.50 |
| 15 | Mix CR JTS flangewys (40600400) | TON | 34 | $50.00 | $100.00 | $200.00 | $300.00 |
| 16 | HMA surf rem butt JT (40600982) | SY | 437 | $10.99 | $1.00 | $10.00 | $25.00 |
| 17 | P HMA BC IL-4.75 N50 (40603200) | TON | 1,045 | $101.93 | $102.00 | $100.00 | $110.00 |
| 18 | HMA SC IL-9.5 D N50 (40604060) | TON | 2,089 | $78.10 | $80.00 | $75.00 | $92.00 |
| 19 | PCC driveway pavt 6 (42300200) | SY | 70 | $154.25 | $145.50 | $123.05 | $145.00 |
| 20 | HMA surf rem 2 1/4 (44000158) | SY | 24,860 | $2.34 | $3.10 | $3.15 | $4.00 |
| 21 | Drive pavement rem (44000200) | SY | 416 | $15.51 | $25.45 | $19.77 | $26.00 |
| 22 | CL D patch T2 6 (44201717) | SY | 473 | $37.50 | $30.00 | $90.00 | $30.00 |
| 23 | CL D patch T3 6 (44201721) | SY | 672 | $37.50 | $30.00 | $70.00 | $30.00 |
| 24 | CL D patch T4 6 (44201723) | SY | 1,269 | $37.50 | $30.00 | $50.00 | $30.00 |
| 25 | Agg wedge SHLD type B (48102100) | TON | 235 | $68.94 | $80.00 | $45.00 | $50.00 |
| 26 | Non SPL waste disposl (66900200) | CY | 38 | $75.00 | $101.00 | $200.00 | $135.00 |
| 27 | Soil disposal analy (66900530) | EACH | 2 | $840.00 | $1,680.00 | $1,400.00 | $1,680.00 |
| 28 | Reg sub P-const plan (66901001) | LS | 1 | $1,700.00 | $3,400.00 | $3,900.00 | $3,400.00 |
| 29 | Reg sub F con report (66901003) | LS | 1 | $250.00 | $500.00 | $500.00 | $500.00 |
| 30 | Reg sub mon (66901006) | CAL DAY | 20 | $350.00 | $100.00 | $700.00 | $700.00 |
| 31 | Mobilization (67100100) | LS | 1 | $39,865 | $41,891 | $50,000 | $150,000 |
| 32 | TR cont & prot 701501 (70102620) | LS | 1 | $7,350.00 | $47,133 | $25,000 | $14,003 |
| 33 | Short term pavt mking (70300100) | LF | 18,880 | $0.01 | $0.01 | $0.25 | $1.00 |
| 34 | SHRT TRM pavt MK rem (70300150) | SF | 6,300 | $0.01 | $0.01 | $1.25 | $0.01 |
| 35 | THPL PVT MK line 4 (78000200) | LF | 36,800 | $0.74 | $0.70 | $0.70 | $0.70 |
| 36 | THPL PVT MK line 24 (78000650) | LF | 15 | $6.30 | $8.00 | $8.00 | $6.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of June 13, 2025. Compiled by Mirage Metrics.