IDOT contract 80C45 bid tabulation

Section 2025-2102-RS. Let by Illinois DOT on June 12, 2026, Mchenry, District 01. 4 bids received; low bid $1,605,106 by Peter Baker & Son Co..

Owner
Illinois DOT
Letting
12 JUN 2026
Pay items
84
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Peter Baker & Son Co.$1,605,106Low
2Curran Contracting Company$1,622,323+1.0%
3Builders Paving, LLC$1,701,980+6.0%
4Plote Construction, Inc.$1,741,374+8.0%
IDOT contract 80C45: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Peter Baker & Son Co.2. Curran Contracting Company3. Builders Paving, LLC4. Plote Construction, Inc.
1Grading & shap SHLDRS (X2020110)UNIT157$50.00$70.00$100.00$125.00
2CC&G RMVL repl < = 10 (X4400501)LF15$222.00$222.00$100.00$200.00
3CC&G RMVL repl > 10FT (X4400503)LF70$222.00$222.00$100.00$200.00
4SS cleaned 12 (X5537800)LF270$1.00$15.00$1.00$1.00
5Centerln rum strip 16 (X6420114)LF5,424$2.91$2.00$1.50$1.70
6Engrs FLD ofc TY A D1 (X6700407)CAL MO12$2,000.00$2,750.00$4,000.00$4,500.00
7Temp info signing (X7200061)SF104$17.00$15.00$17.00$17.00
8HS THPL PM LN 4 (X7800815)LF10,848$0.55$0.55$0.55$0.55
9Accessible ped signal (X8760200)EACH3$2,150.00$3,403.23$3,500.00$3,403.23
10Drainage STR cleaned (Z0018500)EACH18$315.00$500.00$320.00$315.00
11RE-optimize TR sig sys 1 (Z0033044)EACH1$1,150.00$864.00$865.00$864.00
12Topsoil F & P 4 (21101615)SY8$100.00$100.00$50.00$40.00
13Grading & shap ditch (21400100)LF1,200$19.30$18.00$28.00$9.00
14Sodding salt tolerant (25200110)SY8$150.00$150.00$50.00$40.00
15Supple watering (25200200)UNIT1$0.10$0.10$200.00$250.00
16Bit matls tack CT (40600290)LB29,755$0.01$0.50$0.01$0.01
17Long joint sealant (40600370)LF10,892$3.30$2.90$3.00$3.25
18Mix CR JTS flangewys (40600400)TON69$120.00$200.00$300.00$95.00
19HMA surf rem butt JT (40600982)SY191$1.00$24.00$30.00$45.00
20P HMA BC IL-4.75 N50 (40603200)TON2,264$127.00$125.00$115.00$100.00
21HMA SC IL-9.5 D N50 (40604060)TON369$102.00$92.00$95.00$120.00
22HMA SC IL-9.5 D N70 (40604062)TON3,458$97.00$102.00$95.00$100.00
23Protective coat (42001300)SY35$0.01$0.01$0.10$1.00
24HMA surf rem 1/2 (44000151)SY4,388$2.00$1.70$3.00$2.30
25HMA surf rem 1 1/2 (44000155)SY3,496$3.20$2.35$8.00$3.85
26HMA surf rem 2 1/2 (44000159)SY37,659$3.95$3.50$5.00$2.90
27CL D patch T2 10 (44201765)SY27$70.00$200.00$110.00$139.00
28CL D patch T3 10 (44201769)SY40$70.00$160.00$110.00$139.00
29CL D patch T4 10 (44201771)SY66$70.00$120.00$110.00$139.00
30CL D patch T2 19 (44201875)SY247$85.00$275.00$110.00$170.00
31CL D patch T3 19 (44201879)SY371$85.00$215.00$110.00$170.00
32CL D patch T4 19 (44201881)SY618$85.00$150.00$110.00$170.00
33Agg wedge SHLD type B (48102100)TON313$78.05$60.00$75.00$75.00
34CB adjust (60250200)EACH5$1,180.00$750.00$1,250.00$1,250.00
35Conc median surf 6 (60618320)SF70$30.00$30.00$15.00$60.00
36Box cul to BE cleaned (60905305)LF72$50.00$127.00$50.00$50.00
37Pipe culv cleaned 12 (60920012)LF718$4.00$12.00$4.00$4.00
38Pipe culv cleaned 15 (60920015)LF374$5.00$17.30$5.00$5.00
39Pipe culv cleaned 24 (60920024)LF300$7.00$26.90$7.00$7.00
40SPBGR TY A 6FT posts (63000001)LF24$45.00$45.00$45.00$45.00
41Traf bar term T2 (63100045)EACH2$3,200.00$3,200.00$3,200.00$3,200.00
42Guardrail remov (63200310)LF24$10.00$10.00$10.00$10.00
43Shoulder rum strip 8 (64200108)LF13,135$1.08$1.00$1.50$1.10
44Non SPL waste disposl (66900200)CY60$131.00$100.00$150.00$160.00
45Soil disposal analy (66900530)EACH1$1,560.00$900.00$1,560.00$1,560.00
46Reg sub P-const plan (66901001)LS1$3,400.00$5,500.00$3,400.00$3,400.00
47Reg sub F con report (66901003)LS1$500.00$500.00$500.00$500.00
48Reg sub mon (66901006)CAL DAY5$715.00$750.00$715.00$935.00
49Mobilization (67100100)LS1$100,122$81,500$234,999$104,000
50Traf cont-prot 701421 (70100310)LS1$104,181$5,000.00$5,000.00$80,000
51TR cont & prot 701501 (70102620)LS1$5,000.00$10,000$5,000.00$77,000
52TR cont & prot 701601 (70102630)LS1$7,000.00$5,000.00$5,000.00$77,000
53TR cont & prot 701701 (70102635)LS1$1,000.00$1,000.00$1,000.00$1,000.00
54TR cont & prot 701801 (70102640)LS1$1,000.00$1,000.00$1,000.00$1,000.00
55Short term pavt mking (70300100)LF8,223$0.01$0.25$1.75$0.70
56SHRT TRM pavt MK rem (70300150)SF371$5.25$7.50$0.01$5.50
57Temp PVT MK LTR & sym paint (70300211)SF874$0.01$0.50$0.01$0.01
58Temp PVT MK line 4 - paint (70300221)LF44,546$0.01$0.10$0.01$0.01
59Temp PVT MK line 6 - paint (70300241)LF6,676$0.01$0.10$0.01$0.01
60Temp PVT MK line 8 - paint (70300251)LF3,946$0.01$0.10$0.01$0.01
61Temp PVT MK line 12 - paint (70300261)LF3,088$0.01$0.10$0.01$0.01
62Temp PVT MK line 24 - paint (70300281)LF742$0.01$0.10$0.01$0.01
63Temp PVT MK L4 T4 tape (70307120)LF1,122$1.11$0.10$1.00$1.60
64Sign panel T1 (72000100)SF18$60.00$100.00$75.00$50.00
65Teles STL sin support (72800100)LF45$25.00$50.00$30.00$30.00
66THPL PVT MK LTR & sym (78000100)SF437$6.00$6.00$6.00$6.00
67THPL PVT MK line 4 (78000200)LF22,273$0.90$0.90$0.90$0.90
68THPL PVT MK line 6 (78000400)LF3,338$0.95$0.95$0.95$0.95
69THPL PVT MK line 8 (78000500)LF1,973$2.00$2.00$2.00$2.00
70THPL PVT MK line 12 (78000600)LF1,544$3.00$3.00$3.00$3.00
71THPL PVT MK line 24 (78000650)LF371$6.00$6.00$6.00$6.00
72Pref PL PM TD STD L 6 (78004630)LF2,157$8.90$8.90$8.90$8.90
73Mod ureth PM line 4 (78009004)LF11,000$0.75$0.75$0.75$0.75
74Mod ureth PM line 24 (78009024)LF26$15.00$15.00$15.00$15.00
75GRV RCSD PVT MRKG 7 (78011035)LF2,157$2.20$2.20$2.20$2.20
76Raised refl pavt MKR (78100100)EACH227$33.54$33.54$35.00$33.54
77Grdrail ref type A (78200005)EACH4$25.00$25.00$25.00$25.00
78Raised ref PVT MK rem (78300200)EACH227$34.00$13.50$20.00$12.00
79Main EX TR sig instal (85000200)EACH2$9,500.00$2,377.08$2,500.00$2,377.08
80TS backplate (88200100)EACH1$1,750.00$377.32$400.00$377.32
81TS backplate louvered (88200110)EACH1$1,750.00$379.06$400.00$379.06
82Inductive loop detect (88500100)EACH1$1,485.00$456.10$455.00$456.10
83Det loop T1 (88600100)LF2,203$40.00$23.55$24.00$23.55
84Remov EX TS equip (89502375)EACH2$480.00$68.55$70.00$68.55
IDOT contract 80C45: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of June 12, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy