IDOT contract 80D46 bid tabulation

Section 2026-2181-C,HBK. Let by Illinois DOT on June 12, 2026, Lake, District 01. 7 bids received; low bid $1,087,000 by Curran Contracting Company.

Owner
Illinois DOT
Letting
12 JUN 2026
Pay items
86
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Curran Contracting Company$1,087,000Low
2Campanella and Sons, Inc.$1,146,156+5.0%
3Acura Inc.$1,260,823+16%
4Lorig Construction Company$1,306,934+20%
5PirTano Construction Co., LLC$1,358,423+25%
6Martam Construction Incorporated$1,361,632+25%
7Alliance Contractors, Inc.$2,295,397+111%
IDOT contract 80D46: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Curran Contracting Company2. Campanella and Sons, Inc.3. Acura Inc.4. Lorig Construction Company5. PirTano Construction Co., LLC6. Martam Construction Incorporated
1T-amel X GF AB SF 6' (B2000766)EACH3$941.00$700.00$740.00$900.00$500.00$550.00
2S-aronia arb bril 3' (C2000436)EACH95$83.00$95.00$100.00$75.00$85.00$95.00
3S-rhus typhina 2'BR (C3006024)EACH25$83.00$105.00$115.00$75.00$50.00$55.00
4Mulch placement 3 (K0036118)SY482$11.90$9.00$10.00$11.00$10.00$11.00
5Elast CHK val 12 (X5420112)EACH1$4,173.00$3,425.00$5,000.00$6,000.00$5,515.00$5,500.00
6Clean paved ditch (X6061462)LF147$23.35$46.50$50.00$26.00$38.00$55.00
7Shoulder rum strip RM (X6420100)SY826$17.20$40.00$45.00$19.00$40.00$44.00
8Engrs FLD ofc TY A D1 (X6700407)CAL MO4$7,775.00$3,000.00$4,000.00$4,500.00$4,000.00$3,800.00
9Traf cont & prot SPL (X7010216)LS1$67,667$92,000$75,000$300,000$90,000$135,000
10Speed display trailer (X7010410)CAL MO8$443.00$400.00$550.00$400.00$400.00$550.00
11Temp info signing (X7200061)SF200$17.70$16.00$28.00$16.00$16.00$20.00
12Temporary signing (X7200062)EACH2$443.00$400.00$400.00$400.00$400.00$1,400.00
13RRPM reflector removl (X7830050)EACH110$13.30$12.00$11.00$12.00$12.00$15.00
14RRPM reflector replac (X7830052)EACH110$16.60$15.00$16.00$15.00$15.00$48.00
15Construction layout (Z0013798)LS1$7,645.00$30,000$35,000$49,000$6,900.00$7,965.00
16Rock fill - foundatn (Z0054517)TON57$86.45$140.00$200.00$190.00$100.00$65.00
17Temporary fence (20101000)LF673$3.45$7.00$6.00$3.50$6.75$8.00
18Tree prun 1-10 (20101300)EACH5$332.00$160.00$175.00$325.00$300.00$120.00
19Tree prun over 10 (20101350)EACH5$443.00$240.00$255.00$425.00$400.00$150.00
20Earth excavation (20200100)CY760$84.05$0.01$50.00$90.00$81.00$72.00
21Rem & disp uns matl (20201200)CY106$91.35$200.00$45.00$90.00$140.00$72.00
22Porous gran embank (20700220)CY107$51.25$200.00$45.00$200.00$229.00$83.00
23Geotech fab F/GR stab (21001000)SY83$14.75$4.00$5.00$4.00$12.00$5.00
24Topsoil exc & plac (21101505)CY319$22.80$0.01$9.00$60.00$72.00$28.00
25Topsoil F & P 4 (21101615)SY1,204$9.25$20.00$11.00$9.00$6.50$7.00
26Grading & shap ditch (21400100)LF505$16.60$5.00$17.00$12.00$20.00$26.00
27Seeding CL 2A (25000210)ACRE0.75$5,900.25$3,300.00$3,500.00$5,500.00$14,520$32,000
28Seeding CL 4B (25000314)ACRE0.25$10,803$5,600.00$6,000.00$10,000$14,520$32,000
29Nitrogen fert nutr (25000400)LB70$3.85$3.00$4.00$4.00$1.00$2.00
30Phosphorus fert nutr (25000500)LB70$3.85$3.00$4.00$4.00$1.00$2.00
31Potassium fert nutr (25000600)LB70$3.85$3.00$4.00$5.00$1.00$2.00
32Mowing (25000750)ACRE0.75$2,216.05$2,000.00$2,500.00$2,000.00$2,000.00$2,200.00
33Mulch method 2 (25100115)ACRE1$6,759.00$3,540.00$4,000.00$6,100.00$1,000.00$1,100.00
34Erosion contr blanket (25100630)SY3,722$2.30$1.80$2.00$2.25$3.00$3.30
35Sodding salt tolerant (25200110)SY76$31.00$65.00$75.00$30.00$95.00$105.00
36Temp eros contr seed (28000250)LB80$8.85$7.00$8.00$8.00$0.10$1.00
37Temp ditch checks (28000305)LF21$15.50$20.00$17.00$14.00$25.00$45.00
38Perimeter eros bar (28000400)LF1,067$4.35$5.80$5.00$4.00$5.00$5.50
39Inlet & pipe protect (28000500)EACH2$288.00$209.00$275.00$300.00$200.00$220.00
40Temp eros contr blank (28001100)SY3,785$1.05$1.70$1.90$1.00$1.00$1.00
41Agg subgrade improve (30300001)CY28$103.60$80.00$50.00$150.00$224.00$65.00
42Agg subgrade impr 12 (30300112)SY412$31.55$56.40$30.00$52.00$80.00$23.00
43Bit matls tack CT (40600290)LB264$1.00$0.01$0.01$0.10$0.01$0.10
44Long joint sealant (40600370)LF240$49.85$111.35$120.00$52.00$111.00$120.00
45HMA SC IL-9.5 D N70 (40604062)TON22$100.00$397.00$420.00$600.00$397.00$440.00
46P HMA SC SMA 9.5 F N80 (40605026)TON78$498.60$570.20$600.00$700.00$571.00$620.00
47Protective coat (42001300)SY59$14.50$20.00$10.00$5.00$2.00$10.00
48HMA surf rem 2 (44000157)SY193$44.30$27.00$30.00$67.00$27.00$30.00
49Comb curb gutter rem (44000500)LF76$6.55$21.00$10.00$25.00$22.00$15.00
50Conc barrier remov (44001980)LF38$504.90$94.70$160.00$125.00$153.00$212.00
51CL C patch T4 18 (44201449)SY371$221.60$175.00$250.00$200.00$234.00$425.00
52Conc rem (50102400)CY1.10$241.65$3,682.00$500.00$3,500.00$5,215.00$9,500.00
53Structure excavation (50200100)CY351$73.00$130.00$60.00$100.00$143.00$65.00
54Rem/disp uns matl-STR (50200450)CY42$710.85$130.00$60.00$100.00$229.00$85.00
55Reinf bars, epoxy CTD (50800205)LB880$12.00$3.00$10.00$6.50$3.00$8.00
56Temp soil reten systm (52200020)SF620$50.75$0.01$55.00$1.00$200.00$88.00
57Conc box cul (54003000)CY6.10$4,387.00$2,500.00$3,000.00$11,000$3,021.00$4,800.00
58PCBC 5X3 (54010503)LF130$930.65$1,250.00$2,200.00$750.00$2,000.00$1,850.00
59P cul CL D 2 12 (542D1057)LF40$91.90$90.00$175.00$95.00$122.00$135.00
60PRC flar end sec 12 (54213657)EACH2$1,734.00$2,555.00$1,800.00$2,300.00$3,211.00$1,600.00
61Comb CC&G TY B-6.24 (60605000)LF76$260.55$75.00$50.00$150.00$90.00$69.00
62Pipe culv cleaned 24 (60920024)LF62$52.45$50.00$80.00$100.00$10.00$50.00
63Conc bar 2F 44HT (63700280)LF38$425.30$397.75$400.00$325.00$400.00$428.00
64Conc barrier base (63700900)LF38$258.15$342.10$150.00$150.00$200.00$320.00
65Shoulder rum strip 16 (64200116)LF2,475$2.70$5.35$6.00$3.00$5.35$5.00
66Non SPL waste disposl (66900200)CY500$175.00$105.00$90.00$95.00$75.00$72.00
67Soil disposal analy (66900530)EACH2$997.00$780.00$2,000.00$1,500.00$1,450.00$1,600.00
68Reg sub P-const plan (66901001)LS1$5,096.00$4,500.00$5,500.00$3,100.00$3,100.00$3,400.00
69Reg sub F con report (66901003)LS1$554.00$500.00$1,200.00$1,200.00$1,200.00$1,300.00
70Reg sub mon (66901006)CAL DAY15$831.00$715.00$1,400.00$800.00$680.00$750.00
71Mobilization (67100100)LS1$62,930$170,000$74,000$70,000$81,000$72,000
72Changeable message SN (70107025)CAL DAY242$31.00$28.00$28.00$29.00$28.00$33.00
73SHRT TRM pavt MK rem (70300150)SF3,520$0.45$0.40$2.15$0.40$0.40$0.50
74Temp PVT MK L4 T4 tape (70307120)LF14,079$1.30$1.30$1.60$1.35$1.00$1.40
75Temp conc barrier (70400100)LF637.50$49.70$44.85$55.00$32.00$45.00$36.00
76Rel temp conc barrier (70400200)LF1,037.50$4.80$4.35$15.00$4.00$4.00$12.00
77Imp attn temp NRD TL3 (70600250)EACH2$3,878.00$3,500.00$3,500.00$3,500.00$3,500.00$4,400.00
78Imp attn rel NRD TL3 (70600350)EACH2$1,329.00$1,200.00$1,800.00$1,200.00$1,200.00$2,200.00
79THPL PVT MK line 4 (78000200)LF8,723$1.30$1.20$1.35$1.20$1.00$1.50
80THPL PVT MK line 12 (78000600)LF124$3.30$3.00$6.70$3.00$3.00$3.50
81Pref PL PM TD STD L 6 (78004630)LF1,090$11.05$10.00$10.00$10.00$10.00$7.50
82GRV RCSD PVT MRKG 7 (78011035)LF1,090$2.20$2.00$4.50$2.00$2.00$3.00
83Raised refl pavt MKR (78100100)EACH4$1,108.00$1,000.00$825.00$1,000.00$1,000.00$330.00
84Barr wall ref type C (78200011)EACH3$33.00$30.00$28.00$30.00$30.00$30.00
85Raised ref PVT MK rem (78300200)EACH4$150.00$169.70$220.00$25.00$12.00$40.00
86PVT MKG rem WTR blast (78300202)SF2,454$3.30$3.00$4.60$3.00$1.00$4.00
IDOT contract 80D46: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of June 12, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy