IDOT contract 61M42 bid tabulation

Sugar Grove, section 25-00037-00-RS. Let by Illinois DOT on June 12, 2026, Kane, District 01. 4 bids received; low bid $654,874 by D. Construction, Inc..

Owner
Illinois DOT
Letting
12 JUN 2026
Pay items
49
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1D. Construction, Inc.$654,874Low
2Builders Paving, LLC$672,288+3.0%
3Geneva Construction Company$719,965+10%
4Curran Contracting Company$831,076+27%
IDOT contract 61M42: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. D. Construction, Inc.2. Builders Paving, LLC3. Geneva Construction Company4. Curran Contracting Company
1Bike path rem (X0327036)SY14$10.00$23.25$10.00$80.60
2HMA surf rem SPL (X4400196)SY96$25.00$15.00$16.00$30.00
3Change message SN SPL (X7010238)CAL MO6$1,500.00$1,200.00$1,200.00$1,200.00
4Temp info signing (X7200061)SF52$30.00$20.00$20.00$20.00
5Construction layout (Z0013798)LS1$2,500.00$6,500.00$1,500.00$5,000.00
6Topsoil F & P 4 (21101615)SY28$7.70$7.00$7.00$7.00
7Seeding CL 2A (25000210)ACRE0.10$8,800.00$8,000.00$8,000.00$8,000.00
8Nitrogen fert nutr (25000400)LB9$3.30$3.00$3.00$3.00
9Phosphorus fert nutr (25000500)LB9$3.30$3.00$3.00$3.00
10Potassium fert nutr (25000600)LB9$3.30$3.00$3.00$3.00
11Erosion contr blanket (25100630)SY112$7.70$7.00$7.00$7.00
12Sodding salt tolerant (25200110)SY27$110.00$100.00$100.00$100.00
13Supple watering (25200200)UNIT1.50$0.01$0.01$0.01$0.01
14Perimeter eros bar (28000400)LF140$5.50$5.00$5.00$5.00
15Agg base cse B 4 (35101600)SY49$11.50$9.15$3.00$58.00
16Bit matls tack CT (40600290)LB15,758$0.01$0.01$0.01$1.00
17Long joint sealant (40600370)LF8,980$2.92$3.05$2.70$2.75
18Mix CR JTS flangewys (40600400)TON20$0.01$675.00$125.00$350.00
19HMA surf rem butt JT (40600982)SY72$25.00$15.00$14.00$30.00
20HMA BC IL-19.0 N50 (40603080)TON2,978$73.00$72.00$85.00$77.00
21HMA SC IL-9.5 D N50 (40604060)TON1,986$77.00$79.00$88.00$87.00
22Bit matls tack CT (40800029)LB203$0.01$0.01$0.01$1.00
23Incidental HMA surf (40800050)TON51$90.00$200.00$180.00$300.00
24Protective coat (42001300)SY51$1.00$1.00$0.01$7.75
25PC conc sidewalk 5 (42400200)SF315$18.00$10.35$12.00$23.10
26Detectable warnings (42400800)SF34$30.00$46.00$35.00$43.60
27HMA surf rem 3 (44000161)SY7,185$2.75$3.25$4.10$4.75
28HMA surf rem 3 1/2 (44000163)SY16,449$2.85$3.80$4.10$5.25
29Comb curb gutter rem (44000500)LF68$10.00$12.00$18.00$49.75
30Sidewalk rem (44000600)SF231$4.00$2.95$2.25$14.65
31CL D patch T1 6 (44201713)SY150$67.00$60.00$56.00$260.00
32CL D patch T2 6 (44201717)SY150$67.00$60.00$56.00$150.00
33CL D patch T3 6 (44201721)SY150$67.00$60.00$56.00$115.00
34Aggregate SHLDS B (48101200)TON568$32.00$41.00$37.50$40.00
35Comb CC&G TB6.12 aep (60603900)LF68$75.00$42.00$60.00$117.55
36Mobilization (67100100)LS1$39,250$51,050$43,000$42,950
37Traf cont-prot 701201 (70100450)LS1$0.01$500.00$100.00$100.00
38Traf cont-prot 701306 (70100460)LS1$0.01$6,500.00$4,350.00$4,350.00
39Traf cont-prot 701336 (70100600)LS1$0.01$500.00$100.00$100.00
40TR cont & prot 701501 (70102620)LS1$39,300$500.00$100.00$100.00
41TR cont & prot 701801 (70102640)LS1$0.01$500.00$100.00$100.00
42Short term pavt mking (70300100)LF2,797$0.01$0.01$0.01$0.50
43SHRT TRM pavt MK rem (70300150)SF2,113$0.01$0.01$0.01$3.50
44Temp PVT MK L4 T4 tape (70307120)LF11,895$0.01$0.01$1.30$1.30
45THPL PVT MK LTR & sym (78000100)SF37$5.78$6.50$5.25$5.25
46THPL PVT MK line 4 (78000200)LF27,437$0.79$0.74$0.72$0.72
47THPL PVT MK line 6 (78000400)LF309$1.38$1.11$1.25$1.25
48THPL PVT MK line 12 (78000600)LF80$2.75$3.25$2.50$2.50
49THPL PVT MK line 24 (78000650)LF30$5.78$6.50$5.25$5.25
IDOT contract 61M42: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of June 12, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy