IDOT contract 61M23 bid tabulation
Lakewood, section 22-00016-00-RS. Let by Illinois DOT on February 27, 2026, Mchenry, District 01. 5 bids received; low bid $778,992 by Geske and Sons, Inc..
- Owner
- Illinois DOT
- Letting
- 27 FEB 2026
- Pay items
- 48
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Geske and Sons, Inc. | $778,992 | Low |
| 2 | Builders Paving, LLC | $856,218 | +10% |
| 3 | Plote Construction, Inc. | $881,117 | +13% |
| 4 | Peter Baker & Son Co. | $931,980 | +20% |
| 5 | Curran Contracting Company | $953,197 | +22% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Geske and Sons, Inc. | 2. Builders Paving, LLC | 3. Plote Construction, Inc. | 4. Peter Baker & Son Co. | 5. Curran Contracting Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Prun safety/equip CLR (K1004595) | LS | 1 | $8,250.00 | $15,000 | $4,000.00 | $15,500 | $7,500.00 |
| 2 | HMA drive rem & rep (XX006947) | SY | 989 | $28.15 | $44.00 | $9.00 | $38.50 | $45.00 |
| 3 | Temp info signing (X7200061) | SF | 52 | $31.50 | $30.00 | $30.00 | $30.00 | $30.00 |
| 4 | Rem & disp uns matl (20201200) | CY | 228 | $12.50 | $50.00 | $5.00 | $20.00 | $45.00 |
| 5 | Geotech fab F/GR stab (21001000) | SY | 1,360 | $1.00 | $2.00 | $0.01 | $1.00 | $1.50 |
| 6 | Topsoil F & P 4 (21101615) | SY | 5,173 | $0.11 | $2.00 | $2.00 | $2.00 | $0.10 |
| 7 | Seeding CL 2A (25000210) | ACRE | 1.25 | $2,541.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,420.00 |
| 8 | Nitrogen fert nutr (25000400) | LB | 113 | $1.05 | $1.00 | $1.00 | $1.00 | $1.00 |
| 9 | Potassium fert nutr (25000600) | LB | 113 | $1.05 | $1.00 | $1.00 | $1.00 | $1.00 |
| 10 | Wildlife friendly ecb (25100645) | SY | 5,173 | $7.35 | $3.85 | $3.85 | $3.85 | $7.00 |
| 11 | Temp eros contr seed (28000250) | LB | 125 | $0.11 | $0.01 | $0.01 | $0.01 | $0.10 |
| 12 | Agg subgrade improve (30300001) | CY | 228 | $15.00 | $50.00 | $20.00 | $35.00 | $52.50 |
| 13 | Bit matls tack CT (40600290) | LB | 19,784 | $0.30 | $0.01 | $0.01 | $0.01 | $1.25 |
| 14 | Long joint sealant (40600370) | LF | 11,638 | $2.88 | $2.85 | $3.40 | $3.45 | $3.00 |
| 15 | Mix CR JTS flangewys (40600400) | TON | 9 | $150.00 | $500.00 | $1,250.00 | $768.00 | $450.00 |
| 16 | HMA surf rem butt JT (40600982) | SY | 80 | $38.59 | $20.00 | $0.01 | $1.00 | $15.00 |
| 17 | P HMA BC IL-4.75 N50 (40603200) | TON | 1,210 | $100.85 | $95.00 | $105.00 | $99.00 | $100.00 |
| 18 | HMA SC IL-9.5 D N50 (40604060) | TON | 2,873 | $80.95 | $70.00 | $90.00 | $82.50 | $80.00 |
| 19 | HMA surf rem 2 1/2 (44000159) | SY | 29,308 | $2.56 | $3.00 | $3.10 | $3.65 | $3.05 |
| 20 | CL D patch T1 4 (44201690) | SY | 137 | $37.50 | $45.00 | $25.00 | $40.00 | $130.00 |
| 21 | CL D patch T2 4 (44201692) | SY | 204 | $34.10 | $45.00 | $25.00 | $40.00 | $75.00 |
| 22 | CL D patch T3 4 (44201694) | SY | 340 | $34.10 | $40.00 | $25.00 | $40.00 | $65.00 |
| 23 | CL D patch T4 4 (44201696) | SY | 679 | $34.10 | $40.00 | $25.00 | $40.00 | $45.00 |
| 24 | Agg wedge SHLD type B (48102100) | TON | 585 | $49.00 | $50.00 | $30.00 | $70.00 | $72.50 |
| 25 | SPBGR TY A 6FT posts (63000001) | LF | 363 | $32.75 | $33.00 | $33.00 | $33.00 | $31.16 |
| 26 | Traf bar term T2 (63100045) | EACH | 1 | $1,768.00 | $2,100.00 | $2,100.00 | $2,100.00 | $1,683.00 |
| 27 | TR bar TRM T1 SPL tan (63100167) | EACH | 3 | $3,652.00 | $3,620.00 | $3,620.00 | $3,620.00 | $3,478.00 |
| 28 | Guardrail remov (63200310) | LF | 317 | $17.20 | $6.00 | $6.00 | $6.00 | $16.34 |
| 29 | Non SPL waste disposl (66900200) | CY | 228 | $35.00 | $50.00 | $25.00 | $124.00 | $75.00 |
| 30 | Soil disposal analy (66900530) | EACH | 4 | $425.00 | $650.00 | $900.00 | $1,450.00 | $1,450.00 |
| 31 | Reg sub P-const plan (66901001) | LS | 1 | $3,300.00 | $6,600.00 | $2,000.00 | $3,100.00 | $3,100.00 |
| 32 | Reg sub F con report (66901003) | LS | 1 | $250.00 | $500.00 | $900.00 | $1,200.00 | $1,200.00 |
| 33 | Reg sub mon (66901006) | CAL DAY | 10 | $358.00 | $100.00 | $450.00 | $680.00 | $680.00 |
| 34 | Mobilization (67100100) | LS | 1 | $29,680 | $92,986 | $52,000 | $67,842 | $73,500 |
| 35 | Traf cont-prot 701201 (70100450) | LS | 1 | $7,590.00 | $10,000 | $97,400 | $18,268 | $10,000 |
| 36 | Traf cont-prot 701306 (70100460) | LS | 1 | $105.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 37 | Short term pavt mking (70300100) | LF | 186,712 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 38 | SHRT TRM pavt MK rem (70300150) | SF | 62,838 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 39 | Sign panel T1 (72000100) | SF | 107 | $26.25 | $25.00 | $25.00 | $55.00 | $25.00 |
| 40 | Rem & rel sign panel T1 (72400735) | SF | 4 | $78.75 | $75.00 | $75.00 | $300.00 | $75.00 |
| 41 | Terminal marker - DA (72501000) | EACH | 3 | $52.50 | $50.00 | $50.00 | $50.00 | $50.00 |
| 42 | Teles STL sin support (72800100) | LF | 285 | $13.65 | $13.00 | $13.00 | $30.00 | $13.00 |
| 43 | THPL PVT MK line 4 (78000200) | LF | 46,552 | $0.71 | $0.70 | $0.68 | $0.65 | $0.68 |
| 44 | THPL PVT MK line 12 (78000600) | LF | 60 | $2.73 | $2.60 | $2.60 | $1.95 | $2.60 |
| 45 | THPL PVT MK line 24 (78000650) | LF | 66 | $5.46 | $5.20 | $5.20 | $3.90 | $5.20 |
| 46 | GRV RCSD PVT MRKG 5 (78011025) | LF | 19,398 | $0.42 | $0.40 | $0.40 | $0.35 | $0.40 |
| 47 | Raised refl pavt MKR (78100100) | EACH | 146 | $47.25 | $45.00 | $45.00 | $65.00 | $45.00 |
| 48 | Grdrail ref type A (78200005) | EACH | 4 | $13.65 | $15.00 | $15.00 | $15.00 | $13.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.