IDOT contract 62X25 bid tabulation

Section (7HB-K(86)BR. Let by Illinois DOT on April 25, 2025, Cook, District 01. 4 bids received; low bid $241,055 by Martam Construction Incorporated.

Owner
Illinois DOT
Letting
25 APR 2025
Pay items
17
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Martam Construction Incorporated$241,055Low
2Herlihy Mid-Continent Company$356,580+48%
3Path Construction Company, Inc.$407,440+69%
4Alliance Contractors, Inc.$444,932+85%
IDOT contract 62X25: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Martam Construction Incorporated2. Herlihy Mid-Continent Company3. Path Construction Company, Inc.4. Alliance Contractors, Inc.
1Rem TH epxy B DK olay (X0325499)SY866$38.00$64.00$75.00$55.00
2Clean reseal RLF JNT (X0326766)LF236$45.00$20.00$35.00$40.00
3Floor drains cleaned (X5030539)EACH4$550.00$500.00$500.00$500.00
4CLN BRDG scups/DNSPTS (X5230154)EACH8$550.00$500.00$500.00$500.00
5Engrs FLD ofc TY A D1 (X6700407)CAL MO6$3,200.00$5,125.00$3,000.00$500.00
6Traf cont & prot SPL (X7010216)LS1$48,500$14,950$53,440$33,895
7Temp info signing (X7200061)SF80$20.00$20.00$30.00$20.00
8BR DK TH poly ovl 3/8 (Z0012193)SY866$97.00$212.35$225.00$322.00
9Polymer concrete (Z0041895)CF4$1,850.00$3,210.00$1,300.00$1,950.00
10Mobilization (67100100)LS1$14,000$21,390$24,024$26,000
11Short term pavt mking (70300100)LF4,495$0.10$1.55$2.50$2.50
12SHRT TRM pavt MK rem (70300150)SF1,499$0.50$1.90$2.75$2.75
13Mod ureth PM line 4 (78009004)LF1,280$6.00$4.11$5.00$4.11
14Mod ureth PM line 6 (78009006)LF46$7.00$6.17$6.00$6.17
15Mod ureth PM line 12 (78009012)LF52$12.00$12.33$10.00$12.33
16Raised refl pavt MKR (78100100)EACH16$370.00$438.10$340.00$438.10
17Raised ref PVT MK rem (78300200)EACH16$30.00$125.00$145.00$135.00
IDOT contract 62X25: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy