IDOT contract 61J54 bid tabulation

Project Number: Whf6-372 / /, section 16-F3000-15-BT. Let by Illinois DOT on November 7, 2025, Dupage, District 01. 3 bids received; low bid $6,927,969 by Lorig Construction Company.

Owner
Illinois DOT
Letting
07 NOV 2025
Pay items
157
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Lorig Construction Company$6,927,969Low
2Copenhaver Construction, Inc.$7,233,472+4.0%
3Herlihy Mid-Continent Company$7,369,000+6.0%
IDOT contract 61J54: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Lorig Construction Company2. Copenhaver Construction, Inc.3. Herlihy Mid-Continent Company
1T-carya cord 1-1/2 (A2002612)EACH5$575.00$800.00$875.00
2T-carya ovata 1-3/4 (A2002714)EACH6$485.00$800.00$875.00
3T-gymnocla dio 1-3/4 (A2005014)EACH6$325.00$800.00$437.50
4T-platanus occ 1-3/4 (A2005814)EACH8$325.00$800.00$487.50
5T-quercus bicol 1-1/2 (A2006512)EACH6$300.00$800.00$412.50
6T-quercus macr 1-1/2 (A2006712)EACH8$300.00$800.00$412.50
7T-quercus palus 1-1/2 (A2006912)EACH8$300.00$800.00$412.50
8S-corylus amer CG 5G (C2C005G5)EACH18$75.00$100.00$114.00
9S-cornus obliq CG 3G (C2C015G3)EACH21$78.00$80.00$114.00
10S-lind benzoin 5G (C2C043G5)EACH11$80.00$100.00$135.00
11S-sambucus canad 2'C (C2C09624)EACH15$70.00$150.00$114.00
12S-viburn lentag CG 5G (C2C100G5)EACH12$75.00$100.00$114.00
13S-cephalan occi CG 5G (C2001162)EACH17$64.00$100.00$114.00
14P PL wetlnd 2X4 DPPLG (K0013030)UNIT24$530.00$800.00$1,850.00
15Limestone SCRN surf 2 (XX007606)SY3,199$12.50$8.00$8.00
16Ped truss superstr (X0322508)SF2,665$275.00$371.00$331.50
17Rod and clean EX cond (X0324599)LF263$2.00$2.00$2.00
18Temp wir intercon com (X0325938)LS1$30,000$30,000$30,000
19Anti-graffiti coating (X0327999)SF7,391$8.50$10.00$8.33
20R R FL beacon A comp (X1400326)EACH2$12,500$12,500$12,000
21Selective clearing (X2010514)ACRE0.50$10,000$15,000$12,500
22Seeding CL 2 mod (X2501010)ACRE0.50$2,600.00$6,000.00$2,400.00
23Seeding CL 4 mod (X2501800)ACRE2.50$1,400.00$6,000.00$1,800.00
24Seeding CL 5 mod (X2501820)ACRE0.75$1,700.00$8,000.00$4,500.00
25Seeding CL 4B mod (X2502024)ACRE0.25$1,700.00$10,000$5,800.00
26Above grade inlt FLTR (X2800520)EACH2$600.00$300.00$200.00
27PCC sidewalk curb (X4240118)LF88$95.00$50.00$40.00
28CL D patch T4 8 SPL (X4420174)SY25$375.00$190.00$180.00
29Aggregate SHLD removl (X4810200)CY5$125.00$100.00$180.00
30Conc HDWL rem SPL (X5012650)EACH1$1,800.00$5,000.00$1,221.00
31Cofferdam typ 1 IS WW (X5021512)EACH2$1,000.00$10,000$6,700.00
32Stain conc structures (X5030290)SF2,852$4.50$6.00$4.62
33HLMRB disc G exp 100K (X5211605)EACH8$3,925.00$2,000.00$5,989.00
34HLMRB disc G exp 200K (X5211610)EACH4$4,975.00$2,000.00$6,983.00
35Pro SS conn to EX man (X5510011)EACH1$2,700.00$1,500.00$1,621.00
36WD post & rail fence (X6640628)LF770.50$110.00$150.00$106.15
37Temp CL fence SCRN 6 (X6640706)LF1,350$25.00$15.00$24.44
38Traf cont & prot SPL (X7010216)LS1$280,000$347,000$32,000
39Temp info signing (X7200061)SF12.50$50.00$35.00$40.00
40Intercept EX conduit (X8100863)EACH2$1,500.00$1,500.00$1,443.00
41Accessible ped signal (X8760200)EACH2$4,200.00$4,200.00$4,125.00
42Temp TR signal timing (X8900104)EACH3$630.00$630.00$600.00
43Rem & rein FO CBL con (X8950512)LF263$7.00$7.00$6.85
44Stab constr entrance (Z0013797)SY399$3.00$30.00$30.00
45Construction layout (Z0013798)LS1$200,000$19,000$123,457
46Sed cont silt curtain (Z0023201)EACH2$7,000.00$4,000.00$3,800.00
47RE-optimize TR sig sys 1 (Z0033044)EACH1$630.00$630.00$1,200.00
48Trainees (Z0076600)HR1,000$0.80$0.80$0.80
49Trainees TPG (Z0076604)HR1,000$15.00$15.00$15.00
50Tree remov 6-15 (20100110)UNIT32$30.00$45.00$30.00
51Tree remov over 15 (20100210)UNIT36$45.00$77.00$38.00
52Temporary fence (20101000)LF4,731$3.00$8.00$2.50
53Tree trunk protection (20101100)EACH20$150.00$150.00$150.00
54Tree root pruning (20101200)EACH20$124.00$100.00$150.00
55Tree prun 1-10 (20101300)EACH5$75.00$65.00$50.00
56Tree prun over 10 (20101350)EACH5$125.00$200.00$250.00
57Supple watering (20101700)UNIT187$50.00$0.01$10.00
58Earth excavation (20200100)CY3,350$43.00$45.00$30.00
59Rem & disp uns matl (20201200)CY315$70.00$46.00$40.00
60Furnished excavation (20400800)CY800$60.00$10.00$15.00
61Trench backfill (20800150)CY100$50.00$40.00$72.00
62Porous gran backfill (20900110)CY659$120.00$55.00$60.00
63Geotech fab F/GR stab (21001000)SY2,810$2.75$3.00$2.50
64Topsoil exc & plac (21101505)CY5,080$58.00$15.00$47.25
65Seeding CL 7 (25000350)ACRE3.25$1,800.00$7,000.00$600.00
66Mowing (25000750)ACRE3.25$350.00$2,000.00$600.00
67Mulch method 3 (25100125)ACRE3.25$2,200.00$3,000.00$2,900.00
68Wildlife friendly ecb (25100645)SY13,141$1.80$2.00$1.25
69Temp eros contr seed (28000250)LB325$3.00$0.01$5.00
70Temp ditch checks (28000305)LF330$4.00$15.00$8.50
71Perimeter eros bar (28000400)LF8,534$2.00$3.00$2.00
72Inlet filters (28000510)EACH4$250.00$250.00$200.00
73Stone riprap CL A3 (28100105)SY60$135.00$95.00$150.00
74Agg subgrade improve (30300001)CY315$120.00$50.00$45.00
75Agg subgrade impr 12 (30300112)SY3,199$38.00$16.00$19.00
76Sub gran mat B 4 (31101200)SY129$37.00$10.00$16.00
77PC conc sidewalk 5 (42400200)SF1,811$12.00$15.00$11.00
78Detectable warnings (42400800)SF82$89.00$40.00$50.00
79Comb curb gutter rem (44000500)LF70$14.00$10.00$50.00
80Sidewalk rem (44000600)SF114$7.50$5.00$15.00
81Structure excavation (50200100)CY1,701$65.00$55.00$50.00
82Cofferdam excavation (50200300)CY131$65.00$79.00$71.00
83Conc struct (50300225)CY527.20$1,300.00$1,800.00$1,050.00
84Conc sup-STR (50300255)CY167.60$1,300.00$2,600.00$3,575.00
85Form liner tex surf (50300285)SF4,198$12.00$35.00$23.50
86Protective coat (50300300)SY972$1.50$3.00$3.00
87Conc supstr app slab (50301350)CY13$1,350.00$1,200.00$2,550.00
88F & E struct steel (50500105)LS1$1,275,000$1,025,000$1,821,000
89Stud shear connectors (50500505)EACH3,873$8.00$10.00$5.05
90Reinf bars, epoxy CTD (50800205)LB105,880$1.95$2.50$2.45
91Bicycle railing (50901720)LF1,150$400.00$420.00$399.55
92Fur M S pile 12X0.250 (51200957)LF1,456$70.00$130.00$33.00
93Driving piles (51202305)LF1,456$1.00$1.00$1.00
94Test pile met shells (51203200)EACH5$7,000.00$6,500.00$20,000
95Pile shoes (51204650)EACH51$350.00$350.00$400.00
96Name plates (51500100)EACH1$1,000.00$2,000.00$1,000.00
97Pref joint seal 2 1/4 (52000027)LF47$500.00$470.00$585.00
98Anchor bolts 1 (52100520)EACH24$350.00$100.00$555.00
99Anchor bolts 1 1/2 (52100540)EACH16$350.00$110.00$400.00
100Seg conc block wall (52200800)SF1,254$107.00$75.00$49.00
101P cul CL A 1 15 (542A0220)LF76$160.00$140.00$148.00
102P cul CL A 1 15 temp (5421A015)LF100$185.00$120.00$138.00
103PRC flar end sec 12 (54213657)EACH2$2,225.00$1,500.00$2,304.00
104PRC flar end sec 15 (54213660)EACH12$2,600.00$1,800.00$2,374.00
105Storm sew CL A 1 12 (550A0050)LF70$165.00$130.00$138.00
106Storm sewer rem 12 (55100500)LF22$130.00$50.00$35.00
107Water valves adjust (56109210)EACH1$500.00$300.00$787.00
108Granular backfill STR (58600101)CY12.10$135.00$110.00$86.00
109Geocomposite wall DR (59100100)SY288$42.00$30.00$36.00
110Conc HDWL for P drain (60100060)EACH4$1,100.00$500.00$1,233.00
111P undr for struct 4 (60146304)LF255$48.00$20.00$26.00
112P undr for struct SPL 4 (60146305)LF150$50.00$25.00$35.00
113CB TC T8G (60207605)EACH2$3,900.00$3,500.00$2,692.00
114Inlets TA T3F&G (60235700)EACH1$2,500.00$2,500.00$2,312.00
115Inlets adj new T1F OL (60260300)EACH1$2,500.00$500.00$1,135.00
116Remov inlets (60500060)EACH1$900.00$500.00$378.00
117Comb CC&G TB6.18 (60604400)LF25$100.00$49.00$100.00
118Comb CC&G TY B-6.24 (60605000)LF46$110.00$49.00$110.00
119CH LK fence 8 (66400505)LF1,578$41.00$60.00$40.99
120CH LK gate 8X12 singl (66405500)EACH2$1,900.00$4,600.00$1,883.00
121Non SPL waste disposl (66900200)CY2,260$90.00$85.00$75.00
122Soil disposal analy (66900530)EACH5$1,250.00$1,400.00$1,400.00
123Reg sub P-const plan (66901001)LS1$4,400.00$5,000.00$5,200.00
124Reg sub F con report (66901003)LS1$900.00$1,000.00$500.00
125Reg sub mon (66901006)CAL DAY40$1,500.00$300.00$800.00
126Engr field office A (67000400)CAL MO12$3,500.00$3,000.00$4,900.00
127Mobilization (67100100)LS1$350,000$430,000$440,827
128Changeable message SN (70107025)CAL DAY112$65.00$45.00$30.00
129Night work zone light (70200100)LS1$100.00$12,000$700.00
130Sign panel T1 (72000100)SF32$35.00$45.00$38.00
131Metal post TY A (72900100)LF104$20.00$35.00$20.00
132THPL PVT MK line 4 (78000200)LF2,135$2.30$1.00$1.75
133THPL PVT MK line 6 (78000400)LF199$3.50$5.00$2.00
134THPL PVT MK line 12 (78000600)LF315$7.00$10.00$4.00
135THPL PVT MK line 24 (78000650)LF11$14.00$30.00$8.00
136Undrgrd C galvs 2 (81028200)LF15$35.00$35.00$34.82
137Undrgrd C galvs 3 (81028220)LF16$48.00$48.00$47.18
138Undrgrd C galvs 4 (81028240)LF140$119.00$120.00$118.50
139Handhole (81400100)EACH1$4,500.00$4,500.00$4,465.00
140Main EX TR sig instal (85000200)EACH2$5,300.00$5,300.00$5,300.00
141Elcbl C signal 14 2C (87301215)LF311$3.00$3.00$2.98
142Elcbl C signal 14 3C (87301225)LF325$3.25$4.00$3.12
143Elcbl C signal 14 5C (87301245)LF922$3.50$4.00$3.44
144Elcbl C signal 14 7C (87301255)LF198$4.00$4.00$3.77
145Elcbl C egrdc 6 1C (87301900)LF248$3.75$4.00$3.52
146TS post galvs 16 (87502500)EACH2$3,500.00$3,500.00$3,500.00
147Conc FDN TY A (87800100)LF8$575.00$550.00$549.75
148Drill EX handhole (87900200)EACH4$900.00$890.00$882.00
149SH P LED 1F 3S BM (88040070)EACH5$925.00$910.00$902.80
150SH P LED 1F 5S BM (88040150)EACH1$1,200.00$1,200.00$1,154.80
151Ped SH P LED 1F BM CT (88102825)EACH2$800.00$790.00$781.60
152Mod EX contr cab (89502210)EACH1$1,400.00$1,400.00$1,392.00
153Rem elcbl FR con (89502300)LF700$1.00$1.00$0.96
154Rem & RE elcbl FR con (89502350)LF263$7.00$7.00$6.83
155Remov EX TS equip (89502375)EACH1$1,650.00$1,700.00$1,636.50
156Remov EX handhole (89502380)EACH1$1,200.00$1,200.00$1,192.50
157Remov EX conc FDN (89502385)EACH2$700.00$700.00$691.50
IDOT contract 61J54: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of November 7, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy