IDOT contract 87840 bid tabulation
Minooka, section 21-00058-00-BT. Let by Illinois DOT on January 17, 2025, Grundy, District 03. 3 bids received; low bid $1,708,477 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 17 JAN 2025
- Pay items
- 72
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $1,708,477 | Low |
| 2 | Austin Tyler Construction, Inc. | $2,039,321 | +19% |
| 3 | Herlihy Mid-Continent Company | $2,512,800 | +47% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Austin Tyler Construction, Inc. | 3. Herlihy Mid-Continent Company |
|---|---|---|---|---|---|---|
| 1 | Split rail fence (XX000503) | LF | 145 | $31.08 | $9.60 | $28.25 |
| 2 | Flagpole relocation (XX003919) | LS | 1 | $2,000.00 | $1,200.00 | $3,800.00 |
| 3 | Rem & rein sign panel (XX008729) | EACH | 3 | $522.50 | $300.00 | $475.00 |
| 4 | CL D patch SPL (XX009224) | SY | 20 | $168.00 | $175.00 | $225.00 |
| 5 | Ped truss superstr (X0322508) | SF | 2,592 | $250.78 | $302.00 | $382.70 |
| 6 | LT WT cell conc fill (X0325318) | CY | 285.90 | $200.00 | $200.00 | $344.00 |
| 7 | Relocate bench (X0327149) | EACH | 1 | $1,000.00 | $1,490.00 | $550.00 |
| 8 | Bollard removal (X0350810) | EACH | 1 | $500.00 | $370.00 | $500.00 |
| 9 | Earth excavation SPL (X2020410) | CY | 2,900 | $30.00 | $54.00 | $40.00 |
| 10 | Seeding CL 1A SPL (X2500920) | ACRE | 0.15 | $5,255.80 | $4,840.00 | $4,778.00 |
| 11 | Seeding CL 2A SPL (X2501020) | ACRE | 0.40 | $5,358.10 | $4,840.00 | $4,871.00 |
| 12 | Aggregate SHLDS SPL (X4811800) | SY | 25 | $30.00 | $38.00 | $75.00 |
| 13 | Fence removal (X6640104) | LF | 185 | $10.56 | $10.00 | $9.60 |
| 14 | Wood fence rem & RE-E (X6640630) | LF | 300 | $69.23 | $63.00 | $62.94 |
| 15 | Wood rail SPL (X6640634) | LF | 122 | $143.48 | $130.00 | $130.44 |
| 16 | HMA driveway pavt 4 (Z0004514) | SY | 180 | $35.00 | $64.00 | $85.00 |
| 17 | Tree remov 6-15 (20100110) | UNIT | 90 | $33.00 | $30.00 | $35.00 |
| 18 | Tree remov over 15 (20100210) | UNIT | 24 | $44.00 | $40.00 | $45.00 |
| 19 | Rem & disp uns matl (20201200) | CY | 150 | $30.00 | $51.00 | $45.00 |
| 20 | Trench backfill (20800150) | CY | 30 | $80.00 | $0.01 | $170.00 |
| 21 | Topsoil F & P 4 (21101615) | SY | 2,730 | $6.60 | $3.00 | $6.00 |
| 22 | Erosion contr blanket (25100630) | SY | 2,730 | $1.43 | $7.00 | $1.30 |
| 23 | Perimeter eros bar (28000400) | LF | 2,300 | $2.86 | $2.50 | $2.60 |
| 24 | Inlet filters (28000510) | EACH | 3 | $183.70 | $300.00 | $167.00 |
| 25 | Stone riprap CL A4 (28100107) | SY | 265 | $80.00 | $97.00 | $160.00 |
| 26 | Filter fabric (28200200) | SY | 265 | $5.00 | $3.50 | $8.00 |
| 27 | Agg subgrade improve (30300001) | CY | 1,500 | $50.00 | $53.00 | $45.00 |
| 28 | Agg base cse B 6 (35101800) | SY | 2,260 | $12.00 | $13.00 | $16.00 |
| 29 | Preparation of base (35800100) | SY | 50 | $20.00 | $3.50 | $10.00 |
| 30 | Aggregate-temp access (40201000) | TON | 50 | $30.00 | $28.00 | $50.00 |
| 31 | Bit matls PR CT (40600275) | LB | 4,050 | $0.01 | $0.01 | $0.01 |
| 32 | Bit matls tack CT (40600290) | LB | 810 | $0.01 | $0.01 | $0.01 |
| 33 | HMA BC IL-19.0 N50 (40603080) | TON | 230 | $100.00 | $107.00 | $140.00 |
| 34 | HMA SC IL-9.5 C N50 (40604050) | TON | 155 | $110.00 | $133.00 | $145.00 |
| 35 | PCC driveway pavt 6 (42300200) | SY | 20 | $110.00 | $94.00 | $175.00 |
| 36 | PC conc sidewalk 5 (42400200) | SF | 340 | $12.00 | $9.50 | $18.00 |
| 37 | Detectable warnings (42400800) | SF | 115 | $30.00 | $30.00 | $26.00 |
| 38 | Pavement rem (44000100) | SY | 50 | $30.00 | $18.00 | $35.00 |
| 39 | Drive pavement rem (44000200) | SY | 200 | $14.00 | $19.00 | $35.00 |
| 40 | Comb curb gutter rem (44000500) | LF | 60 | $10.00 | $12.00 | $30.00 |
| 41 | Sidewalk rem (44000600) | SF | 55 | $10.00 | $4.00 | $15.00 |
| 42 | Structure excavation (50200100) | CY | 121 | $35.00 | $94.00 | $96.00 |
| 43 | Conc struct (50300225) | CY | 59.60 | $1,600.00 | $1,488.00 | $5,300.00 |
| 44 | Conc sup-STR (50300255) | CY | 48 | $1,000.00 | $1,515.00 | $2,000.00 |
| 45 | Protective coat (50300300) | SY | 340 | $2.00 | $3.00 | $2.40 |
| 46 | Conc supstr app slab (50301350) | CY | 17.30 | $500.00 | $1,285.00 | $2,500.00 |
| 47 | Reinf bars, epoxy CTD (50800205) | LB | 23,970 | $3.00 | $2.00 | $1.80 |
| 48 | Fur STL pile HP14X73 (51201800) | LF | 405 | $115.00 | $325.00 | $44.61 |
| 49 | Driving piles (51202305) | LF | 405 | $0.01 | $0.01 | $1.00 |
| 50 | Test pile ST HP14X73 (51203800) | EACH | 2 | $5,000.00 | $2,570.00 | $23,000 |
| 51 | Pile shoes (51204650) | EACH | 11 | $250.00 | $142.00 | $135.00 |
| 52 | Name plates (51500100) | EACH | 1 | $1,000.00 | $500.00 | $1,100.00 |
| 53 | Perm SHT piling (52200015) | SF | 2,332 | $54.00 | $55.00 | $48.32 |
| 54 | Seg conc block wall (52200800) | SF | 725 | $41.80 | $100.00 | $38.00 |
| 55 | P cul CL A 1 12 (542A0217) | LF | 35 | $80.00 | $100.00 | $185.00 |
| 56 | P cul CL A 1 15 (542A0220) | LF | 92 | $90.00 | $102.00 | $198.00 |
| 57 | PRC flar end sec 12 (54213657) | EACH | 2 | $1,200.00 | $1,170.00 | $2,533.00 |
| 58 | PRC flar end sec 15 (54213660) | EACH | 4 | $1,500.00 | $1,522.00 | $2,693.00 |
| 59 | Granular backfill STR (58600101) | CY | 19 | $50.00 | $79.00 | $103.00 |
| 60 | Concrete sealer (58700300) | SF | 883 | $3.00 | $2.00 | $3.00 |
| 61 | Geocomposite wall DR (59100100) | SY | 438 | $30.00 | $12.00 | $28.00 |
| 62 | Conc HDWL for P drain (60100060) | EACH | 2 | $500.00 | $840.00 | $2,100.00 |
| 63 | P undr for struct 4 (60146304) | LF | 40 | $30.00 | $49.00 | $62.00 |
| 64 | P undr for struct 6 (60146306) | LF | 150 | $25.00 | $51.50 | $70.00 |
| 65 | Comb CC&G TB6.12 (60603800) | LF | 60 | $45.00 | $66.00 | $80.00 |
| 66 | Mobilization (67100100) | LS | 1 | $102,550 | $91,000 | $149,983 |
| 67 | TR cont & prot 701501 (70102620) | LS | 1 | $26,074 | $5,000.00 | $6,425.00 |
| 68 | TR cont & prot 701801 (70102640) | LS | 1 | $0.01 | $5,000.00 | $100.00 |
| 69 | Sign panel T1 (72000100) | SF | 45 | $27.50 | $60.00 | $25.00 |
| 70 | Metal post TY A (72900100) | LF | 200 | $14.30 | $13.50 | $13.00 |
| 71 | THPL PVT MK line 12 (78000600) | LF | 300 | $16.28 | $14.80 | $14.80 |
| 72 | THPL PVT MK line 24 (78000650) | LF | 30 | $28.66 | $26.05 | $26.05 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.