IDOT contract 61L21 bid tabulation
Rosemont, section 19-00035-00-SP. Let by Illinois DOT on November 7, 2025, Cook, District 01. 2 bids received; low bid $4,177,932 by H & H Electric Co..
- Owner
- Illinois DOT
- Letting
- 07 NOV 2025
- Pay items
- 137
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | H & H Electric Co. | $4,177,932 | Low |
| 2 | John Burns Construction Company | $4,409,000 | +6.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. H & H Electric Co. | 2. John Burns Construction Company |
|---|---|---|---|---|---|
| 1 | S-rosa knockout CG 3G (C2007010) | EACH | 4 | $336.41 | $200.00 |
| 2 | P PL ornament T gal P (K0012990) | UNIT | 0.23 | $5,046.12 | $3,000.00 |
| 3 | Mulch placement 2 (K0036117) | SY | 43 | $16.82 | $10.00 |
| 4 | Explor excavation (XX000541) | CY | 20 | $1,379.16 | $900.00 |
| 5 | Conc truck washout (XX006821) | LS | 1 | $5,887.14 | $10,000 |
| 6 | Exposed agg surf (XX024100) | SF | 145 | $151.38 | $60.00 |
| 7 | EM veh P S LSC 20 3C (X0324085) | LF | 3,842 | $1.48 | $3.00 |
| 8 | Rod and clean EX cond (X0324599) | LF | 1,350 | $0.01 | $1.00 |
| 9 | Concrete land slab (X0325942) | SF | 351 | $30.28 | $16.50 |
| 10 | Conc paver pavement (X0327978) | SY | 40 | $883.07 | $445.00 |
| 11 | Unint PWR sup & C SPL (X1400144) | EACH | 2 | $11,456 | $12,900 |
| 12 | Serv instl GR MT MTR (X1400150) | EACH | 3 | $4,982.83 | $5,100.00 |
| 13 | Luminaire LED special (X1400238) | EACH | 2 | $1,012.13 | $1,500.00 |
| 14 | Ped signal post 10 FT (X1400367) | EACH | 14 | $1,783.46 | $2,800.00 |
| 15 | Curb wall SPL (X1700107) | SF | 359 | $168.20 | $203.00 |
| 16 | PC conc sidewalk 8 SP (X4240460) | SF | 945 | $70.65 | $22.50 |
| 17 | Retaining wall remov (X5220101) | SF | 104 | $67.28 | $50.00 |
| 18 | Ground EX handhole (X8140102) | EACH | 3 | $327.35 | $1,500.00 |
| 19 | Fac in exist cab (X8570215) | EACH | 2 | $15,163 | $14,900 |
| 20 | Fac T super P cab SP (X8570233) | EACH | 3 | $49,117 | $57,600 |
| 21 | Uninter power sup SPL (X8620200) | EACH | 3 | $8,230.08 | $12,600 |
| 22 | FOCC62.5/125 MM12SM24 (X8710024) | LF | 4,609 | $5.88 | $2.15 |
| 23 | Accessible ped signal (X8760200) | EACH | 25 | $2,587.21 | $2,600.00 |
| 24 | Conc FDN TY A 12D (X8780012) | LF | 56 | $374.35 | $260.00 |
| 25 | Vid veh det sys SN AP (X8891009) | EACH | 3 | $13,183 | $18,000 |
| 26 | Temp TR sig instal SP (X8900100) | EACH | 4 | $20,494 | $41,000 |
| 27 | Construction layout (Z0013798) | LS | 1 | $35,323 | $10,000 |
| 28 | Drill-grout #6 T-bar (Z0018911) | EACH | 427 | $50.46 | $25.00 |
| 29 | Lum sfty CBL assembly (Z0033020) | EACH | 2 | $384.73 | $160.00 |
| 30 | Temp TR signal timing (Z0073510) | EACH | 6 | $672.82 | $400.00 |
| 31 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 |
| 32 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 |
| 33 | Earth excavation (20200100) | CY | 121 | $210.26 | $100.00 |
| 34 | Topsoil F & P 4 (21101615) | SY | 50 | $40.37 | $24.00 |
| 35 | Topsoil F & P 12 (21101645) | SY | 43 | $111.01 | $66.00 |
| 36 | Seeding CL 2A (25000210) | ACRE | 0.01 | $151,384 | $90,000 |
| 37 | Nitrogen fert nutr (25000400) | LB | 1 | $20.18 | $12.00 |
| 38 | Phosphorus fert nutr (25000500) | LB | 1 | $20.18 | $12.00 |
| 39 | Potassium fert nutr (25000600) | LB | 1 | $20.18 | $12.00 |
| 40 | Erosion contr blanket (25100630) | SY | 50 | $33.64 | $20.00 |
| 41 | Temp eros contr seed (28000250) | LB | 1 | $84.10 | $50.00 |
| 42 | Inlet filters (28000510) | EACH | 12 | $504.61 | $300.00 |
| 43 | Sub gran mat B 2 (31101180) | SY | 508 | $21.03 | $4.00 |
| 44 | Sub gran mat B 8 (31101600) | SY | 494 | $42.05 | $16.00 |
| 45 | PCC bse cse 10 (35300500) | SY | 294 | $159.79 | $70.00 |
| 46 | Bit matls PR CT (40600275) | LB | 666 | $0.02 | $0.10 |
| 47 | Bit matls tack CT (40600290) | LB | 67 | $0.02 | $0.10 |
| 48 | HMA SC IL-9.5 D N70 (40604062) | TON | 34 | $1,261.53 | $2,000.00 |
| 49 | PC conc sidewalk 5 (42400200) | SF | 3,067 | $63.08 | $17.50 |
| 50 | Detectable warnings (42400800) | SF | 400 | $75.69 | $40.00 |
| 51 | Pavement rem (44000100) | SY | 410 | $159.79 | $20.00 |
| 52 | Comb curb gutter rem (44000500) | LF | 613 | $33.64 | $50.00 |
| 53 | Sidewalk rem (44000600) | SF | 3,717 | $6.73 | $5.00 |
| 54 | Form liner tex surf (50300285) | SF | 100 | $168.20 | $20.00 |
| 55 | CB adjust (60250200) | EACH | 4 | $1,009.22 | $500.00 |
| 56 | Man adjust (60255500) | EACH | 5 | $1,009.22 | $500.00 |
| 57 | Inlets adjust (60260100) | EACH | 1 | $1,009.22 | $500.00 |
| 58 | Conc curb TB (60600605) | LF | 424 | $126.15 | $89.00 |
| 59 | Comb CC&G TB6.12 (60603800) | LF | 700 | $109.33 | $109.00 |
| 60 | Comb CC&G TY B-6.24 (60605000) | LF | 8 | $252.31 | $119.00 |
| 61 | Conc median surf 4 (60618300) | SF | 65 | $42.05 | $18.00 |
| 62 | Corrugated med (60624600) | SF | 60 | $148.26 | $75.00 |
| 63 | Non SPL waste disposl (66900200) | CY | 5 | $616.03 | $60.00 |
| 64 | Soil disposal analy (66900530) | EACH | 2 | $1,345.63 | $800.00 |
| 65 | Reg sub P-const plan (66901001) | LS | 1 | $8,410.20 | $5,000.00 |
| 66 | Reg sub F con report (66901003) | LS | 1 | $841.02 | $500.00 |
| 67 | Reg sub mon (66901006) | CAL DAY | 160 | $1,143.79 | $680.00 |
| 68 | Mobilization (67100100) | LS | 1 | $834,048 | $264,046 |
| 69 | TR cont & prot 701602 (70102632) | LS | 1 | $17,012 | $100.00 |
| 70 | TR cont & prot 701701 (70102635) | LS | 1 | $50,871 | $25,000 |
| 71 | TR cont & prot 701801 (70102640) | LS | 1 | $15,369 | $100.00 |
| 72 | Changeable message SN (70107025) | CAL DAY | 120 | $176.61 | $35.00 |
| 73 | Sign panel T1 (72000100) | SF | 260 | $102.44 | $37.50 |
| 74 | Sign panel T2 (72000200) | SF | 152 | $123.63 | $45.00 |
| 75 | Reloc sign panel T1 (72400710) | SF | 45 | $17.66 | $25.00 |
| 76 | Teles STL sin support (72800100) | LF | 22 | $105.97 | $25.00 |
| 77 | THPL PVT MK LTR & sym (78000100) | SF | 75 | $12.04 | $6.95 |
| 78 | THPL PVT MK line 4 (78000200) | LF | 440 | $2.77 | $1.60 |
| 79 | THPL PVT MK line 6 (78000400) | LF | 650 | $3.29 | $1.90 |
| 80 | THPL PVT MK line 12 (78000600) | LF | 1,735 | $5.75 | $3.32 |
| 81 | THPL PVT MK line 24 (78000650) | LF | 350 | $12.82 | $7.40 |
| 82 | PVT MKG rem WTR blast (78300202) | SF | 1,530 | $6.32 | $3.65 |
| 83 | Undrgrd C galvs 2 (81028200) | LF | 3,405 | $23.05 | $100.00 |
| 84 | Undrgrd C galvs 3 (81028220) | LF | 827 | $78.55 | $150.00 |
| 85 | Undrgrd C galvs 4 (81028240) | LF | 1,173 | $89.66 | $175.00 |
| 86 | Handhole (81400100) | EACH | 16 | $2,574.17 | $6,200.00 |
| 87 | HD handhole (81400200) | EACH | 5 | $4,265.22 | $8,400.00 |
| 88 | DBL handhole (81400300) | EACH | 4 | $6,439.03 | $10,300 |
| 89 | EC C XLP use 1C 10 (81702110) | LF | 274 | $1.61 | $3.00 |
| 90 | Main EX TR sig instal (85000200) | EACH | 7 | $10,603 | $5,000.00 |
| 91 | Transceiver - fib opt (86400100) | EACH | 3 | $5,229.01 | $4,700.00 |
| 92 | Elcbl C tracer 14 1C (87300925) | LF | 4,609 | $0.29 | $0.25 |
| 93 | Elcbl C signal 14 2C (87301215) | LF | 3,503 | $1.67 | $3.00 |
| 94 | Elcbl C signal 14 3C (87301225) | LF | 8,439 | $1.90 | $1.50 |
| 95 | Elcbl C signal 14 5C (87301245) | LF | 7,777 | $2.50 | $2.00 |
| 96 | Elcbl C signal 14 7C (87301255) | LF | 3,963 | $2.99 | $2.50 |
| 97 | Elcbl C lead 14 1PR (87301305) | LF | 3,394 | $1.94 | $2.00 |
| 98 | Elcbl C serv 6 2C (87301805) | LF | 426 | $4.55 | $20.00 |
| 99 | Elcbl C egrdc 6 1C (87301900) | LF | 4,440 | $2.76 | $2.00 |
| 100 | TS post galvs 16 (87502500) | EACH | 7 | $3,154.32 | $4,100.00 |
| 101 | S maa & P 24 (87700160) | EACH | 2 | $14,324 | $18,400 |
| 102 | S maa & P 30 (87700190) | EACH | 1 | $17,038 | $20,800 |
| 103 | S maa & P 36 (87700220) | EACH | 3 | $19,598 | $23,300 |
| 104 | S maa & P 38 (87700230) | EACH | 2 | $19,731 | $24,800 |
| 105 | S maa & P 40 (87700240) | EACH | 1 | $20,047 | $25,000 |
| 106 | S maa & P 48 (87700280) | EACH | 1 | $22,954 | $27,800 |
| 107 | S maa & P 50 (87700290) | EACH | 1 | $23,258 | $30,800 |
| 108 | S maa & P 52 (87700300) | EACH | 2 | $24,100 | $31,600 |
| 109 | Smaap dma 20 & 22 (87702206) | EACH | 1 | $22,040 | $28,500 |
| 110 | STL comb maa&P 44 (87702950) | EACH | 1 | $28,903 | $35,400 |
| 111 | STL comb maa&P 48 (87702970) | EACH | 1 | $30,940 | $37,400 |
| 112 | Conc FDN TY A (87800100) | LF | 40 | $421.50 | $340.00 |
| 113 | Conc FDN TY C (87800150) | LF | 12 | $1,140.25 | $930.00 |
| 114 | Conc FDN TY E 30D (87800400) | LF | 94 | $357.15 | $1,000.00 |
| 115 | Conc FDN TY E 36D (87800415) | LF | 70 | $471.80 | $1,200.00 |
| 116 | Drill EX handhole (87900200) | EACH | 12 | $596.25 | $840.00 |
| 117 | SH LED 1F 1S mam (88030010) | EACH | 2 | $765.27 | $750.00 |
| 118 | SH LED 1F 3S mam (88030020) | EACH | 32 | $1,121.86 | $1,090.00 |
| 119 | SH LED 1F 3S BM (88030050) | EACH | 9 | $897.58 | $870.00 |
| 120 | SH LED 1F 4S BM (88030070) | EACH | 11 | $1,131.95 | $1,090.00 |
| 121 | SH LED 1F 4S mam (88030080) | EACH | 14 | $1,478.05 | $1,320.00 |
| 122 | SH LED 1F 5S BM (88030100) | EACH | 2 | $1,263.15 | $1,210.00 |
| 123 | SH LED 1F 5S mam (88030110) | EACH | 4 | $1,647.93 | $1,500.00 |
| 124 | Ped SH LED 1F BM CDT (88102717) | EACH | 22 | $873.47 | $800.00 |
| 125 | TS backplate ret-refl (88200510) | EACH | 221 | $532.72 | $1,200.00 |
| 126 | Inductive loop detect (88500100) | EACH | 20 | $286.67 | $225.00 |
| 127 | Det loop T1 (88600100) | LF | 1,713 | $24.66 | $30.00 |
| 128 | Light detector (88700200) | EACH | 18 | $1,509.29 | $1,410.00 |
| 129 | Light detector amp (88700300) | EACH | 7 | $4,053.26 | $4,000.00 |
| 130 | Temp TR sig install (89000100) | EACH | 2 | $57,871 | $62,000 |
| 131 | Reloc EX TS equip (89501250) | EACH | 6 | $730.63 | $800.00 |
| 132 | Mod EX contr cab (89502210) | EACH | 5 | $2,236.97 | $1,070.00 |
| 133 | Rem elcbl FR con (89502300) | LF | 7,824 | $0.96 | $2.00 |
| 134 | Remov EX TS equip (89502375) | EACH | 13 | $1,901.78 | $34,000 |
| 135 | Remov EX handhole (89502380) | EACH | 14 | $615.94 | $800.00 |
| 136 | Remov EX DBL handhole (89502382) | EACH | 2 | $657.99 | $2,400.00 |
| 137 | Remov EX conc FDN (89502385) | EACH | 14 | $615.94 | $1,600.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of November 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.