IDOT contract 72A62 bid tabulation
. Let by Illinois DOT on November 7, 2025, Sangamon, District 06. 2 bids received; low bid $1,014,537 by William Charles Construction Company, LLC.
- Owner
- Illinois DOT
- Letting
- 07 NOV 2025
- Pay items
- 35
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | William Charles Construction Company, LLC | $1,014,537 | Low |
| 2 | Sangamo Construction Company | $1,157,627 | +14% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. William Charles Construction Company, LLC | 2. Sangamo Construction Company |
|---|---|---|---|---|---|
| 1 | Clearing special (X2010505) | LS | 1 | $5,500.00 | $11,230 |
| 2 | Rem atten base (X6431110) | EACH | 1 | $4,600.00 | $5,133.61 |
| 3 | Rem imp atten SM (X6431120) | EACH | 35 | $120.00 | $160.62 |
| 4 | TC-prot 701402 SPL (X7010208) | EACH | 2 | $42,650 | $75,096 |
| 5 | TR C-prot 701401 SPL (X7010805) | LS | 1 | $32,750 | $104,263 |
| 6 | Detour signing (X7200203) | LS | 1 | $26,750 | $25,977 |
| 7 | Furnished excavation (20400800) | CY | 115 | $100.00 | $126.51 |
| 8 | Seeding CL 2 (25000200) | ACRE | 0.20 | $9,150.00 | $9,677.55 |
| 9 | Nitrogen fert nutr (25000400) | LB | 19 | $10.00 | $10.58 |
| 10 | Phosphorus fert nutr (25000500) | LB | 19 | $10.00 | $10.58 |
| 11 | Potassium fert nutr (25000600) | LB | 19 | $10.00 | $10.58 |
| 12 | Mulch method 2 (25100115) | ACRE | 0.20 | $9,150.00 | $9,677.55 |
| 13 | Inlet & pipe protect (28000500) | EACH | 2 | $850.00 | $236.38 |
| 14 | Sub gran mat C (31101900) | TON | 23 | $135.00 | $148.45 |
| 15 | Base cse widening 12 (35650520) | SY | 27 | $435.00 | $371.70 |
| 16 | Pavement rem (44000100) | SY | 6 | $950.00 | $282.24 |
| 17 | Paved SHLD removal (44004250) | SY | 39 | $135.00 | $241.82 |
| 18 | Agg wedge SHLD type B (48102100) | TON | 5 | $525.00 | $150.06 |
| 19 | Rem exist struct (50100100) | EACH | 1 | $527,250 | $483,866 |
| 20 | Slope wall remov (50104650) | SY | 240 | $65.00 | $38.10 |
| 21 | Protective shield (50157300) | SY | 201 | $0.10 | $1.00 |
| 22 | SPBGR TY A 6FT posts (63000001) | LF | 121 | $53.25 | $56.32 |
| 23 | Guardrail remov (63200310) | LF | 100 | $32.50 | $34.37 |
| 24 | CH LK fence 6 (66400305) | LF | 75 | $65.00 | $68.75 |
| 25 | Engr field office A (67000400) | CAL MO | 6 | $5,400.00 | $3,123.07 |
| 26 | Mobilization (67100100) | LS | 1 | $60,000 | $68,300 |
| 27 | Traf cont-prot 701411 (70100420) | EACH | 2 | $750.00 | $9,686.33 |
| 28 | Traf cont-prot 701451 (70100820) | LS | 1 | $7,285.00 | $8,010.98 |
| 29 | Changeable message SN (70107025) | CAL DAY | 700 | $75.00 | $125.88 |
| 30 | Temp conc barrier (70400100) | LF | 1,350 | $51.00 | $36.59 |
| 31 | Imp attn temp FRN TL3 (70600260) | EACH | 4 | $6,200.00 | $11,192 |
| 32 | Sign panel T1 (72000100) | SF | 27 | $36.25 | $38.34 |
| 33 | Sign panel T2 (72000200) | SF | 20 | $17.75 | $18.77 |
| 34 | Teles STL sin support (72800100) | LF | 176 | $19.25 | $20.36 |
| 35 | Grdrail ref type A (78200005) | EACH | 6 | $12.00 | $12.69 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of November 7, 2025. Compiled by Mirage Metrics.