IDOT contract 93847 bid tabulation
Pittsfield, section 24-00037-00-RS. Let by Illinois DOT on November 7, 2025, Pike, District 06. 2 bids received; low bid $5,451,649 by Rees Construction Company of Quincy.
- Owner
- Illinois DOT
- Letting
- 07 NOV 2025
- Pay items
- 124
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Rees Construction Company of Quincy | $5,451,649 | Low |
| 2 | Hood Construction Group Midwest | $7,038,260 | +29% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Rees Construction Company of Quincy | 2. Hood Construction Group Midwest |
|---|---|---|---|---|---|
| 1 | T-acer sacr GM 2-1/2 (A2001820) | EACH | 1 | $682.50 | $1,725.00 |
| 2 | T-carp carol 2-1/2 (A2002520) | EACH | 2 | $682.50 | $1,725.00 |
| 3 | T-taxodi dis SB 3 (A2007724) | EACH | 2 | $735.00 | $1,725.00 |
| 4 | P PL ornament T gal P (K0012990) | UNIT | 0.78 | $315.00 | $300.00 |
| 5 | P PL prairie TY gal P (K0013020) | UNIT | 0.84 | $315.00 | $300.00 |
| 6 | Street clock (XX008870) | EACH | 1 | $23,489 | $16,000 |
| 7 | Landscaping planter (X0325495) | EACH | 15 | $1,700.00 | $817.00 |
| 8 | Ornam light unit comp (X0326654) | EACH | 25 | $8,211.00 | $9,500.00 |
| 9 | Abandon exist utls (X0327547) | LS | 1 | $45,000 | $69,000 |
| 10 | Trash receptacles (X0327997) | EACH | 5 | $2,100.00 | $2,067.00 |
| 11 | Luminaire replacement SPL (X1400403) | EACH | 13 | $2,226.00 | $2,500.00 |
| 12 | Lighting assembly SPL (X1400431) | EACH | 11 | $17,889 | $17,600 |
| 13 | Stamp col PCC SDWLK 5 (X1700067) | SF | 7,556 | $33.00 | $29.00 |
| 14 | Topsoil F & P SPL (X2110100) | CY | 276 | $60.00 | $163.00 |
| 15 | Temp access- priv ent (X4021000) | EACH | 60 | $675.00 | $568.00 |
| 16 | Temp access- com ent (X4022000) | EACH | 13 | $1,100.00 | $718.00 |
| 17 | Retaining wall SPL (X5220090) | SF | 88 | $153.00 | $322.00 |
| 18 | Water main encasememt (X5610020) | LF | 162 | $168.00 | $350.00 |
| 19 | Water main abandon (X5610675) | EACH | 1 | $28,000 | $10,939 |
| 20 | WM line stop 6 (X5610746) | EACH | 6 | $7,800.00 | $12,000 |
| 21 | WM line stop 8 (X5610748) | EACH | 4 | $8,800.00 | $14,000 |
| 22 | Fire hydrant complete (X5640175) | EACH | 5 | $7,800.00 | $4,810.00 |
| 23 | Conc curb TB SPL (X6061005) | LF | 36 | $100.00 | $72.00 |
| 24 | Ornamental fence (X6640618) | LF | 192 | $147.00 | $204.00 |
| 25 | Traf cont & prot SPL (X7010216) | LS | 1 | $65,000 | $175,000 |
| 26 | Teles STL sin sup SPL (X7280105) | LF | 441 | $60.00 | $55.00 |
| 27 | Decorative sign post (X7290004) | EACH | 7 | $7,100.10 | $5,600.00 |
| 28 | Light controller SPL (X8250505) | EACH | 1 | $19,110 | $19,700 |
| 29 | Conc FDN SPL (X8780105) | EACH | 1 | $1,995.00 | $2,335.00 |
| 30 | Benches (Z0003850) | EACH | 6 | $2,400.00 | $2,487.00 |
| 31 | Bicycle racks (Z0003855) | EACH | 2 | $1,000.00 | $1,362.00 |
| 32 | Concrete steps (Z0012450) | CY | 8.50 | $7,800.00 | $2,335.00 |
| 33 | Construction layout (Z0013798) | LS | 1 | $27,000 | $114,000 |
| 34 | Storm sew WM req 12 (Z0056608) | LF | 1,585 | $175.00 | $196.00 |
| 35 | Trainees (Z0076600) | HR | 2,000 | $0.80 | $0.80 |
| 36 | Trainees TPG (Z0076604) | HR | 2,000 | $15.00 | $15.00 |
| 37 | Trench backfill (20800150) | CY | 625 | $88.00 | $84.00 |
| 38 | Seeding CL 1B (25000115) | ACRE | 0.25 | $13,650 | $55,000 |
| 39 | Nitrogen fert nutr (25000400) | LB | 23 | $10.50 | $10.00 |
| 40 | Phosphorus fert nutr (25000500) | LB | 23 | $10.50 | $10.00 |
| 41 | Potassium fert nutr (25000600) | LB | 23 | $10.50 | $10.00 |
| 42 | Erosion contr blanket (25100630) | SY | 1,210 | $4.46 | $8.00 |
| 43 | Temp eros contr seed (28000250) | LB | 25 | $10.50 | $17.00 |
| 44 | Perimeter eros bar (28000400) | LF | 1,200 | $4.46 | $5.00 |
| 45 | Inlet & pipe protect (28000500) | EACH | 24 | $262.50 | $215.00 |
| 46 | PCC bse cse 8 (35300300) | SY | 2,966 | $145.00 | $146.00 |
| 47 | Preparation of base (35800100) | SY | 4,101 | $10.00 | $10.00 |
| 48 | Agg base repair (35800200) | TON | 1,389 | $39.00 | $64.00 |
| 49 | Bit matls tack CT (40600290) | LB | 7,975 | $0.95 | $3.00 |
| 50 | Temporary ramp (40600990) | SY | 216 | $166.78 | $22.00 |
| 51 | HMA BC IL-9.5FG N50 (40602965) | TON | 1,290 | $166.78 | $195.00 |
| 52 | HMA SC IL-9.5 C N50 (40604050) | TON | 993 | $180.14 | $200.00 |
| 53 | Protective coat (42001300) | SY | 4,856 | $5.00 | $3.00 |
| 54 | PCC driveway pavt 8 (42300400) | SY | 291 | $158.00 | $192.00 |
| 55 | PC conc sidewalk 4 (42400100) | SF | 30,530 | $18.00 | $25.00 |
| 56 | Detectable warnings (42400800) | SF | 393 | $70.00 | $71.00 |
| 57 | Pavement rem (44000100) | SY | 5,644 | $22.00 | $21.00 |
| 58 | HMA surf rem 1 3/4 (44000156) | SY | 8,555 | $8.29 | $10.00 |
| 59 | Drive pavement rem (44000200) | SY | 125 | $18.00 | $14.00 |
| 60 | Comb curb gutter rem (44000500) | LF | 1,974 | $16.00 | $14.00 |
| 61 | Sidewalk rem (44000600) | SF | 29,229 | $4.00 | $7.00 |
| 62 | Pavt patch T1 8 (44200089) | SY | 5 | $180.00 | $402.00 |
| 63 | Pavt patch T2 8 (44200094) | SY | 153 | $170.00 | $376.00 |
| 64 | Pavt patch T3 8 (44200099) | SY | 41 | $170.00 | $342.00 |
| 65 | Pavt patch T4 8 (44200101) | SY | 188 | $165.00 | $340.00 |
| 66 | Pipe handrail (50901760) | LF | 261 | $132.30 | $297.00 |
| 67 | Storm sewer rem 8 (55100300) | LF | 26 | $19.00 | $60.00 |
| 68 | Storm sewer rem 10 (55100400) | LF | 383 | $19.00 | $60.00 |
| 69 | Storm sewer rem 12 (55100500) | LF | 448 | $19.00 | $60.00 |
| 70 | Water main 8 (56100700) | LF | 2,070 | $178.00 | $354.00 |
| 71 | Water valves 8 (56105000) | EACH | 11 | $3,900.00 | $4,463.00 |
| 72 | Tap valve & sleeve 6 (56108800) | EACH | 1 | $8,800.00 | $11,000 |
| 73 | Tap valve & sleeve 10 (56109000) | EACH | 1 | $12,000 | $15,000 |
| 74 | Water serv line 1 (56200300) | LF | 654 | $260.00 | $120.00 |
| 75 | Water serv line 1 1/2 (56200500) | LF | 254 | $340.00 | $140.00 |
| 76 | Water serv line 2 (56200700) | LF | 86 | $300.00 | $160.00 |
| 77 | Adj san sewer 8 less (56300100) | LF | 100 | $115.00 | $300.00 |
| 78 | Adj san sewer over 8 (56300200) | LF | 100 | $120.00 | $365.00 |
| 79 | Fire hydnts to BE rem (56400500) | EACH | 5 | $800.00 | $2,700.00 |
| 80 | Dom met VLTS (56500500) | EACH | 15 | $600.00 | $4,030.00 |
| 81 | Man TA 4 dia T1F CL (60218400) | EACH | 4 | $6,800.00 | $6,385.00 |
| 82 | Man TA 4 dia T3F&G (60218500) | EACH | 2 | $7,000.00 | $6,453.00 |
| 83 | Inlets TA T1F OL (60234200) | EACH | 1 | $3,200.00 | $2,570.00 |
| 84 | Inlets TA T3F&G (60235700) | EACH | 16 | $3,400.00 | $2,570.00 |
| 85 | Inlets TB T3F&G (60240220) | EACH | 5 | $4,000.00 | $3,223.00 |
| 86 | Man adjust (60255500) | EACH | 3 | $900.00 | $1,016.00 |
| 87 | Remov manholes (60500040) | EACH | 2 | $800.00 | $788.00 |
| 88 | Remov inlets (60500060) | EACH | 6 | $800.00 | $788.00 |
| 89 | Comb CC&G TB6.18 (60604400) | LF | 4,084 | $46.00 | $65.00 |
| 90 | Storm sewer spec 4 (61139800) | LF | 100 | $90.00 | $89.00 |
| 91 | Storm sewer spec 6 (61139900) | LF | 100 | $100.00 | $102.00 |
| 92 | Non SPL waste disposl (66900200) | CY | 7 | $440.00 | $500.00 |
| 93 | Soil disposal analy (66900530) | EACH | 1 | $1,540.00 | $1,725.00 |
| 94 | Reg sub P-const plan (66901001) | LS | 1 | $2,420.00 | $2,875.00 |
| 95 | Reg sub F con report (66901003) | LS | 1 | $2,420.00 | $2,875.00 |
| 96 | Reg sub mon (66901006) | CAL DAY | 2 | $1,018.00 | $1,150.00 |
| 97 | Mobilization (67100100) | LS | 1 | $156,506 | $543,000 |
| 98 | Short term pavt mking (70300100) | LF | 1,428 | $1.62 | $3.00 |
| 99 | SHRT TRM pavt MK rem (70300150) | SF | 476 | $5.00 | $3.00 |
| 100 | Temp PVT MK LTR & sym paint (70300211) | SF | 296 | $3.15 | $3.20 |
| 101 | Temp PVT MK line 5 - paint (70300231) | LF | 7,457 | $1.01 | $1.05 |
| 102 | Temp PVT MK line 6 - paint (70300241) | LF | 459 | $1.21 | $1.30 |
| 103 | Temp PVT MK line 8 - paint (70300251) | LF | 4,000 | $1.62 | $1.70 |
| 104 | Temp PVT MK line 12 - paint (70300261) | LF | 3,078 | $2.57 | $2.70 |
| 105 | Temp PVT MK line 24 - paint (70300281) | LF | 89 | $4.98 | $5.25 |
| 106 | Sign panel T1 (72000100) | SF | 308 | $48.00 | $55.00 |
| 107 | Mod ureth PM LTR-sym (78009000) | SF | 296 | $10.50 | $11.00 |
| 108 | Mod ureth PM line 5 (78009005) | LF | 7,457 | $4.26 | $4.50 |
| 109 | Mod ureth PM line 6 (78009006) | LF | 459 | $5.12 | $5.30 |
| 110 | Mod ureth PM line 8 (78009008) | LF | 4,000 | $6.82 | $7.00 |
| 111 | Mod ureth PM line 12 (78009012) | LF | 3,078 | $10.23 | $11.00 |
| 112 | Mod ureth PM line 24 (78009024) | LF | 89 | $20.47 | $21.00 |
| 113 | PVT MKG rem WTR blast (78300202) | SF | 11,777 | $2.20 | $2.50 |
| 114 | Elect serv install (80400100) | EACH | 1 | $4,410.00 | $2,500.00 |
| 115 | Undrgrd C PVC 1 1/4 (81028330) | LF | 627 | $17.01 | $22.00 |
| 116 | Undrgrd C PVC 1 1/2 (81028340) | LF | 5,346 | $18.37 | $19.00 |
| 117 | Undrgrd C PVC 2 (81028350) | LF | 100 | $42.00 | $27.00 |
| 118 | Undrgrd C PVC 4 (81028390) | LF | 100 | $52.50 | $31.00 |
| 119 | Handhole C conc (81400730) | EACH | 8 | $3,360.00 | $1,400.00 |
| 120 | EC C XLP use 1C 6 (81702130) | LF | 14,378 | $2.52 | $2.50 |
| 121 | EC C XLP use 1C 4 (81702140) | LF | 4,056 | $3.41 | $3.30 |
| 122 | EC C XLP use 1C 2 (81702150) | LF | 116 | $6.30 | $5.00 |
| 123 | Rem LT unit salv (84200500) | EACH | 3 | $840.00 | $1,000.00 |
| 124 | Rem LT U no salv (84200600) | EACH | 18 | $955.50 | $1,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of November 7, 2025. Compiled by Mirage Metrics.