IDOT contract 78B54 bid tabulation

. Let by Illinois DOT on November 7, 2025, Jackson, District 09. 2 bids received; low bid $175,469 by E. T. Simonds Construction Company.

Owner
Illinois DOT
Letting
07 NOV 2025
Pay items
22
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1E. T. Simonds Construction Company$175,469Low
2Samron Midwest Contracting, Inc.$178,335+2.0%
IDOT contract 78B54: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. E. T. Simonds Construction Company2. Samron Midwest Contracting, Inc.
1Bit matls tack CT (40600290)LB3,706$0.01$0.01
2Long joint sealant (40600370)LF2,745$6.04$6.25
3Temporary ramp (40600990)SY24$107.48$0.01
4HMA BC IL-9.5FG N50 (40602965)TON385$88.07$110.00
5HMA SC IL-9.5FG C N50 (40604000)TON462$83.38$108.00
6Incidental HMA surf (40800050)TON27$319.19$465.00
7PC conc sidewalk 5 (42400200)SF80$30.31$25.00
8Detectable warnings (42400800)SF20$21.20$25.00
9HMA surf rem 1 1/2 (44000155)SY5,490$3.55$4.00
10Sidewalk rem (44000600)SF80$0.01$15.00
11CL D patch T1 6 (44201713)SY11$471.00$95.00
12CL D patch T2 6 (44201717)SY18$465.00$90.00
13Agg wedge SHLD type B (48102100)TON71$70.58$29.00
14Mobilization (67100100)LS1$19,708$10,500
15TR cont & prot 701501 (70102620)LS1$8,597.90$8,500.00
16TR cont & prot 701801 (70102640)LS1$0.01$750.00
17Changeable message SN (70107025)CAL DAY42$0.01$0.01
18Short term pavt mking (70300100)LF275$5.93$0.75
19SHRT TRM pavt MK rem (70300150)SF92$0.01$20.00
20Temp PVT MK line 4 - paint (70300221)LF686$0.01$0.01
21THPL PVT MK line 4 (78000200)LF686$6.38$6.05
22PVT MKG rem grinding (78300201)SF229$0.01$0.01
IDOT contract 78B54: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of November 7, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy