IDOT contract 46944 bid tabulation
. Let by Illinois DOT on November 7, 2025, Whiteside, District 02. 3 bids received; low bid $1,029,566 by Martin & Company Excavating.
- Owner
- Illinois DOT
- Letting
- 07 NOV 2025
- Pay items
- 65
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Martin & Company Excavating | $1,029,566 | Low |
| 2 | Civil Constructors, Inc. d/b/a/ Helm Civil | $1,193,271 | +16% |
| 3 | Brandt Construction Co. | $1,704,955 | +66% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Martin & Company Excavating | 2. Civil Constructors, Inc. d/b/a/ Helm Civil | 3. Brandt Construction Co. |
|---|---|---|---|---|---|---|
| 1 | Washout basin (X0326806) | LS | 1 | $500.00 | $1,700.00 | $3,250.00 |
| 2 | Conc wearing surf VD (X5030301) | SY | 372 | $215.00 | $160.00 | $350.00 |
| 3 | Traf bar term T6 mod (X6310187) | EACH | 1 | $9,000.00 | $8,116.00 | $9,150.00 |
| 4 | CH LK fence remov (X6640300) | LF | 16 | $12.00 | $9.80 | $65.00 |
| 5 | Traf cont & prot SPL (X7010216) | LS | 1 | $10,500 | $9,100.00 | $12,000 |
| 6 | Asb bearing pad remov (Z0001900) | EACH | 44 | $50.00 | $80.00 | $175.00 |
| 7 | STR rep con DP = < 5 (Z0012754) | SF | 17 | $240.00 | $322.00 | $900.00 |
| 8 | Construction layout (Z0013798) | LS | 1 | $3,500.00 | $7,000.00 | $16,000 |
| 9 | Earth excavation (20200100) | CY | 437 | $24.00 | $60.00 | $45.00 |
| 10 | Porous gran embank (20700220) | CY | 10 | $42.00 | $85.00 | $260.00 |
| 11 | Trench backfill (20800150) | CY | 18 | $42.00 | $30.00 | $75.00 |
| 12 | Topsoil F & P 4 (21101615) | SY | 876 | $5.00 | $11.00 | $17.00 |
| 13 | Seeding CL 1B (25000115) | ACRE | 0.20 | $11,000 | $10,000 | $11,250 |
| 14 | Nitrogen fert nutr (25000400) | LB | 20 | $2.00 | $1.00 | $1.15 |
| 15 | Phosphorus fert nutr (25000500) | LB | 20 | $2.00 | $1.00 | $1.15 |
| 16 | Potassium fert nutr (25000600) | LB | 20 | $2.00 | $1.00 | $1.15 |
| 17 | Mulch method 1 (25100105) | ACRE | 0.20 | $11,000 | $10,000 | $11,250 |
| 18 | Temp eros contr seed (28000250) | LB | 11 | $5.00 | $5.00 | $5.50 |
| 19 | Perimeter eros bar (28000400) | LF | 638 | $5.25 | $4.00 | $4.50 |
| 20 | Inlet filters (28000510) | EACH | 4 | $125.00 | $250.00 | $375.00 |
| 21 | Stone dump rip CL A3 (28100705) | SY | 18 | $65.00 | $72.00 | $98.00 |
| 22 | Filter fabric (28200200) | SY | 24 | $5.00 | $5.00 | $40.00 |
| 23 | Sub gran mat C 9 (31102600) | SY | 150 | $14.00 | $28.00 | $48.00 |
| 24 | Agg base cse A 12 (35101100) | SY | 730 | $19.00 | $22.00 | $40.00 |
| 25 | Agg surf cse A 6 (40200500) | SY | 180 | $10.00 | $17.00 | $25.00 |
| 26 | Bit matls PR CT (40600275) | LB | 1,643 | $1.00 | $1.00 | $1.00 |
| 27 | Bit matls tack CT (40600290) | LB | 730 | $1.00 | $0.60 | $1.00 |
| 28 | HMA surf rem butt JT (40600982) | SY | 31 | $25.00 | $15.00 | $118.00 |
| 29 | HMA BC IL-9.5 N50 (40602978) | TON | 57 | $170.00 | $120.00 | $235.00 |
| 30 | HMA SC IL-9.5FG C N50 (40604000) | TON | 57 | $180.00 | $120.00 | $300.00 |
| 31 | PC conc sidewalk 5 (42400200) | SF | 1,363 | $11.00 | $10.00 | $18.00 |
| 32 | Sidewalk rem (44000600) | SF | 1,376 | $2.00 | $2.00 | $2.00 |
| 33 | HMA shoulders 6 (48203021) | SY | 150 | $66.50 | $60.00 | $135.00 |
| 34 | Rem exist sup-STR (50101500) | EACH | 1 | $60,000 | $120,000 | $200,000 |
| 35 | Conc rem (50102400) | CY | 11.10 | $450.00 | $2,885.00 | $5,400.00 |
| 36 | Structure excavation (50200100) | CY | 20.40 | $60.00 | $70.00 | $100.00 |
| 37 | Conc struct (50300225) | CY | 33.70 | $1,250.00 | $1,600.00 | $3,300.00 |
| 38 | Conc sup-STR (50300255) | CY | 26.30 | $1,200.00 | $1,700.00 | $3,200.00 |
| 39 | P P conc DK BM 21 DP (50400405) | SF | 1,444 | $109.00 | $114.00 | $125.00 |
| 40 | P P conc DK BM 27 DP (50400505) | SF | 1,898 | $112.00 | $118.00 | $127.00 |
| 41 | Reinf bars, epoxy CTD (50800205) | LB | 14,230 | $2.90 | $3.10 | $3.50 |
| 42 | Bicycle railing (50901720) | LF | 160 | $350.00 | $343.00 | $380.00 |
| 43 | Parapet railing (50901750) | LF | 100 | $140.00 | $138.00 | $145.00 |
| 44 | Pipe handrail (50901760) | LF | 37 | $280.00 | $261.00 | $300.00 |
| 45 | Slope wall 4 (51100100) | SY | 70 | $120.00 | $530.00 | $685.00 |
| 46 | Name plates (51500100) | EACH | 1 | $1,350.00 | $980.00 | $1,375.00 |
| 47 | Pref JT strip seal (52000110) | LF | 66 | $400.00 | $258.00 | $400.00 |
| 48 | Metal FL end sec 15" (54262715) | EACH | 1 | $325.00 | $1,100.00 | $1,050.00 |
| 49 | Storm sew CL A 1 12 (550A0050) | LF | 48 | $90.00 | $97.00 | $138.00 |
| 50 | Storm sew CL B 2 15 (550B0360) | LF | 40 | $60.00 | $99.00 | $238.00 |
| 51 | Inlets TA T3V F&G (60235705) | EACH | 2 | $2,800.00 | $2,900.00 | $5,000.00 |
| 52 | Inlets TB T1F CL (60240215) | EACH | 1 | $3,900.00 | $2,900.00 | $7,300.00 |
| 53 | Inlets TB T3V F&G (60240222) | EACH | 2 | $4,100.00 | $3,100.00 | $5,750.00 |
| 54 | Comb CC&G TY B-6.24 (60605000) | LF | 82 | $60.00 | $69.00 | $85.00 |
| 55 | SPBGR TY A 6FT posts (63000001) | LF | 90 | $39.00 | $34.28 | $38.00 |
| 56 | SPBGR TY A 9FT posts (63000003) | LF | 80 | $47.00 | $43.16 | $48.00 |
| 57 | BCK SD prot of GRDRL (63000035) | LF | 235 | $25.00 | $22.11 | $25.00 |
| 58 | Traf bar term T5 (63100070) | EACH | 2 | $1,200.00 | $1,131.00 | $1,275.00 |
| 59 | Traf bar term T6 (63100085) | EACH | 1 | $4,600.00 | $4,417.00 | $4,975.00 |
| 60 | TR bar TRM T1 SPL tan (63100167) | EACH | 4 | $3,500.00 | $3,366.00 | $3,790.00 |
| 61 | Guardrail remov (63200310) | LF | 467 | $6.26 | $6.26 | $7.00 |
| 62 | Engr field office B (67000500) | CAL MO | 6 | $3,200.00 | $3,300.00 | $4,500.00 |
| 63 | Mobilization (67100100) | LS | 1 | $58,000 | $71,596 | $100,000 |
| 64 | Epoxy PVT MK line 4 (78005110) | LF | 420 | $10.00 | $9.15 | $30.00 |
| 65 | Polyurea PM T1 LN 4 (78008210) | LF | 903 | $10.50 | $9.85 | $14.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of November 7, 2025. Compiled by Mirage Metrics.