IDOT contract 61L73 bid tabulation
Project Number:, section 21-P4015-00-BT. Let by Illinois DOT on November 7, 2025, Will, District 01. 6 bids received; low bid $352,856 by D. Construction, Inc..
- Owner
- Illinois DOT
- Letting
- 07 NOV 2025
- Pay items
- 58
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D. Construction, Inc. | $352,856 | Low |
| 2 | Austin Tyler Construction, Inc. | $395,907 | +12% |
| 3 | Gallagher Asphalt Corporation | $431,771 | +22% |
| 4 | P. T. Ferro Construction Co. | $461,168 | +31% |
| 5 | Winninger Excavating | $509,578 | +44% |
| 6 | K-Five Construction Corporation | $619,823 | +76% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D. Construction, Inc. | 2. Austin Tyler Construction, Inc. | 3. Gallagher Asphalt Corporation | 4. P. T. Ferro Construction Co. | 5. Winninger Excavating | 6. K-Five Construction Corporation |
|---|---|---|---|---|---|---|---|---|---|
| 1 | T-catalpa spec 2-1/2 (A2002820) | EACH | 6 | $693.00 | $630.00 | $650.00 | $611.00 | $600.00 | $700.00 |
| 2 | T-lirioden tul 2-1/2 (A2005420) | EACH | 7 | $808.50 | $735.00 | $650.00 | $611.00 | $600.00 | $600.00 |
| 3 | T-quercus bicol 2 (A2006516) | EACH | 4 | $610.50 | $555.00 | $600.00 | $516.00 | $600.00 | $660.00 |
| 4 | T-quercus macr 2 (A2006716) | EACH | 3 | $616.00 | $560.00 | $600.00 | $516.00 | $650.00 | $660.00 |
| 5 | T-quercus rubra 2 (A2007116) | EACH | 3 | $610.50 | $555.00 | $600.00 | $516.00 | $650.00 | $660.00 |
| 6 | Washout basin (X0326806) | LS | 1 | $1,000.00 | $500.00 | $575.00 | $1.00 | $500.00 | $500.00 |
| 7 | Fold down bollards (X0350805) | EACH | 3 | $2,000.00 | $2,470.00 | $2,500.00 | $3,500.00 | $3,000.00 | $3,500.00 |
| 8 | Fence removal (X6640104) | LF | 20 | $25.00 | $8.00 | $35.90 | $150.00 | $5.00 | $150.00 |
| 9 | Temp info signing (X7200061) | SF | 129 | $25.00 | $35.00 | $26.00 | $24.00 | $24.00 | $24.00 |
| 10 | Stab constr entrance (Z0013797) | SY | 1,414 | $0.01 | $11.00 | $0.01 | $0.01 | $15.00 | $5.00 |
| 11 | Construction layout (Z0013798) | LS | 1 | $10,000 | $9,200.00 | $9,000.00 | $12,000 | $15,000 | $20,000 |
| 12 | Tree remov 6-15 (20100110) | UNIT | 116 | $24.20 | $22.00 | $23.75 | $22.00 | $22.00 | $21.30 |
| 13 | Tree remov over 15 (20100210) | UNIT | 348 | $30.80 | $28.00 | $30.25 | $28.00 | $33.00 | $23.00 |
| 14 | Temporary fence (20101000) | LF | 1,000 | $3.85 | $3.50 | $5.40 | $5.00 | $8.00 | $5.00 |
| 15 | Earth excavation (20200100) | CY | 2,431 | $25.00 | $40.00 | $46.50 | $40.00 | $55.00 | $70.00 |
| 16 | Rem & disp uns matl (20201200) | CY | 253 | $25.00 | $38.00 | $30.00 | $50.00 | $35.00 | $84.00 |
| 17 | Furnished excavation (20400800) | CY | 140 | $30.00 | $57.00 | $50.00 | $50.00 | $15.00 | $43.00 |
| 18 | Geotech fab F/GR stab (21001000) | SY | 758 | $4.00 | $2.00 | $4.75 | $3.50 | $2.00 | $1.50 |
| 19 | Topsoil exc & plac (21101505) | CY | 460 | $22.50 | $46.00 | $70.00 | $40.00 | $35.00 | $55.00 |
| 20 | Topsoil F & P 6 (21101625) | SY | 303 | $7.70 | $7.00 | $5.50 | $9.00 | $8.00 | $10.00 |
| 21 | Seeding CL 1 (25000100) | ACRE | 2 | $2,750.00 | $2,500.00 | $1,300.00 | $2,894.00 | $2,000.00 | $2,800.00 |
| 22 | Seeding CL 4A (25000312) | ACRE | 0.25 | $5,500.00 | $5,000.00 | $1,300.00 | $3,348.00 | $2,500.00 | $3,500.00 |
| 23 | Seeding CL 4B (25000314) | ACRE | 0.50 | $5,390.00 | $4,900.00 | $2,600.00 | $3,723.00 | $3,000.00 | $6,000.00 |
| 24 | Seeding CL 5B (25000324) | ACRE | 0.50 | $4,400.00 | $4,000.00 | $2,600.00 | $2,390.00 | $3,000.00 | $1,000.00 |
| 25 | Nitrogen fert nutr (25000400) | LB | 180 | $3.30 | $3.00 | $3.10 | $3.00 | $4.00 | $3.00 |
| 26 | Potassium fert nutr (25000600) | LB | 180 | $3.30 | $3.00 | $2.70 | $3.00 | $4.00 | $3.00 |
| 27 | Wildlife friendly ecb (25100645) | SY | 11,801 | $1.49 | $1.35 | $2.70 | $2.40 | $2.00 | $2.00 |
| 28 | Supple watering (25200200) | UNIT | 2 | $220.00 | $200.00 | $270.00 | $100.00 | $1.00 | $1.00 |
| 29 | Perimeter eros bar (28000400) | LF | 1,364 | $3.85 | $3.50 | $3.25 | $3.30 | $5.00 | $3.50 |
| 30 | Inlet filters (28000510) | EACH | 2 | $275.00 | $170.00 | $195.00 | $219.00 | $300.00 | $180.00 |
| 31 | Stone riprap CL A3 (28100105) | SY | 16 | $130.00 | $121.00 | $200.00 | $100.00 | $240.00 | $186.15 |
| 32 | Agg subgrade improve (30300001) | CY | 253 | $60.00 | $41.00 | $50.00 | $60.00 | $35.00 | $147.56 |
| 33 | Agg base cse B 8 (35102000) | SY | 2,083 | $16.00 | $13.00 | $18.00 | $21.00 | $25.00 | $40.65 |
| 34 | Bit matls PR CT (40600275) | LB | 4,055 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 35 | HMA SC IL-9.5 D N50 (40604060) | TON | 303 | $116.00 | $141.00 | $125.00 | $150.00 | $225.00 | $195.65 |
| 36 | PC conc sidewalk 5 (42400200) | SF | 480 | $10.00 | $12.00 | $15.00 | $20.00 | $20.00 | $19.00 |
| 37 | Detectable warnings (42400800) | SF | 76 | $30.00 | $34.00 | $22.00 | $25.00 | $30.00 | $55.00 |
| 38 | Pavement rem (44000100) | SY | 33 | $35.00 | $47.00 | $38.00 | $30.00 | $25.00 | $40.00 |
| 39 | Drive pavement rem (44000200) | SY | 31 | $20.00 | $28.00 | $40.00 | $30.00 | $15.00 | $100.00 |
| 40 | Comb curb gutter rem (44000500) | LF | 56 | $10.00 | $18.00 | $30.00 | $32.00 | $50.00 | $32.00 |
| 41 | Sidewalk rem (44000600) | SF | 131 | $5.00 | $3.00 | $11.00 | $4.50 | $8.00 | $6.50 |
| 42 | Pipe culvert remov (50105220) | LF | 42 | $10.00 | $19.00 | $13.70 | $75.00 | $30.00 | $12.70 |
| 43 | P cul CL C 1 12 (542C0217) | LF | 109 | $50.00 | $89.00 | $50.00 | $130.00 | $65.00 | $50.25 |
| 44 | P cul CL C 1 15 (542C0220) | LF | 21 | $55.00 | $97.00 | $60.00 | $130.00 | $100.00 | $58.75 |
| 45 | Steel FL end sec 12" (54261712) | EACH | 7 | $175.00 | $620.00 | $150.00 | $640.00 | $650.00 | $172.70 |
| 46 | Steel FL end sec 15" (54261715) | EACH | 4 | $200.00 | $790.00 | $165.00 | $660.00 | $615.00 | $192.65 |
| 47 | CB TC T8G (60207605) | EACH | 2 | $1,400.00 | $1,570.00 | $2,500.00 | $1,700.00 | $1,550.00 | $1,440.00 |
| 48 | Man adjust (60255500) | EACH | 1 | $1,000.00 | $865.00 | $400.00 | $1,000.00 | $500.00 | $550.00 |
| 49 | Comb CC&G TB6.12 (60603800) | LF | 56 | $45.00 | $57.00 | $90.00 | $80.00 | $120.00 | $76.00 |
| 50 | Mobilization (67100100) | LS | 1 | $20,556 | $18,000 | $25,800 | $25,000 | $26,000 | $37,000 |
| 51 | TR cont & prot 701501 (70102620) | LS | 1 | $0.01 | $2,500.00 | $7,999.99 | $25,000 | $4,500.00 | $10,500 |
| 52 | TR cont & prot 701801 (70102640) | LS | 1 | $33,000 | $500.00 | $100.00 | $100.00 | $125.00 | $100.00 |
| 53 | Sign panel T1 (72000100) | SF | 69 | $30.25 | $30.00 | $29.00 | $27.50 | $35.00 | $27.50 |
| 54 | Metal post TY A (72900100) | LF | 75 | $18.15 | $25.00 | $17.80 | $16.50 | $20.00 | $16.50 |
| 55 | THPL PVT MK line 12 (78000600) | LF | 327 | $5.34 | $12.00 | $5.20 | $4.85 | $5.00 | $4.85 |
| 56 | THPL PVT MK line 24 (78000650) | LF | 34 | $9.24 | $26.00 | $9.00 | $8.40 | $9.00 | $8.40 |
| 57 | Paint PVT MK line 4 (78001110) | LF | 1,622 | $2.53 | $2.33 | $2.45 | $2.30 | $3.00 | $2.30 |
| 58 | PVT MKG rem grinding (78300201) | SF | 69 | $8.97 | $5.00 | $2.70 | $8.15 | $9.00 | $8.15 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of November 7, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.