IDOT contract 61L73 bid tabulation

Project Number:, section 21-P4015-00-BT. Let by Illinois DOT on November 7, 2025, Will, District 01. 6 bids received; low bid $352,856 by D. Construction, Inc..

Owner
Illinois DOT
Letting
07 NOV 2025
Pay items
58
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1D. Construction, Inc.$352,856Low
2Austin Tyler Construction, Inc.$395,907+12%
3Gallagher Asphalt Corporation$431,771+22%
4P. T. Ferro Construction Co.$461,168+31%
5Winninger Excavating$509,578+44%
6K-Five Construction Corporation$619,823+76%
IDOT contract 61L73: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. D. Construction, Inc.2. Austin Tyler Construction, Inc.3. Gallagher Asphalt Corporation4. P. T. Ferro Construction Co.5. Winninger Excavating6. K-Five Construction Corporation
1T-catalpa spec 2-1/2 (A2002820)EACH6$693.00$630.00$650.00$611.00$600.00$700.00
2T-lirioden tul 2-1/2 (A2005420)EACH7$808.50$735.00$650.00$611.00$600.00$600.00
3T-quercus bicol 2 (A2006516)EACH4$610.50$555.00$600.00$516.00$600.00$660.00
4T-quercus macr 2 (A2006716)EACH3$616.00$560.00$600.00$516.00$650.00$660.00
5T-quercus rubra 2 (A2007116)EACH3$610.50$555.00$600.00$516.00$650.00$660.00
6Washout basin (X0326806)LS1$1,000.00$500.00$575.00$1.00$500.00$500.00
7Fold down bollards (X0350805)EACH3$2,000.00$2,470.00$2,500.00$3,500.00$3,000.00$3,500.00
8Fence removal (X6640104)LF20$25.00$8.00$35.90$150.00$5.00$150.00
9Temp info signing (X7200061)SF129$25.00$35.00$26.00$24.00$24.00$24.00
10Stab constr entrance (Z0013797)SY1,414$0.01$11.00$0.01$0.01$15.00$5.00
11Construction layout (Z0013798)LS1$10,000$9,200.00$9,000.00$12,000$15,000$20,000
12Tree remov 6-15 (20100110)UNIT116$24.20$22.00$23.75$22.00$22.00$21.30
13Tree remov over 15 (20100210)UNIT348$30.80$28.00$30.25$28.00$33.00$23.00
14Temporary fence (20101000)LF1,000$3.85$3.50$5.40$5.00$8.00$5.00
15Earth excavation (20200100)CY2,431$25.00$40.00$46.50$40.00$55.00$70.00
16Rem & disp uns matl (20201200)CY253$25.00$38.00$30.00$50.00$35.00$84.00
17Furnished excavation (20400800)CY140$30.00$57.00$50.00$50.00$15.00$43.00
18Geotech fab F/GR stab (21001000)SY758$4.00$2.00$4.75$3.50$2.00$1.50
19Topsoil exc & plac (21101505)CY460$22.50$46.00$70.00$40.00$35.00$55.00
20Topsoil F & P 6 (21101625)SY303$7.70$7.00$5.50$9.00$8.00$10.00
21Seeding CL 1 (25000100)ACRE2$2,750.00$2,500.00$1,300.00$2,894.00$2,000.00$2,800.00
22Seeding CL 4A (25000312)ACRE0.25$5,500.00$5,000.00$1,300.00$3,348.00$2,500.00$3,500.00
23Seeding CL 4B (25000314)ACRE0.50$5,390.00$4,900.00$2,600.00$3,723.00$3,000.00$6,000.00
24Seeding CL 5B (25000324)ACRE0.50$4,400.00$4,000.00$2,600.00$2,390.00$3,000.00$1,000.00
25Nitrogen fert nutr (25000400)LB180$3.30$3.00$3.10$3.00$4.00$3.00
26Potassium fert nutr (25000600)LB180$3.30$3.00$2.70$3.00$4.00$3.00
27Wildlife friendly ecb (25100645)SY11,801$1.49$1.35$2.70$2.40$2.00$2.00
28Supple watering (25200200)UNIT2$220.00$200.00$270.00$100.00$1.00$1.00
29Perimeter eros bar (28000400)LF1,364$3.85$3.50$3.25$3.30$5.00$3.50
30Inlet filters (28000510)EACH2$275.00$170.00$195.00$219.00$300.00$180.00
31Stone riprap CL A3 (28100105)SY16$130.00$121.00$200.00$100.00$240.00$186.15
32Agg subgrade improve (30300001)CY253$60.00$41.00$50.00$60.00$35.00$147.56
33Agg base cse B 8 (35102000)SY2,083$16.00$13.00$18.00$21.00$25.00$40.65
34Bit matls PR CT (40600275)LB4,055$0.01$0.01$0.01$0.01$0.01$0.01
35HMA SC IL-9.5 D N50 (40604060)TON303$116.00$141.00$125.00$150.00$225.00$195.65
36PC conc sidewalk 5 (42400200)SF480$10.00$12.00$15.00$20.00$20.00$19.00
37Detectable warnings (42400800)SF76$30.00$34.00$22.00$25.00$30.00$55.00
38Pavement rem (44000100)SY33$35.00$47.00$38.00$30.00$25.00$40.00
39Drive pavement rem (44000200)SY31$20.00$28.00$40.00$30.00$15.00$100.00
40Comb curb gutter rem (44000500)LF56$10.00$18.00$30.00$32.00$50.00$32.00
41Sidewalk rem (44000600)SF131$5.00$3.00$11.00$4.50$8.00$6.50
42Pipe culvert remov (50105220)LF42$10.00$19.00$13.70$75.00$30.00$12.70
43P cul CL C 1 12 (542C0217)LF109$50.00$89.00$50.00$130.00$65.00$50.25
44P cul CL C 1 15 (542C0220)LF21$55.00$97.00$60.00$130.00$100.00$58.75
45Steel FL end sec 12" (54261712)EACH7$175.00$620.00$150.00$640.00$650.00$172.70
46Steel FL end sec 15" (54261715)EACH4$200.00$790.00$165.00$660.00$615.00$192.65
47CB TC T8G (60207605)EACH2$1,400.00$1,570.00$2,500.00$1,700.00$1,550.00$1,440.00
48Man adjust (60255500)EACH1$1,000.00$865.00$400.00$1,000.00$500.00$550.00
49Comb CC&G TB6.12 (60603800)LF56$45.00$57.00$90.00$80.00$120.00$76.00
50Mobilization (67100100)LS1$20,556$18,000$25,800$25,000$26,000$37,000
51TR cont & prot 701501 (70102620)LS1$0.01$2,500.00$7,999.99$25,000$4,500.00$10,500
52TR cont & prot 701801 (70102640)LS1$33,000$500.00$100.00$100.00$125.00$100.00
53Sign panel T1 (72000100)SF69$30.25$30.00$29.00$27.50$35.00$27.50
54Metal post TY A (72900100)LF75$18.15$25.00$17.80$16.50$20.00$16.50
55THPL PVT MK line 12 (78000600)LF327$5.34$12.00$5.20$4.85$5.00$4.85
56THPL PVT MK line 24 (78000650)LF34$9.24$26.00$9.00$8.40$9.00$8.40
57Paint PVT MK line 4 (78001110)LF1,622$2.53$2.33$2.45$2.30$3.00$2.30
58PVT MKG rem grinding (78300201)SF69$8.97$5.00$2.70$8.15$9.00$8.15
IDOT contract 61L73: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of November 7, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy