IDOT contract 61L29 bid tabulation
Bloomingdale, section 20-00073-00-RS. Let by Illinois DOT on April 25, 2025, Dupage, District 01. 10 bids received; low bid $1,534,281 by Builders Paving, LLC.
- Owner
- Illinois DOT
- Letting
- 25 APR 2025
- Pay items
- 43
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Builders Paving, LLC | $1,534,281 | Low |
| 2 | A Lamp Concrete Contractors, Inc. | $1,584,176 | +3.0% |
| 3 | Plote Construction, Inc. | $1,617,748 | +5.0% |
| 4 | Davis Concrete Construction Co. | $1,622,144 | +6.0% |
| 5 | Schroeder Asphalt Services, Inc. | $1,646,103 | +7.0% |
| 6 | D'Land Construction, LLC | $1,698,791 | +11% |
| 7 | Brothers Asphalt Paving, Inc. | $1,712,420 | +12% |
| 8 | Alliance Contractors, Inc. | $1,727,345 | +13% |
| 9 | K-Five Construction Corporation | $1,731,773 | +13% |
| 10 | R. W. Dunteman Company | $1,784,485 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Builders Paving, LLC | 2. A Lamp Concrete Contractors, Inc. | 3. Plote Construction, Inc. | 4. Davis Concrete Construction Co. | 5. Schroeder Asphalt Services, Inc. | 6. D'Land Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Pavement marking SPL (XX008910) | SF | 1,600 | $32.00 | $32.00 | $32.00 | $32.00 | $36.00 | $35.50 |
| 2 | CL D patch T4 2 1/4 (XX009709) | SY | 4,500 | $22.00 | $9.00 | $9.00 | $17.50 | $20.00 | $24.00 |
| 3 | Pavement marking SPL2 (XX009710) | SF | 275 | $23.00 | $23.00 | $23.00 | $23.00 | $25.00 | $25.50 |
| 4 | Washout basin (X0326806) | LS | 1 | $4,000.00 | $1,000.00 | $4,000.00 | $2,000.00 | $3,745.00 | $5,500.00 |
| 5 | Sodding SPL (X2520700) | SY | 3,700 | $16.25 | $15.50 | $15.50 | $15.50 | $18.10 | $18.00 |
| 6 | HMA driveway pavt 3 (X4060280) | SY | 150 | $45.00 | $43.00 | $55.00 | $22.50 | $37.00 | $40.00 |
| 7 | PCC driveway PVT 6 SP (X4230710) | SY | 1,500 | $80.10 | $89.50 | $80.10 | $84.00 | $100.50 | $80.00 |
| 8 | PC conc sidewalk 5 SP (X4240430) | SF | 7,400 | $8.75 | $9.75 | $8.75 | $9.40 | $11.70 | $10.00 |
| 9 | HMA surf rem var DP (X4401198) | SY | 17,213 | $6.25 | $6.75 | $6.60 | $5.25 | $5.15 | $6.25 |
| 10 | FR & lids adjust SPL (X6030310) | EACH | 3 | $2,500.00 | $875.00 | $2,500.00 | $2,500.00 | $2,750.00 | $1,200.00 |
| 11 | Comb CC&G TB SPL (X6061700) | LF | 12,000 | $24.65 | $28.00 | $24.65 | $26.75 | $37.45 | $30.00 |
| 12 | Temp info signing (X7200061) | SF | 52 | $15.00 | $20.00 | $18.00 | $15.00 | $24.00 | $17.00 |
| 13 | Det loop repl (X8860105) | LF | 200 | $28.93 | $34.19 | $28.93 | $29.00 | $32.00 | $32.00 |
| 14 | Temporary fence (20101000) | LF | 250 | $5.00 | $1.00 | $4.00 | $4.00 | $5.50 | $6.00 |
| 15 | Tree root pruning (20101200) | EACH | 25 | $100.00 | $50.00 | $100.00 | $100.00 | $110.00 | $110.00 |
| 16 | Supple watering (25200200) | UNIT | 100 | $45.00 | $1.00 | $0.01 | $0.01 | $50.00 | $50.00 |
| 17 | Inlet filters (28000510) | EACH | 45 | $200.00 | $50.00 | $200.00 | $1.00 | $215.00 | $275.00 |
| 18 | Bit matls tack CT (40600290) | LB | 15,750 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.50 |
| 19 | Mix CR JTS flangewys (40600400) | TON | 10 | $450.00 | $400.00 | $200.00 | $250.00 | $275.00 | $400.00 |
| 20 | HMA surf rem butt JT (40600982) | SY | 855 | $7.00 | $6.00 | $1.00 | $21.00 | $6.00 | $10.00 |
| 21 | HMA BC IL-9.5 N50 (40602978) | TON | 1,995 | $86.00 | $88.00 | $95.00 | $91.00 | $85.00 | $88.00 |
| 22 | HMA SC IL-9.5 D N50 (40604060) | TON | 1,995 | $88.00 | $88.00 | $95.00 | $92.00 | $85.00 | $89.00 |
| 23 | Detectable warnings (42400800) | SF | 520 | $28.00 | $25.00 | $28.00 | $22.00 | $42.80 | $30.00 |
| 24 | HMA surf rem 2 3/4 (44000160) | SY | 5,683 | $4.75 | $4.25 | $5.30 | $4.10 | $2.65 | $3.00 |
| 25 | Drive pavement rem (44000200) | SY | 1,500 | $13.05 | $9.25 | $14.00 | $14.00 | $16.00 | $15.00 |
| 26 | Comb curb gutter rem (44000500) | LF | 12,000 | $4.75 | $4.75 | $4.75 | $10.00 | $4.28 | $6.00 |
| 27 | Sidewalk rem (44000600) | SF | 7,400 | $1.45 | $1.50 | $1.45 | $3.00 | $0.53 | $1.35 |
| 28 | CL D patch T3 5 (44201709) | SY | 450 | $46.50 | $44.00 | $35.00 | $42.50 | $43.50 | $47.00 |
| 29 | CL D patch T4 5 (44201711) | SY | 600 | $43.50 | $38.00 | $35.00 | $46.50 | $43.50 | $47.00 |
| 30 | Inlets adjust (60260100) | EACH | 8 | $465.00 | $550.00 | $465.00 | $465.00 | $505.00 | $550.00 |
| 31 | Inlets adj new T1F OL (60260300) | EACH | 7 | $950.00 | $1,050.00 | $950.00 | $950.00 | $1,050.00 | $905.00 |
| 32 | Inlets adj new T11F&G (60261300) | EACH | 30 | $1,150.00 | $1,100.00 | $1,150.00 | $1,150.00 | $1,265.00 | $1,100.00 |
| 33 | Mobilization (67100100) | LS | 1 | $85,000 | $95,000 | $90,000 | $100,000 | $12,000 | $85,000 |
| 34 | TR cont & prot 701501 (70102620) | LS | 1 | $10,000 | $78,000 | $121,200 | $10,000 | $16,000 | $41,000 |
| 35 | TR cont & prot 701701 (70102635) | LS | 1 | $1.00 | $1.00 | $4,220.00 | $1.00 | $110.00 | $1.00 |
| 36 | TR cont & prot 701801 (70102640) | LS | 1 | $1.00 | $1.00 | $4,220.00 | $1.00 | $110.00 | $1.00 |
| 37 | Changeable message SN (70107025) | CAL DAY | 35 | $35.00 | $1.00 | $35.00 | $35.00 | $45.00 | $39.00 |
| 38 | Short term pavt mking (70300100) | LF | 2,100 | $1.00 | $0.01 | $1.00 | $1.00 | $2.00 | $3.00 |
| 39 | SHRT TRM pavt MK rem (70300150) | SF | 700 | $2.00 | $0.01 | $0.01 | $1.00 | $3.00 | $9.00 |
| 40 | THPL PVT MK LTR & sym (78000100) | SF | 125 | $9.00 | $6.50 | $9.00 | $9.00 | $9.90 | $5.50 |
| 41 | THPL PVT MK line 4 (78000200) | LF | 3,400 | $1.25 | $0.90 | $1.25 | $1.25 | $1.50 | $1.70 |
| 42 | THPL PVT MK line 6 (78000400) | LF | 1,100 | $1.85 | $3.00 | $1.85 | $1.85 | $2.05 | $2.52 |
| 43 | THPL PVT MK line 24 (78000650) | LF | 180 | $9.00 | $7.15 | $9.00 | $9.00 | $10.00 | $10.10 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of April 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.