IDOT contract 61L36 bid tabulation
Downers Grove, section 23-00121-00-CH. Let by Illinois DOT on January 16, 2026, Dupage, District 01. 10 bids received; low bid $2,105,861 by Acura Inc..
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 139
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Acura Inc. | $2,105,861 | Low |
| 2 | Alliance Contractors, Inc. | $2,157,670 | +2.0% |
| 3 | D'Land Construction, LLC | $2,183,127 | +4.0% |
| 4 | R. W. Dunteman Company | $2,193,985 | +4.0% |
| 5 | K-Five Construction Corporation | $2,196,909 | +4.0% |
| 6 | A Lamp Concrete Contractors, Inc. | $2,274,925 | +8.0% |
| 7 | Landmark Contractors, Inc. | $2,291,255 | +9.0% |
| 8 | Schroeder Asphalt Services, Inc. | $2,469,651 | +17% |
| 9 | Plote Construction, Inc. | $2,521,177 | +20% |
| 10 | Everlast Blacktop Inc. | $2,923,951 | +39% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Acura Inc. | 2. Alliance Contractors, Inc. | 3. D'Land Construction, LLC | 4. R. W. Dunteman Company | 5. K-Five Construction Corporation | 6. A Lamp Concrete Contractors, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | T-quercus macr 2 (A2006716) | EACH | 4 | $650.00 | $600.00 | $672.00 | $600.00 | $600.00 | $600.00 |
| 2 | T-syrg pek M TF 2-1/2 (B2006120) | EACH | 3 | $700.00 | $650.00 | $661.00 | $650.00 | $650.00 | $650.00 |
| 3 | Rec ref PVT markr rem (XX007092) | EACH | 128 | $90.00 | $20.00 | $30.00 | $14.19 | $27.00 | $25.00 |
| 4 | Mailbox post (XX206400) | EACH | 13 | $225.00 | $20.00 | $250.00 | $245.70 | $450.00 | $275.00 |
| 5 | Mailbox rem & repl (X0327902) | EACH | 13 | $250.00 | $200.00 | $750.00 | $395.70 | $500.00 | $325.00 |
| 6 | Explor trench SPL (X2130010) | LF | 100 | $40.00 | $35.00 | $65.00 | $35.00 | $78.44 | $10.00 |
| 7 | Temp access- priv ent (X4021000) | EACH | 20 | $600.00 | $1.00 | $250.00 | $275.00 | $832.00 | $200.00 |
| 8 | Temp access- com ent (X4022000) | EACH | 2 | $800.00 | $1.00 | $600.00 | $450.00 | $832.00 | $275.00 |
| 9 | Temp access- road (X4023000) | EACH | 4 | $1,500.00 | $1.00 | $750.00 | $575.00 | $832.00 | $400.00 |
| 10 | HMA driveway pavt 3 (X4060280) | SY | 401 | $55.00 | $48.00 | $54.00 | $37.25 | $48.00 | $34.50 |
| 11 | Abandon & fill EX SS (X5509900) | LF | 50 | $100.00 | $73.00 | $253.00 | $73.00 | $73.00 | $23.00 |
| 12 | Sanitary manhole adj (X6026050) | EACH | 3 | $1,600.00 | $1,000.00 | $1,150.00 | $1,000.00 | $1,000.00 | $1,175.00 |
| 13 | Change message SN SPL (X7010238) | CAL MO | 14 | $640.00 | $600.00 | $672.00 | $600.00 | $600.00 | $100.00 |
| 14 | Temp info signing (X7200061) | SF | 103 | $16.00 | $15.00 | $17.00 | $15.00 | $15.00 | $14.50 |
| 15 | RCSD refl pavt marker (X7810300) | EACH | 121 | $54.00 | $48.50 | $54.32 | $44.00 | $44.00 | $48.50 |
| 16 | Maint lighting systm (X8000003) | CAL MO | 2.50 | $2,500.00 | $1,914.00 | $2,419.00 | $1,914.00 | $2,159.89 | $1,914.00 |
| 17 | Conduit splice (X8100105) | EACH | 1 | $560.00 | $1,164.50 | $588.00 | $1,164.50 | $524.97 | $1,164.50 |
| 18 | Light pole FDN 24D OS (X8360215) | LF | 54 | $455.00 | $512.25 | $487.18 | $512.25 | $434.98 | $512.25 |
| 19 | Bkwy dev TR BS SP (X8380075) | EACH | 10 | $690.00 | $666.75 | $729.45 | $666.75 | $651.29 | $666.75 |
| 20 | Rem & rein FO CBL con (X8950512) | LF | 1,774 | $7.80 | $2.30 | $8.38 | $2.30 | $7.48 | $2.30 |
| 21 | Construction layout (Z0013798) | LS | 1 | $20,000 | $19,900 | $23,520 | $19,900 | $26,400 | $19,900 |
| 22 | Lum sfty CBL assembly (Z0033020) | EACH | 10 | $260.00 | $373.00 | $274.00 | $373.00 | $244.64 | $373.00 |
| 23 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 |
| 24 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 25 | Tree remov 6-15 (20100110) | UNIT | 64 | $38.00 | $35.00 | $39.00 | $35.00 | $35.00 | $35.00 |
| 26 | Tree remov over 15 (20100210) | UNIT | 36 | $43.00 | $40.00 | $45.00 | $40.00 | $37.00 | $40.00 |
| 27 | Tree root pruning (20101200) | EACH | 5 | $110.00 | $100.00 | $112.00 | $100.00 | $125.00 | $100.00 |
| 28 | Tree prun over 10 (20101350) | EACH | 1 | $130.00 | $125.00 | $140.00 | $125.00 | $50.00 | $137.50 |
| 29 | Supple watering (20101700) | UNIT | 7 | $55.00 | $0.10 | $0.10 | $0.10 | $0.10 | $0.10 |
| 30 | Earth excavation (20200100) | CY | 3,798 | $38.00 | $1.00 | $38.00 | $43.00 | $0.01 | $40.00 |
| 31 | Rem & disp uns matl (20201200) | CY | 2,550 | $38.00 | $1.00 | $41.00 | $50.00 | $0.01 | $10.00 |
| 32 | Trench backfill (20800150) | CY | 101 | $80.00 | $73.00 | $24.00 | $73.00 | $73.00 | $51.00 |
| 33 | Geotech fab F/GR stab (21001000) | SY | 794 | $2.00 | $1.20 | $3.00 | $4.25 | $1.64 | $2.50 |
| 34 | Topsoil F & P 6 (21101625) | SY | 4,539 | $8.50 | $0.10 | $7.85 | $0.10 | $0.10 | $0.10 |
| 35 | Nitrogen fert nutr (25000400) | LB | 56 | $3.10 | $1.00 | $5.60 | $1.00 | $1.00 | $1.00 |
| 36 | Phosphorus fert nutr (25000500) | LB | 56 | $3.10 | $1.00 | $5.60 | $1.00 | $1.00 | $1.00 |
| 37 | Potassium fert nutr (25000600) | LB | 56 | $3.10 | $1.00 | $5.60 | $1.00 | $1.00 | $1.00 |
| 38 | Erosion contr blanket (25100630) | SY | 4,539 | $0.80 | $0.10 | $1.35 | $0.10 | $0.14 | $0.10 |
| 39 | Sodding salt tolerant (25200110) | SY | 4,539 | $11.00 | $17.00 | $14.00 | $17.00 | $17.00 | $17.00 |
| 40 | Supple watering (25200200) | UNIT | 249 | $55.00 | $0.10 | $0.10 | $0.10 | $0.10 | $0.10 |
| 41 | Temp eros contr seed (28000250) | LB | 94 | $1.00 | $0.10 | $5.60 | $0.10 | $0.10 | $0.10 |
| 42 | Perimeter eros bar (28000400) | LF | 1,188 | $4.00 | $3.25 | $4.00 | $3.25 | $3.25 | $1.00 |
| 43 | Inlet filters (28000510) | EACH | 12 | $250.00 | $25.00 | $168.00 | $150.00 | $150.00 | $15.00 |
| 44 | Stone riprap CL A4 (28100107) | SY | 18 | $150.00 | $135.20 | $95.00 | $103.00 | $103.00 | $108.00 |
| 45 | Filter fabric (28200200) | SY | 18 | $5.00 | $0.90 | $12.00 | $1.00 | $1.00 | $9.50 |
| 46 | Agg subgrade improve (30300001) | CY | 311 | $48.00 | $41.95 | $75.00 | $55.00 | $34.00 | $40.00 |
| 47 | Agg subgrade impr 16 (30300116) | SY | 3,168 | $38.00 | $20.20 | $30.00 | $25.75 | $25.00 | $24.00 |
| 48 | Agg base cse B 4 (35101600) | SY | 590 | $10.00 | $4.10 | $5.00 | $9.40 | $6.00 | $9.00 |
| 49 | Agg base cse B 6 (35101800) | SY | 535 | $12.00 | $6.20 | $7.00 | $12.25 | $20.00 | $15.50 |
| 50 | Agg base cse B 8 (35102000) | SY | 862 | $14.00 | $8.25 | $18.00 | $14.75 | $6.00 | $17.00 |
| 51 | PCC bse cse 9 (35300400) | SY | 1,673 | $85.00 | $150.00 | $90.00 | $81.45 | $91.00 | $90.00 |
| 52 | PCC base cse W 9 (35400400) | SY | 553 | $90.00 | $150.00 | $75.00 | $103.45 | $91.00 | $91.00 |
| 53 | Bit matls PR CT (40600275) | LB | 1,092 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 54 | Bit matls tack CT (40600290) | LB | 6,485 | $0.01 | $0.01 | $0.01 | $0.10 | $0.01 | $0.01 |
| 55 | Long joint sealant (40600370) | LF | 6,112 | $4.25 | $4.15 | $4.65 | $4.50 | $3.94 | $3.37 |
| 56 | Mix CR JTS flangewys (40600400) | TON | 10 | $1,100.00 | $350.00 | $392.00 | $397.00 | $1,200.00 | $250.00 |
| 57 | HMA surf rem butt JT (40600982) | SY | 95 | $0.01 | $20.00 | $22.00 | $23.00 | $0.01 | $22.00 |
| 58 | HMA BC IL-19.0 N50 (40603080) | TON | 164 | $116.00 | $140.00 | $157.00 | $132.15 | $119.28 | $105.00 |
| 59 | P HMA BC IL-4.75 N50 (40603200) | TON | 531 | $145.00 | $135.00 | $151.00 | $118.75 | $147.65 | $143.50 |
| 60 | HMA SC IL-9.5 D N70 (40604062) | TON | 1,112 | $120.00 | $100.00 | $112.00 | $111.75 | $118.64 | $110.00 |
| 61 | PCC driveway pavt 7 (42300300) | SY | 371 | $80.00 | $191.25 | $90.00 | $83.50 | $100.00 | $111.00 |
| 62 | PCC driveway pavt 8 (42300400) | SY | 90 | $90.00 | $196.20 | $100.00 | $101.50 | $108.00 | $150.00 |
| 63 | PC conc sidewalk 5 (42400200) | SF | 5,229 | $10.00 | $20.00 | $10.00 | $8.95 | $10.00 | $9.50 |
| 64 | Detectable warnings (42400800) | SF | 171 | $45.00 | $40.00 | $40.00 | $39.25 | $40.00 | $35.00 |
| 65 | Pavement rem (44000100) | SY | 1,311 | $25.00 | $20.00 | $18.00 | $36.75 | $30.57 | $26.50 |
| 66 | HMA surf rem 3 (44000161) | SY | 7,454 | $5.50 | $4.50 | $5.00 | $9.25 | $6.00 | $4.75 |
| 67 | Drive pavement rem (44000200) | SY | 919 | $20.00 | $20.00 | $15.00 | $35.75 | $15.00 | $25.00 |
| 68 | Comb curb gutter rem (44000500) | LF | 3,135 | $6.00 | $15.00 | $9.00 | $11.25 | $10.00 | $6.50 |
| 69 | Sidewalk rem (44000600) | SF | 4,644 | $2.00 | $2.00 | $1.50 | $2.65 | $6.00 | $1.65 |
| 70 | CL B patch T4 9 (44200964) | SY | 27 | $250.00 | $601.10 | $125.00 | $274.35 | $300.00 | $204.00 |
| 71 | CL C patch T2 10 (44201353) | SY | 112 | $170.00 | $251.20 | $100.00 | $218.00 | $105.00 | $100.00 |
| 72 | CL C patch T3 10 (44201357) | SY | 112 | $150.00 | $251.20 | $100.00 | $210.00 | $105.00 | $95.00 |
| 73 | CL C patch T4 10 (44201359) | SY | 112 | $150.00 | $251.20 | $100.00 | $201.00 | $105.00 | $90.00 |
| 74 | CL D patch T2 8 (44201741) | SY | 10 | $500.00 | $120.00 | $134.00 | $238.00 | $450.00 | $181.00 |
| 75 | CL D patch T3 8 (44201745) | SY | 10 | $500.00 | $120.00 | $134.00 | $238.00 | $450.00 | $161.00 |
| 76 | CL D patch T4 8 (44201747) | SY | 10 | $500.00 | $120.00 | $134.00 | $238.00 | $450.00 | $97.00 |
| 77 | Aggregate SHLDS B (48101200) | TON | 31 | $60.00 | $17.15 | $78.00 | $64.50 | $25.00 | $84.00 |
| 78 | Pipe culvert remov (50105220) | LF | 21 | $50.00 | $44.00 | $15.00 | $44.00 | $44.00 | $25.00 |
| 79 | PRC flar end sec 12 (54213657) | EACH | 1 | $2,200.00 | $1,945.00 | $2,164.00 | $1,945.00 | $1,945.00 | $3,825.00 |
| 80 | Concrete collar (54248510) | CY | 0.64 | $1,500.00 | $3,040.00 | $1,900.00 | $1,285.00 | $1,285.00 | $250.00 |
| 81 | Storm sew CL A 2 12 (550A0340) | LF | 416 | $70.00 | $65.00 | $122.00 | $65.00 | $65.00 | $123.00 |
| 82 | Storm sew CL A 2 15 (550A0360) | LF | 65 | $80.00 | $75.00 | $161.00 | $75.00 | $75.00 | $157.00 |
| 83 | Storm sewer rem 10 (55100400) | LF | 11 | $40.00 | $81.00 | $15.00 | $81.00 | $81.00 | $10.00 |
| 84 | Storm sewer rem 12 (55100500) | LF | 78 | $40.00 | $28.00 | $18.00 | $28.00 | $28.00 | $12.00 |
| 85 | Fire hydnts to BE MVD (56400100) | EACH | 3 | $8,000.00 | $7,594.00 | $8,500.00 | $7,594.00 | $7,594.00 | $7,900.00 |
| 86 | Dom wat ser box adj (56500600) | EACH | 4 | $150.00 | $137.00 | $650.00 | $137.00 | $137.00 | $235.00 |
| 87 | Pipe underdr T 2 4 (60108204) | LF | 751 | $21.00 | $19.00 | $25.00 | $19.00 | $19.00 | $40.00 |
| 88 | CB TA 4 dia T23F&G (60201330) | EACH | 5 | $4,000.00 | $3,725.00 | $4,340.00 | $3,725.00 | $3,725.00 | $3,725.00 |
| 89 | Man TA 4 dia T1F OL (60218300) | EACH | 1 | $4,000.00 | $3,500.00 | $5,400.00 | $3,500.00 | $3,500.00 | $5,200.00 |
| 90 | Man TA 4 dia T1F CL (60218400) | EACH | 3 | $4,000.00 | $3,768.00 | $5,400.00 | $3,768.00 | $3,768.00 | $5,200.00 |
| 91 | Man TA 4 dia T23F&G (60219530) | EACH | 1 | $4,000.00 | $3,440.00 | $5,465.00 | $3,440.00 | $3,440.00 | $6,200.00 |
| 92 | Man TA 6 dia T1F CL (60223800) | EACH | 2 | $7,500.00 | $6,798.00 | $8,620.00 | $6,798.00 | $6,798.00 | $11,600 |
| 93 | Inlets TA T1F OL (60234200) | EACH | 1 | $1,800.00 | $1,690.00 | $2,350.00 | $1,690.00 | $1,690.00 | $3,150.00 |
| 94 | Inlets TA T8G (60236200) | EACH | 1 | $1,600.00 | $1,460.00 | $2,325.00 | $1,460.00 | $1,460.00 | $2,950.00 |
| 95 | Inlets TA T23F&G (60237460) | EACH | 6 | $2,000.00 | $1,860.00 | $2,535.00 | $1,860.00 | $1,860.00 | $3,050.00 |
| 96 | Inlets TB T23F&G (60240327) | EACH | 2 | $2,500.00 | $2,370.00 | $2,811.00 | $2,370.00 | $2,370.00 | $3,750.00 |
| 97 | CB adjust (60250200) | EACH | 2 | $600.00 | $540.00 | $850.00 | $540.00 | $540.00 | $575.00 |
| 98 | VV adjust (60265700) | EACH | 5 | $600.00 | $540.00 | $850.00 | $540.00 | $540.00 | $750.00 |
| 99 | Valve box adj (60266600) | EACH | 4 | $250.00 | $237.00 | $550.00 | $237.00 | $237.00 | $700.00 |
| 100 | Remov manholes (60500040) | EACH | 2 | $1,000.00 | $890.00 | $500.00 | $890.00 | $890.00 | $600.00 |
| 101 | Remov catch bas (60500050) | EACH | 2 | $1,000.00 | $890.00 | $500.00 | $890.00 | $890.00 | $600.00 |
| 102 | Remov inlets (60500060) | EACH | 6 | $900.00 | $731.00 | $500.00 | $731.00 | $731.00 | $325.00 |
| 103 | Conc curb TB (60600605) | LF | 200 | $33.00 | $98.40 | $35.00 | $35.75 | $38.00 | $40.00 |
| 104 | Comb CC&G TB6.12 (60603800) | LF | 446 | $33.00 | $102.85 | $40.00 | $34.25 | $38.00 | $48.50 |
| 105 | Comb CC&G TB6.18 (60604400) | LF | 2,682 | $33.00 | $92.65 | $44.00 | $34.50 | $40.00 | $47.50 |
| 106 | Mobilization (67100100) | LS | 1 | $126,000 | $130,027 | $122,750 | $135,500 | $135,361 | $136,450 |
| 107 | TR cont & prot 701501 (70102620) | LS | 1 | $3,000.00 | $2,290.00 | $2,565.00 | $74,500 | $2,290.00 | $312,500 |
| 108 | TR cont & prot 701606 (70102625) | LS | 1 | $3,000.00 | $2,290.00 | $21,565 | $11,000 | $384,227 | $1.00 |
| 109 | TR cont & prot 701602 (70102632) | LS | 1 | $3,000.00 | $2,290.00 | $2,565.00 | $11,000 | $2,290.00 | $1.00 |
| 110 | TR cont & prot 701611 (70102634) | LS | 1 | $3,000.00 | $2,290.00 | $2,565.00 | $11,000 | $2,290.00 | $1.00 |
| 111 | TR cont & prot 701701 (70102635) | LS | 1 | $3,000.00 | $2,290.00 | $2,565.00 | $3,500.00 | $2,290.00 | $1.00 |
| 112 | TR cont & prot 701801 (70102640) | LS | 1 | $3,000.00 | $2,290.00 | $22,565 | $3,500.00 | $2,290.00 | $1.00 |
| 113 | Short term pavt mking (70300100) | LF | 2,372 | $1.00 | $2.00 | $3.00 | $1.75 | $1.00 | $1.00 |
| 114 | SHRT TRM pavt MK rem (70300150) | SF | 792 | $1.00 | $2.00 | $1.00 | $2.00 | $2.00 | $2.00 |
| 115 | Sign panel T1 (72000100) | SF | 139 | $35.00 | $30.00 | $34.50 | $30.00 | $30.00 | $25.00 |
| 116 | Remov sin pan assy TA (72400100) | EACH | 2 | $110.00 | $105.00 | $121.00 | $105.00 | $105.00 | $100.00 |
| 117 | Rem & rel sign panel asmbly TA (72400205) | EACH | 7 | $160.00 | $150.00 | $173.00 | $150.00 | $150.00 | $200.00 |
| 118 | Teles STL sin support (72800100) | LF | 165 | $20.00 | $18.00 | $21.00 | $18.00 | $18.00 | $22.00 |
| 119 | THPL PVT MK LTR & sym (78000100) | SF | 202 | $6.50 | $6.00 | $6.72 | $5.50 | $5.50 | $6.00 |
| 120 | THPL PVT MK line 4 (78000200) | LF | 4,529 | $1.55 | $1.45 | $1.62 | $0.77 | $0.77 | $1.45 |
| 121 | THPL PVT MK line 6 (78000400) | LF | 298 | $1.80 | $1.72 | $1.92 | $1.25 | $1.25 | $1.72 |
| 122 | THPL PVT MK line 12 (78000600) | LF | 1,056 | $3.55 | $3.32 | $7.72 | $2.50 | $2.50 | $3.32 |
| 123 | THPL PVT MK line 24 (78000650) | LF | 58 | $6.50 | $6.00 | $6.72 | $5.50 | $5.50 | $6.00 |
| 124 | Elect serv install (80400100) | EACH | 1 | $4,000.00 | $3,930.00 | $4,099.00 | $3,930.00 | $3,659.89 | $3,930.00 |
| 125 | Elect util serv conn (80400200) | LS | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 | $5,000.00 |
| 126 | Undrgrd C galvs 4 (81028240) | LF | 709 | $65.00 | $72.45 | $68.34 | $72.45 | $61.02 | $72.45 |
| 127 | Handhole (81400100) | EACH | 1 | $4,200.00 | $2,850.00 | $4,401.41 | $2,850.00 | $3,929.83 | $2,850.00 |
| 128 | UD 3#8 #10G xlpuse 1 (81603060) | LF | 1,120 | $22.00 | $17.36 | $22.88 | $17.36 | $20.43 | $17.36 |
| 129 | EC C XLP use 1C 1/0 (81702160) | LF | 120 | $10.00 | $10.19 | $10.11 | $10.19 | $9.03 | $10.19 |
| 130 | Lum LED rdwy E (82110005) | EACH | 10 | $825.00 | $886.00 | $873.42 | $886.00 | $779.84 | $886.00 |
| 131 | LT cont basem 240V100 (82500350) | EACH | 1 | $18,800 | $11,898 | $20,072 | $11,898 | $17,922 | $11,898 |
| 132 | LT P A 35MH 10MA (83007400) | EACH | 10 | $4,000.00 | $4,264.25 | $4,328.79 | $4,264.25 | $3,864.99 | $4,264.25 |
| 133 | Light pole FDN 24D (83600200) | LF | 36 | $375.00 | $372.75 | $394.79 | $372.75 | $352.49 | $372.75 |
| 134 | Rem LT unit salv (84200500) | EACH | 4 | $980.00 | $1,152.50 | $1,041.53 | $1,152.50 | $929.94 | $1,152.50 |
| 135 | Rem pole FDN (84200804) | EACH | 4 | $1,250.00 | $696.50 | $1,335.52 | $696.50 | $1,192.43 | $696.50 |
| 136 | Remov lighting contr (84500110) | EACH | 1 | $1,000.00 | $1,127.50 | $1,041.53 | $1,127.50 | $929.94 | $1,127.50 |
| 137 | Remov LTG contr FDN (84500130) | EACH | 1 | $1,020.00 | $887.00 | $1,041.53 | $887.00 | $959.94 | $887.00 |
| 138 | Main EX TR sig instal (85000200) | EACH | 1 | $5,500.00 | $4,785.00 | $5,510.15 | $4,785.00 | $4,919.78 | $4,785.00 |
| 139 | Rem & RE elcbl FR con (89502350) | LF | 1,761 | $5.00 | $2.32 | $5.21 | $2.32 | $4.65 | $2.32 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.