IDOT contract 61M31 bid tabulation
Hoffman Estates, section 22-00111-00-RS. Let by Illinois DOT on February 27, 2026, Cook, District 01. 6 bids received; low bid $631,786 by A Lamp Concrete Contractors, Inc..
- Owner
- Illinois DOT
- Letting
- 27 FEB 2026
- Pay items
- 55
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | A Lamp Concrete Contractors, Inc. | $631,786 | Low |
| 2 | Builders Paving, LLC | $650,942 | +3.0% |
| 3 | Schroeder Asphalt Services, Inc. | $660,607 | +5.0% |
| 4 | K-Five Construction Corporation | $665,729 | +5.0% |
| 5 | Plote Construction, Inc. | $698,172 | +11% |
| 6 | Everlast Blacktop Inc. | $711,949 | +13% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. A Lamp Concrete Contractors, Inc. | 2. Builders Paving, LLC | 3. Schroeder Asphalt Services, Inc. | 4. K-Five Construction Corporation | 5. Plote Construction, Inc. | 6. Everlast Blacktop Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | R&R curb & gutter SPL (XX009049) | LF | 1,135 | $44.50 | $40.00 | $53.00 | $45.00 | $60.00 | $44.00 |
| 2 | PC conc sidewalk 5 SP (X4240430) | SF | 8,307 | $9.35 | $12.00 | $11.75 | $8.40 | $10.00 | $12.50 |
| 3 | FR & lids adjust SPL (X6030310) | EACH | 1 | $2,500.00 | $1,175.00 | $1,175.00 | $1,805.00 | $1,200.00 | $1,450.00 |
| 4 | Temp info signing (X7200061) | SF | 51 | $20.00 | $25.00 | $30.00 | $25.00 | $25.00 | $28.00 |
| 5 | Drain util STR adj (Z0017400) | EACH | 20 | $450.00 | $500.00 | $500.00 | $400.00 | $500.00 | $900.00 |
| 6 | Tree trunk protection (20101100) | EACH | 8 | $150.00 | $75.00 | $100.00 | $75.00 | $225.00 | $200.00 |
| 7 | Tree root pruning (20101200) | EACH | 9 | $250.00 | $75.00 | $100.00 | $75.00 | $225.00 | $200.00 |
| 8 | Tree prun 1-10 (20101300) | EACH | 5 | $100.00 | $200.00 | $120.00 | $50.00 | $100.00 | $50.00 |
| 9 | Tree prun over 10 (20101350) | EACH | 5 | $300.00 | $250.00 | $200.00 | $121.51 | $350.00 | $150.00 |
| 10 | Earth excavation (20200100) | CY | 234 | $55.00 | $35.00 | $65.00 | $15.00 | $85.00 | $59.00 |
| 11 | Geotech fab F/GR stab (21001000) | SY | 178 | $0.01 | $2.50 | $2.00 | $0.01 | $4.00 | $3.00 |
| 12 | Topsoil F & P var DP (21101600) | SY | 2,175 | $8.95 | $2.00 | $2.50 | $2.00 | $2.00 | $5.00 |
| 13 | Seeding CL 1 (25000100) | ACRE | 0.50 | $6,750.00 | $3,600.00 | $4,000.00 | $3,600.00 | $3,600.00 | $3,000.00 |
| 14 | Nitrogen fert nutr (25000400) | LB | 45 | $1.00 | $1.00 | $2.00 | $1.00 | $1.00 | $3.00 |
| 15 | Potassium fert nutr (25000600) | LB | 45 | $1.00 | $1.00 | $2.00 | $1.00 | $1.00 | $3.00 |
| 16 | Erosion contr blanket (25100630) | SY | 2,420 | $3.10 | $4.00 | $5.00 | $4.00 | $4.00 | $3.00 |
| 17 | Inlet filters (28000510) | EACH | 20 | $15.00 | $150.00 | $180.00 | $175.00 | $150.00 | $180.00 |
| 18 | Agg base cse B 4 (35101600) | SY | 711 | $9.85 | $4.00 | $11.33 | $5.50 | $20.00 | $24.00 |
| 19 | Bit matls tack CT (40600290) | LB | 7,114 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 20 | Mix CR JTS flangewys (40600400) | TON | 5 | $615.00 | $300.00 | $500.00 | $1,000.00 | $1,450.00 | $500.00 |
| 21 | HMA surf rem butt JT (40600982) | SY | 116 | $19.25 | $35.00 | $15.00 | $25.00 | $40.00 | $28.00 |
| 22 | HMA BC IL-19.0 N50 (40603080) | TON | 527 | $91.50 | $85.00 | $88.00 | $85.00 | $87.00 | $89.00 |
| 23 | P HMA BC IL-4.75 N50 (40603200) | TON | 419 | $115.00 | $130.50 | $108.00 | $109.00 | $105.00 | $108.21 |
| 24 | HMA SC IL-9.5 D N50 (40604060) | TON | 1,029 | $91.00 | $92.75 | $87.50 | $87.00 | $88.00 | $92.31 |
| 25 | PCC driveway pavt 8 (42300400) | SY | 76 | $128.00 | $81.00 | $123.00 | $110.00 | $90.00 | $135.00 |
| 26 | PC conc sidewalk 5 (42400200) | SF | 6,395 | $8.50 | $10.00 | $10.50 | $7.50 | $12.00 | $12.50 |
| 27 | Detectable warnings (42400800) | SF | 227 | $30.00 | $40.00 | $43.50 | $26.00 | $30.00 | $45.00 |
| 28 | HMA surf rem 2 1/4 (44000158) | SY | 9,863 | $2.50 | $3.50 | $2.25 | $2.75 | $4.50 | $2.68 |
| 29 | HMA surf rem 6 (44000173) | SY | 2,030 | $6.25 | $7.25 | $6.00 | $7.50 | $6.50 | $9.87 |
| 30 | Drive pavement rem (44000200) | SY | 76 | $19.75 | $36.00 | $25.00 | $18.00 | $30.00 | $18.00 |
| 31 | Sidewalk rem (44000600) | SF | 7,970 | $1.10 | $4.00 | $2.50 | $1.55 | $2.00 | $2.50 |
| 32 | CL D patch T1 8 (44201737) | SY | 99 | $100.00 | $77.00 | $88.00 | $30.00 | $35.00 | $66.00 |
| 33 | CL D patch T2 8 (44201741) | SY | 99 | $83.00 | $64.00 | $88.00 | $30.00 | $35.00 | $61.00 |
| 34 | CL D patch T3 8 (44201745) | SY | 197 | $67.00 | $52.00 | $85.00 | $30.00 | $35.00 | $62.00 |
| 35 | CL D patch T4 8 (44201747) | SY | 197 | $67.00 | $46.00 | $85.00 | $30.00 | $35.00 | $60.00 |
| 36 | Dom wat ser box adj (56500600) | EACH | 1 | $250.00 | $150.00 | $165.00 | $380.00 | $150.00 | $1,200.00 |
| 37 | Man TA 4 dia T3F&G (60218500) | EACH | 1 | $8,950.00 | $4,250.00 | $4,250.00 | $7,500.00 | $4,250.00 | $5,800.00 |
| 38 | Remov manholes (60500040) | EACH | 1 | $300.00 | $1,055.00 | $1,056.00 | $1,055.00 | $1,100.00 | $3,500.00 |
| 39 | Mobilization (67100100) | LS | 1 | $37,500 | $31,801 | $21,000 | $35,000 | $35,000 | $27,000 |
| 40 | TR cont & prot 701501 (70102620) | LS | 1 | $13,750 | $7,900.00 | $12,000 | $121,700 | $36,900 | $6,050.00 |
| 41 | TR cont & prot 701701 (70102635) | LS | 1 | $1.00 | $100.00 | $1.00 | $100.00 | $100.00 | $1,100.00 |
| 42 | TR cont & prot 701801 (70102640) | LS | 1 | $1.00 | $100.00 | $1.00 | $100.00 | $100.00 | $6,050.00 |
| 43 | Short term pavt mking (70300100) | LF | 418 | $0.01 | $2.40 | $2.00 | $0.01 | $1.00 | $1.00 |
| 44 | SHRT TRM pavt MK rem (70300150) | SF | 139 | $0.01 | $0.01 | $3.00 | $0.01 | $12.50 | $3.50 |
| 45 | Temp PVT MK line 4 - paint (70300221) | LF | 4,185 | $0.01 | $0.15 | $0.54 | $0.01 | $0.01 | $1.00 |
| 46 | Temp PVT MK line 6 - paint (70300241) | LF | 971 | $0.01 | $0.20 | $0.82 | $0.01 | $0.01 | $1.50 |
| 47 | Temp PVT MK line 24 - paint (70300281) | LF | 67 | $0.01 | $0.75 | $3.10 | $0.01 | $0.01 | $6.00 |
| 48 | Sign panel T1 (72000100) | SF | 17 | $25.00 | $27.50 | $31.00 | $0.01 | $30.00 | $75.00 |
| 49 | Teles STL sin support (72800100) | LF | 30 | $30.00 | $15.50 | $17.50 | $15.50 | $15.00 | $75.00 |
| 50 | Pref THPL PM LTR-sym (78006100) | SF | 208 | $28.90 | $29.00 | $33.00 | $28.90 | $30.00 | $22.00 |
| 51 | Mod ureth PM LTR-sym (78009000) | SF | 73 | $6.00 | $6.00 | $7.00 | $6.00 | $6.00 | $10.00 |
| 52 | Mod ureth PM line 4 (78009004) | LF | 4,185 | $1.25 | $1.25 | $1.40 | $1.25 | $1.25 | $2.00 |
| 53 | Mod ureth PM line 6 (78009006) | LF | 971 | $1.50 | $1.50 | $1.70 | $1.50 | $1.50 | $2.25 |
| 54 | Mod ureth PM line 8 (78009008) | LF | 63 | $3.00 | $3.00 | $3.30 | $3.00 | $3.00 | $5.00 |
| 55 | Mod ureth PM line 24 (78009024) | LF | 187 | $6.00 | $6.00 | $7.00 | $6.00 | $6.00 | $15.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.