IDOT contract 61L89 bid tabulation

Brookfield, section 25-00138-00-RS. Let by Illinois DOT on January 16, 2026, Cook, District 01. 7 bids received; low bid $1,934,050 by Builders Paving, LLC.

Owner
Illinois DOT
Letting
16 JAN 2026
Pay items
90
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Builders Paving, LLC$1,934,050Low
2Lindahl Brothers, Inc.$1,948,038+1.0%
3K-Five Construction Corporation$1,963,789+2.0%
4Everlast Blacktop Inc.$2,166,042+12%
5Schroeder Asphalt Services, Inc.$2,228,120+15%
6Plote Construction, Inc.$2,391,956+24%
7A Lamp Concrete Contractors, Inc.$2,428,977+26%
IDOT contract 61L89: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Builders Paving, LLC2. Lindahl Brothers, Inc.3. K-Five Construction Corporation4. Everlast Blacktop Inc.5. Schroeder Asphalt Services, Inc.6. Plote Construction, Inc.
1Explor excavation (XX000541)CY75$55.00$100.00$100.00$50.00$115.00$100.00
2San sew service 6 (XX003803)LF120$180.00$81.00$80.00$191.00$82.00$81.00
312" X 6" PVC sew con (XX005634)EACH15$5,000.00$3,600.00$600.00$4,500.00$1,195.00$3,600.00
4PVC CS pipe repl 12" (XX006449)LF140$160.00$295.00$80.00$186.00$715.00$295.00
5PVC CS pipe repl 15" (XX006450)LF40$225.00$470.00$90.00$265.00$1,065.00$470.00
615" X 6" PVC sew con (XX006452)EACH4$5,000.00$3,650.00$1,250.00$11,900$1,195.00$3,650.00
730" X 6" PVC sew con (XX007205)EACH3$8,500.00$5,830.00$1,750.00$14,000$8,400.00$5,830.00
8Comb sew rem & repl (XX008190)LF38$250.00$845.00$150.00$194.00$2,025.00$845.00
9Washout basin (X0326806)LS1$2,000.00$2,000.00$2,000.00$900.00$2,500.00$2,000.00
10R R FL beacon A comp (X1400326)EACH2$12,400$12,461$12,461$14,200$13,800$12,461
11Temp access- priv ent (X4021000)EACH4$300.00$50.00$425.00$400.00$90.00$100.00
12Temp access- com ent (X4022000)EACH8$600.00$50.00$700.00$400.00$200.00$250.00
13Detectable warn SPL (X4240800)SF200$60.00$40.00$53.25$69.00$60.00$50.00
14HMA surf rem SPL (X4400196)SY175$47.00$25.00$35.00$36.00$20.00$30.00
15HMA surf rem var DP (X4401198)SY24,000$6.50$6.00$4.30$4.12$4.75$6.50
16Temporary patching (X4420210)SY600$10.00$28.00$85.00$60.00$30.00$28.00
17FR & lids adjust SPL (X6030310)EACH47$1,200.00$1,150.00$1,500.00$975.00$1,400.00$1,150.00
18Temp info signing (X7200061)SF102$15.00$15.00$15.00$19.00$18.00$15.00
19Main EX FL beacon ins (X8500110)EACH2$600.00$600.00$600.00$800.00$700.00$600.00
20Det loop repl (X8860105)LF175$40.10$40.10$40.10$46.00$46.00$40.10
21Drainage STR removed (Z0018700)EACH1$900.00$450.00$1,000.00$500.00$980.00$450.00
22Trainees (Z0076600)HR500$0.80$0.80$0.80$0.80$0.80$0.80
23Trainees TPG (Z0076604)HR500$15.00$15.00$15.00$15.00$15.00$15.00
24Tree trunk protection (20101100)EACH100$150.00$150.00$75.00$140.00$215.00$75.00
25Tree root pruning (20101200)EACH10$124.00$125.00$250.00$220.00$245.00$250.00
26Earth excavation (20200100)CY85$140.00$75.00$150.00$75.00$80.00$80.00
27Trench backfill (20800150)CY300$55.00$48.00$85.00$62.00$96.00$48.00
28Topsoil F & P 4 (21101615)SY4,550$6.00$8.00$6.00$6.00$12.30$6.00
29Topsoil F & P 12 (21101645)SY250$16.50$12.00$14.00$19.94$36.50$14.00
30Nitrogen fert nutr (25000400)LB50$10.00$10.00$3.00$1.00$5.00$3.00
31Potassium fert nutr (25000600)LB50$10.00$10.00$3.00$1.00$5.00$3.00
32Sodding salt tolerant (25200110)SY4,800$12.50$8.00$10.00$12.50$21.00$10.00
33Supple watering (25200200)UNIT260$30.00$30.00$55.00$1.00$40.00$55.00
34Inlet filters (28000510)EACH80$185.00$200.00$80.00$170.00$240.00$175.00
35PCC bse cse 8 (35300300)SY150$80.00$95.00$128.53$152.00$145.00$96.00
36Bit matls tack CT (40600290)LB17,000$0.01$0.01$0.01$0.01$0.01$0.01
37Long joint sealant (40600370)LF15,000$3.00$3.07$3.35$3.80$3.80$4.10
38Mix CR JTS flangewys (40600400)TON40$300.00$385.00$150.00$390.00$350.00$175.00
39HMA surf rem butt JT (40600982)SY300$20.00$25.00$0.01$31.00$15.00$50.00
40HMA BC IL-9.5 N50 (40602978)TON2,100$95.00$97.00$88.05$89.10$93.00$120.00
41HMA SC IL-9.5 D N50 (40604060)TON2,800$84.00$97.00$86.00$90.50$93.00$105.00
42Incidental HMA surf (40800050)TON40$200.00$200.00$250.00$220.00$125.00$350.00
43PCC PVT 8 (42000300)SY225$150.00$105.35$119.21$152.00$136.00$110.00
44Protective coat (42001300)SY2,850$0.10$2.00$1.00$4.00$1.00$1.00
45PCC driveway pavt 7 (42300300)SY275$125.00$100.00$110.13$118.00$125.00$107.00
46PC conc sidewalk 5 (42400200)SF16,000$9.00$9.95$9.00$12.00$10.00$9.65
47Detectable warnings (42400800)SF500$42.00$34.00$43.82$59.00$50.00$45.00
48Pavement rem (44000100)SY500$22.00$15.00$25.00$18.00$20.00$24.00
49Drive pavement rem (44000200)SY300$20.00$17.75$7.00$18.00$12.00$18.00
50Comb curb gutter rem (44000500)LF2,150$9.00$8.00$7.00$8.40$9.00$8.50
51Sidewalk rem (44000600)SF17,000$3.00$1.95$1.75$1.94$2.50$2.19
52CL D patch T1 10 (44201761)SY150$108.00$105.00$80.00$141.00$120.00$160.00
53CL D patch T2 10 (44201765)SY275$90.00$85.00$80.00$96.00$115.00$160.00
54CL D patch T3 10 (44201769)SY325$85.00$80.00$80.00$96.00$110.00$160.00
55CL D patch T4 10 (44201771)SY575$68.00$80.00$80.00$96.00$108.00$160.00
56Saw cuts (44213200)LF3,850$1.50$0.25$0.01$3.25$2.25$3.90
57Tie bars 3/4 (44213204)EACH200$17.00$7.00$5.00$22.00$12.00$7.50
58SS RG CL A 2 15 (550A2530)LF8$250.00$425.00$150.00$800.00$900.00$425.00
59SS RG CL A 2 24 (550A2560)LF47$300.00$275.00$150.00$350.00$670.00$275.00
60Storm sewer rem 15 (55100700)LF8$30.00$30.00$50.00$800.00$12.25$30.00
61Storm sewer rem 24 (55101200)LF47$30.00$30.00$50.00$40.00$12.25$30.00
62Dom wat ser box adj (56500600)EACH10$850.00$210.00$750.00$700.00$265.00$210.00
63CB TC T1F OL (60206905)EACH1$3,500.00$2,900.00$3,000.00$3,500.00$5,150.00$2,900.00
64CB reconst (60252800)EACH3$2,100.00$1,900.00$3,000.00$2,000.00$2,650.00$1,900.00
65Man reconst (60257900)EACH3$2,800.00$3,000.00$3,000.00$2,000.00$2,650.00$3,000.00
66FR & lids adjust (60300305)EACH34$900.00$550.00$1,500.00$750.00$962.00$550.00
67Lids T1 OL (60403700)EACH28$300.00$320.00$950.00$850.00$295.00$320.00
68FR & lids T1 OL (60406000)EACH26$575.00$450.00$950.00$850.00$675.00$450.00
69FR & lids T1 CL (60406100)EACH10$550.00$450.00$950.00$850.00$675.00$450.00
70Comb CC&G TB6.12 (60603800)LF275$45.00$43.00$40.00$58.00$48.00$44.00
71Comb CC&G TB6.12 mod (60604100)LF225$45.00$43.00$40.00$54.00$48.00$44.00
72Comb CC&G TB6.18 mod (60604700)LF1,650$48.00$48.00$43.32$41.00$48.00$53.00
73Non SPL waste disposl (66900200)CY325$80.00$106.00$115.00$88.00$105.00$165.00
74Soil disposal analy (66900530)EACH1$1,450.00$1,450.00$1,300.00$2,200.00$1,700.00$1,600.00
75Reg sub P-const plan (66901001)LS1$3,100.00$3,100.00$3,100.00$2,900.00$4,800.00$3,400.00
76Reg sub F con report (66901003)LS1$1,200.00$1,200.00$1,200.00$2,800.00$600.00$2,400.00
77Reg sub mon (66901006)CAL DAY10$680.00$680.00$680.00$1,300.00$900.00$870.00
78Mobilization (67100100)LS1$65,660$100,000$119,000$83,309$30,000$143,500
79TR cont & prot 701501 (70102620)LS1$9,000.00$9,000.00$126,000$61,035$15,500$115,000
80TR cont & prot 701801 (70102640)LS1$1.00$1.00$1.00$2,500.00$15,500$22,000
81Changeable message SN (70107025)CAL DAY50$35.00$35.00$35.00$66.00$40.00$30.00
82Short term pavt mking (70300100)LF2,100$1.53$2.00$1.00$6.00$3.00$3.75
83SHRT TRM pavt MK rem (70300150)SF700$0.01$2.00$2.00$3.00$4.00$8.00
84THPL PVT MK LTR & sym (78000100)SF100$5.50$5.50$5.50$6.60$8.50$6.00
85THPL PVT MK line 4 (78000200)LF9,600$0.81$0.81$0.81$1.00$0.90$0.82
86THPL PVT MK line 6 (78000400)LF1,650$1.22$1.22$1.22$1.70$1.45$1.30
87THPL PVT MK line 12 (78000600)LF500$2.45$2.45$2.45$3.20$4.35$2.90
88THPL PVT MK line 24 (78000650)LF375$5.50$5.50$5.50$7.00$8.50$6.00
89Remov EX handhole (89502380)EACH1$1,200.00$1,200.00$1,200.00$1,400.00$1,400.00$1,200.00
90Rem EX FB instal comp (89502400)EACH2$1,600.00$1,600.00$1,600.00$1,800.00$1,800.00$1,600.00
IDOT contract 61L89: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy