IDOT contract 61L89 bid tabulation
Brookfield, section 25-00138-00-RS. Let by Illinois DOT on January 16, 2026, Cook, District 01. 7 bids received; low bid $1,934,050 by Builders Paving, LLC.
- Owner
- Illinois DOT
- Letting
- 16 JAN 2026
- Pay items
- 90
- Data through
- 18 SEP 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Builders Paving, LLC | $1,934,050 | Low |
| 2 | Lindahl Brothers, Inc. | $1,948,038 | +1.0% |
| 3 | K-Five Construction Corporation | $1,963,789 | +2.0% |
| 4 | Everlast Blacktop Inc. | $2,166,042 | +12% |
| 5 | Schroeder Asphalt Services, Inc. | $2,228,120 | +15% |
| 6 | Plote Construction, Inc. | $2,391,956 | +24% |
| 7 | A Lamp Concrete Contractors, Inc. | $2,428,977 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Builders Paving, LLC | 2. Lindahl Brothers, Inc. | 3. K-Five Construction Corporation | 4. Everlast Blacktop Inc. | 5. Schroeder Asphalt Services, Inc. | 6. Plote Construction, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Explor excavation (XX000541) | CY | 75 | $55.00 | $100.00 | $100.00 | $50.00 | $115.00 | $100.00 |
| 2 | San sew service 6 (XX003803) | LF | 120 | $180.00 | $81.00 | $80.00 | $191.00 | $82.00 | $81.00 |
| 3 | 12" X 6" PVC sew con (XX005634) | EACH | 15 | $5,000.00 | $3,600.00 | $600.00 | $4,500.00 | $1,195.00 | $3,600.00 |
| 4 | PVC CS pipe repl 12" (XX006449) | LF | 140 | $160.00 | $295.00 | $80.00 | $186.00 | $715.00 | $295.00 |
| 5 | PVC CS pipe repl 15" (XX006450) | LF | 40 | $225.00 | $470.00 | $90.00 | $265.00 | $1,065.00 | $470.00 |
| 6 | 15" X 6" PVC sew con (XX006452) | EACH | 4 | $5,000.00 | $3,650.00 | $1,250.00 | $11,900 | $1,195.00 | $3,650.00 |
| 7 | 30" X 6" PVC sew con (XX007205) | EACH | 3 | $8,500.00 | $5,830.00 | $1,750.00 | $14,000 | $8,400.00 | $5,830.00 |
| 8 | Comb sew rem & repl (XX008190) | LF | 38 | $250.00 | $845.00 | $150.00 | $194.00 | $2,025.00 | $845.00 |
| 9 | Washout basin (X0326806) | LS | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $900.00 | $2,500.00 | $2,000.00 |
| 10 | R R FL beacon A comp (X1400326) | EACH | 2 | $12,400 | $12,461 | $12,461 | $14,200 | $13,800 | $12,461 |
| 11 | Temp access- priv ent (X4021000) | EACH | 4 | $300.00 | $50.00 | $425.00 | $400.00 | $90.00 | $100.00 |
| 12 | Temp access- com ent (X4022000) | EACH | 8 | $600.00 | $50.00 | $700.00 | $400.00 | $200.00 | $250.00 |
| 13 | Detectable warn SPL (X4240800) | SF | 200 | $60.00 | $40.00 | $53.25 | $69.00 | $60.00 | $50.00 |
| 14 | HMA surf rem SPL (X4400196) | SY | 175 | $47.00 | $25.00 | $35.00 | $36.00 | $20.00 | $30.00 |
| 15 | HMA surf rem var DP (X4401198) | SY | 24,000 | $6.50 | $6.00 | $4.30 | $4.12 | $4.75 | $6.50 |
| 16 | Temporary patching (X4420210) | SY | 600 | $10.00 | $28.00 | $85.00 | $60.00 | $30.00 | $28.00 |
| 17 | FR & lids adjust SPL (X6030310) | EACH | 47 | $1,200.00 | $1,150.00 | $1,500.00 | $975.00 | $1,400.00 | $1,150.00 |
| 18 | Temp info signing (X7200061) | SF | 102 | $15.00 | $15.00 | $15.00 | $19.00 | $18.00 | $15.00 |
| 19 | Main EX FL beacon ins (X8500110) | EACH | 2 | $600.00 | $600.00 | $600.00 | $800.00 | $700.00 | $600.00 |
| 20 | Det loop repl (X8860105) | LF | 175 | $40.10 | $40.10 | $40.10 | $46.00 | $46.00 | $40.10 |
| 21 | Drainage STR removed (Z0018700) | EACH | 1 | $900.00 | $450.00 | $1,000.00 | $500.00 | $980.00 | $450.00 |
| 22 | Trainees (Z0076600) | HR | 500 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 | $0.80 |
| 23 | Trainees TPG (Z0076604) | HR | 500 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 24 | Tree trunk protection (20101100) | EACH | 100 | $150.00 | $150.00 | $75.00 | $140.00 | $215.00 | $75.00 |
| 25 | Tree root pruning (20101200) | EACH | 10 | $124.00 | $125.00 | $250.00 | $220.00 | $245.00 | $250.00 |
| 26 | Earth excavation (20200100) | CY | 85 | $140.00 | $75.00 | $150.00 | $75.00 | $80.00 | $80.00 |
| 27 | Trench backfill (20800150) | CY | 300 | $55.00 | $48.00 | $85.00 | $62.00 | $96.00 | $48.00 |
| 28 | Topsoil F & P 4 (21101615) | SY | 4,550 | $6.00 | $8.00 | $6.00 | $6.00 | $12.30 | $6.00 |
| 29 | Topsoil F & P 12 (21101645) | SY | 250 | $16.50 | $12.00 | $14.00 | $19.94 | $36.50 | $14.00 |
| 30 | Nitrogen fert nutr (25000400) | LB | 50 | $10.00 | $10.00 | $3.00 | $1.00 | $5.00 | $3.00 |
| 31 | Potassium fert nutr (25000600) | LB | 50 | $10.00 | $10.00 | $3.00 | $1.00 | $5.00 | $3.00 |
| 32 | Sodding salt tolerant (25200110) | SY | 4,800 | $12.50 | $8.00 | $10.00 | $12.50 | $21.00 | $10.00 |
| 33 | Supple watering (25200200) | UNIT | 260 | $30.00 | $30.00 | $55.00 | $1.00 | $40.00 | $55.00 |
| 34 | Inlet filters (28000510) | EACH | 80 | $185.00 | $200.00 | $80.00 | $170.00 | $240.00 | $175.00 |
| 35 | PCC bse cse 8 (35300300) | SY | 150 | $80.00 | $95.00 | $128.53 | $152.00 | $145.00 | $96.00 |
| 36 | Bit matls tack CT (40600290) | LB | 17,000 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 37 | Long joint sealant (40600370) | LF | 15,000 | $3.00 | $3.07 | $3.35 | $3.80 | $3.80 | $4.10 |
| 38 | Mix CR JTS flangewys (40600400) | TON | 40 | $300.00 | $385.00 | $150.00 | $390.00 | $350.00 | $175.00 |
| 39 | HMA surf rem butt JT (40600982) | SY | 300 | $20.00 | $25.00 | $0.01 | $31.00 | $15.00 | $50.00 |
| 40 | HMA BC IL-9.5 N50 (40602978) | TON | 2,100 | $95.00 | $97.00 | $88.05 | $89.10 | $93.00 | $120.00 |
| 41 | HMA SC IL-9.5 D N50 (40604060) | TON | 2,800 | $84.00 | $97.00 | $86.00 | $90.50 | $93.00 | $105.00 |
| 42 | Incidental HMA surf (40800050) | TON | 40 | $200.00 | $200.00 | $250.00 | $220.00 | $125.00 | $350.00 |
| 43 | PCC PVT 8 (42000300) | SY | 225 | $150.00 | $105.35 | $119.21 | $152.00 | $136.00 | $110.00 |
| 44 | Protective coat (42001300) | SY | 2,850 | $0.10 | $2.00 | $1.00 | $4.00 | $1.00 | $1.00 |
| 45 | PCC driveway pavt 7 (42300300) | SY | 275 | $125.00 | $100.00 | $110.13 | $118.00 | $125.00 | $107.00 |
| 46 | PC conc sidewalk 5 (42400200) | SF | 16,000 | $9.00 | $9.95 | $9.00 | $12.00 | $10.00 | $9.65 |
| 47 | Detectable warnings (42400800) | SF | 500 | $42.00 | $34.00 | $43.82 | $59.00 | $50.00 | $45.00 |
| 48 | Pavement rem (44000100) | SY | 500 | $22.00 | $15.00 | $25.00 | $18.00 | $20.00 | $24.00 |
| 49 | Drive pavement rem (44000200) | SY | 300 | $20.00 | $17.75 | $7.00 | $18.00 | $12.00 | $18.00 |
| 50 | Comb curb gutter rem (44000500) | LF | 2,150 | $9.00 | $8.00 | $7.00 | $8.40 | $9.00 | $8.50 |
| 51 | Sidewalk rem (44000600) | SF | 17,000 | $3.00 | $1.95 | $1.75 | $1.94 | $2.50 | $2.19 |
| 52 | CL D patch T1 10 (44201761) | SY | 150 | $108.00 | $105.00 | $80.00 | $141.00 | $120.00 | $160.00 |
| 53 | CL D patch T2 10 (44201765) | SY | 275 | $90.00 | $85.00 | $80.00 | $96.00 | $115.00 | $160.00 |
| 54 | CL D patch T3 10 (44201769) | SY | 325 | $85.00 | $80.00 | $80.00 | $96.00 | $110.00 | $160.00 |
| 55 | CL D patch T4 10 (44201771) | SY | 575 | $68.00 | $80.00 | $80.00 | $96.00 | $108.00 | $160.00 |
| 56 | Saw cuts (44213200) | LF | 3,850 | $1.50 | $0.25 | $0.01 | $3.25 | $2.25 | $3.90 |
| 57 | Tie bars 3/4 (44213204) | EACH | 200 | $17.00 | $7.00 | $5.00 | $22.00 | $12.00 | $7.50 |
| 58 | SS RG CL A 2 15 (550A2530) | LF | 8 | $250.00 | $425.00 | $150.00 | $800.00 | $900.00 | $425.00 |
| 59 | SS RG CL A 2 24 (550A2560) | LF | 47 | $300.00 | $275.00 | $150.00 | $350.00 | $670.00 | $275.00 |
| 60 | Storm sewer rem 15 (55100700) | LF | 8 | $30.00 | $30.00 | $50.00 | $800.00 | $12.25 | $30.00 |
| 61 | Storm sewer rem 24 (55101200) | LF | 47 | $30.00 | $30.00 | $50.00 | $40.00 | $12.25 | $30.00 |
| 62 | Dom wat ser box adj (56500600) | EACH | 10 | $850.00 | $210.00 | $750.00 | $700.00 | $265.00 | $210.00 |
| 63 | CB TC T1F OL (60206905) | EACH | 1 | $3,500.00 | $2,900.00 | $3,000.00 | $3,500.00 | $5,150.00 | $2,900.00 |
| 64 | CB reconst (60252800) | EACH | 3 | $2,100.00 | $1,900.00 | $3,000.00 | $2,000.00 | $2,650.00 | $1,900.00 |
| 65 | Man reconst (60257900) | EACH | 3 | $2,800.00 | $3,000.00 | $3,000.00 | $2,000.00 | $2,650.00 | $3,000.00 |
| 66 | FR & lids adjust (60300305) | EACH | 34 | $900.00 | $550.00 | $1,500.00 | $750.00 | $962.00 | $550.00 |
| 67 | Lids T1 OL (60403700) | EACH | 28 | $300.00 | $320.00 | $950.00 | $850.00 | $295.00 | $320.00 |
| 68 | FR & lids T1 OL (60406000) | EACH | 26 | $575.00 | $450.00 | $950.00 | $850.00 | $675.00 | $450.00 |
| 69 | FR & lids T1 CL (60406100) | EACH | 10 | $550.00 | $450.00 | $950.00 | $850.00 | $675.00 | $450.00 |
| 70 | Comb CC&G TB6.12 (60603800) | LF | 275 | $45.00 | $43.00 | $40.00 | $58.00 | $48.00 | $44.00 |
| 71 | Comb CC&G TB6.12 mod (60604100) | LF | 225 | $45.00 | $43.00 | $40.00 | $54.00 | $48.00 | $44.00 |
| 72 | Comb CC&G TB6.18 mod (60604700) | LF | 1,650 | $48.00 | $48.00 | $43.32 | $41.00 | $48.00 | $53.00 |
| 73 | Non SPL waste disposl (66900200) | CY | 325 | $80.00 | $106.00 | $115.00 | $88.00 | $105.00 | $165.00 |
| 74 | Soil disposal analy (66900530) | EACH | 1 | $1,450.00 | $1,450.00 | $1,300.00 | $2,200.00 | $1,700.00 | $1,600.00 |
| 75 | Reg sub P-const plan (66901001) | LS | 1 | $3,100.00 | $3,100.00 | $3,100.00 | $2,900.00 | $4,800.00 | $3,400.00 |
| 76 | Reg sub F con report (66901003) | LS | 1 | $1,200.00 | $1,200.00 | $1,200.00 | $2,800.00 | $600.00 | $2,400.00 |
| 77 | Reg sub mon (66901006) | CAL DAY | 10 | $680.00 | $680.00 | $680.00 | $1,300.00 | $900.00 | $870.00 |
| 78 | Mobilization (67100100) | LS | 1 | $65,660 | $100,000 | $119,000 | $83,309 | $30,000 | $143,500 |
| 79 | TR cont & prot 701501 (70102620) | LS | 1 | $9,000.00 | $9,000.00 | $126,000 | $61,035 | $15,500 | $115,000 |
| 80 | TR cont & prot 701801 (70102640) | LS | 1 | $1.00 | $1.00 | $1.00 | $2,500.00 | $15,500 | $22,000 |
| 81 | Changeable message SN (70107025) | CAL DAY | 50 | $35.00 | $35.00 | $35.00 | $66.00 | $40.00 | $30.00 |
| 82 | Short term pavt mking (70300100) | LF | 2,100 | $1.53 | $2.00 | $1.00 | $6.00 | $3.00 | $3.75 |
| 83 | SHRT TRM pavt MK rem (70300150) | SF | 700 | $0.01 | $2.00 | $2.00 | $3.00 | $4.00 | $8.00 |
| 84 | THPL PVT MK LTR & sym (78000100) | SF | 100 | $5.50 | $5.50 | $5.50 | $6.60 | $8.50 | $6.00 |
| 85 | THPL PVT MK line 4 (78000200) | LF | 9,600 | $0.81 | $0.81 | $0.81 | $1.00 | $0.90 | $0.82 |
| 86 | THPL PVT MK line 6 (78000400) | LF | 1,650 | $1.22 | $1.22 | $1.22 | $1.70 | $1.45 | $1.30 |
| 87 | THPL PVT MK line 12 (78000600) | LF | 500 | $2.45 | $2.45 | $2.45 | $3.20 | $4.35 | $2.90 |
| 88 | THPL PVT MK line 24 (78000650) | LF | 375 | $5.50 | $5.50 | $5.50 | $7.00 | $8.50 | $6.00 |
| 89 | Remov EX handhole (89502380) | EACH | 1 | $1,200.00 | $1,200.00 | $1,200.00 | $1,400.00 | $1,400.00 | $1,200.00 |
| 90 | Rem EX FB instal comp (89502400) | EACH | 2 | $1,600.00 | $1,600.00 | $1,600.00 | $1,800.00 | $1,800.00 | $1,600.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.
Every contract let that day: IDOT letting of January 16, 2026. Compiled by Mirage Metrics.