IDOT contract 61L66 bid tabulation

East Dundee, section 24-00050-00-RS. Let by Illinois DOT on February 27, 2026, Kane, District 01. 5 bids received; low bid $393,716 by Schroeder Asphalt Services, Inc..

Owner
Illinois DOT
Letting
27 FEB 2026
Pay items
44
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Schroeder Asphalt Services, Inc.$393,716Low
2A Lamp Concrete Contractors, Inc.$394,0730.0%
3Builders Paving, LLC$396,206+1.0%
4Geske and Sons, Inc.$428,991+9.0%
5Everlast Blacktop Inc.$514,039+31%
IDOT contract 61L66: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Schroeder Asphalt Services, Inc.2. A Lamp Concrete Contractors, Inc.3. Builders Paving, LLC4. Geske and Sons, Inc.5. Everlast Blacktop Inc.
1Temp info signing (X7200061)SF52$30.00$20.00$18.00$19.80$30.00
2Tree trunk protection (20101100)EACH1$120.00$250.00$100.00$265.00$350.00
3Tree root pruning (20101200)EACH1$120.00$500.00$100.00$80.00$350.00
4Topsoil F & P 4 (21101615)SY146$2.50$7.75$2.00$6.65$12.00
5Seeding CL 1A (25000110)ACRE0.25$6,000.00$1.00$4,400.00$3,894.00$4,500.00
6Nitrogen fert nutr (25000400)LB23$3.00$1.00$2.00$6.33$2.00
7Potassium fert nutr (25000600)LB23$3.00$1.00$2.00$6.33$2.00
8Erosion contr blanket (25100630)SY146$9.00$3.50$7.00$17.60$6.00
9Agg base cse B (35101400)TON31$68.00$49.00$38.50$40.00$50.00
10Bit matls tack CT (40600290)LB7,094$0.01$0.01$0.01$0.40$0.66
11Long joint sealant (40600370)LF3,054$4.80$3.97$4.50$4.37$4.50
12Mix CR JTS flangewys (40600400)TON15$275.00$375.00$300.00$150.00$900.00
13HMA surf rem butt JT (40600982)SY297$10.00$6.00$25.00$15.50$30.00
14HMA BC IL-9.5 N50 (40602978)TON1,177$85.00$90.00$75.00$88.30$93.00
15HMA SC IL-9.5 D N50 (40604060)TON1,177$85.00$90.00$81.50$91.45$95.00
16PC conc sidewalk 5 (42400200)SF1,498$12.50$8.75$13.50$14.45$15.00
17Detectable warnings (42400800)SF303$48.00$30.00$38.00$40.66$66.00
18HMA surf rem 3 3/4 (44000164)SY10,511$3.50$4.10$5.25$4.14$4.75
19Comb curb gutter rem (44000500)LF372$12.00$7.50$18.50$20.35$12.00
20Sidewalk rem (44000600)SF1,320$3.00$1.60$5.25$5.78$3.50
21CL D patch T2 4 (44201692)SY45$48.00$56.00$55.00$44.60$65.00
22CL D patch T3 4 (44201694)SY61$45.00$45.00$42.00$44.60$65.00
23CL D patch T4 4 (44201696)SY400$42.00$41.00$32.00$44.60$65.00
24Man adjust (60255500)EACH1$900.00$865.00$1,100.00$2,750.00$1,200.00
25Man adj new T1F CL (60255800)EACH3$1,500.00$1,250.00$1,500.00$3,300.00$5,500.00
26Comb CC&G TB6.12 (60603800)LF330$47.00$39.00$50.00$53.00$42.00
27Comb CC&G TB6.18 (60604400)LF42$57.00$68.00$65.00$68.90$45.00
28Mobilization (67100100)LS1$7,500.00$23,000$17,801$17,400$33,000
29TR cont & prot 701501 (70102620)LS1$12,000$14,250$5,000.00$6,710.00$10,000
30TR cont & prot 701701 (70102635)LS1$100.00$1.00$1.00$770.00$2,000.00
31TR cont & prot 701801 (70102640)LS1$100.00$1.00$1,900.00$770.00$3,500.00
32Short term pavt mking (70300100)LF1,222$2.25$0.01$1.75$0.50$6.00
33SHRT TRM pavt MK rem (70300150)SF407$3.00$0.01$0.01$1.00$4.00
34Temp PVT MK LTR & sym paint (70300211)SF53$1.60$0.01$0.50$0.01$10.00
35Temp PVT MK line 4 - paint (70300221)LF3,228$0.55$0.01$0.10$0.01$1.10
36Temp PVT MK line 6 - paint (70300241)LF682$0.85$0.01$0.15$0.01$1.25
37Temp PVT MK line 12 - paint (70300261)LF241$1.60$0.01$0.25$0.01$3.30
38Temp PVT MK line 24 - paint (70300281)LF184$3.15$0.01$0.50$0.01$6.95
39THPL PVT MK LTR & sym (78000100)SF53$6.45$7.00$9.00$6.82$20.00
40THPL PVT MK line 4 (78000200)LF3,228$1.05$1.30$1.00$1.52$1.00
41THPL PVT MK line 6 (78000400)LF682$1.55$1.75$1.50$2.15$1.50
42THPL PVT MK line 12 (78000600)LF241$3.10$3.50$4.50$3.69$3.00
43THPL PVT MK line 24 (78000650)LF184$6.55$7.00$9.00$6.82$6.95
44PVT MKG rem WTR blast (78300202)SF2,077$3.50$0.10$1.50$1.49$2.25
IDOT contract 61L66: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of February 27, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy